1 / 22

Competition and Regulation Interface in Developing Countries: Realities from the Power Sector

Competition and Regulation Interface in Developing Countries: Realities from the Power Sector. By Ama Asantewah Ahene * and Emmanuel A. Codjoe **. *Institute of Statistical, Social and Economic Research (ISSER), Univ. of Ghana, Legon. **Department of Economics, university of Ghana, Legon.

adriel
Download Presentation

Competition and Regulation Interface in Developing Countries: Realities from the Power Sector

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Competition and Regulation Interface in Developing Countries: Realities from the Power Sector By Ama Asantewah Ahene* and Emmanuel A. Codjoe** *Institute of Statistical, Social and Economic Research (ISSER), Univ. of Ghana, Legon. **Department of Economics, university of Ghana, Legon.

  2. Introduction • Growth of Power Generation in Developing Countries • Government’s Quest to Increase Citizen’s Access to Electricity (Power) • Instituting Reforms to Attract Private Participation in the Power Sector

  3. Introduction (cont.) • Controversy of Private Participation in the Power Sector • World Bank’s Push for Reforms in the Power Sector • Review of Institutions and Reforms of the Power Sector in some African Countries

  4. Power Sector Reforms • Implies Commercialisation, Privatisation, Restruction and Competition. • Implies an Alternative Source of Funding for Governments. • However, as at mid-1998 only 39% of Key Reform Steps had been carried out in Developing Countries (World Bank Survey).

  5. Reform Processes • Unbundling – Assigning Existing Costs to Various Components and Developing Prices Based on the Costs • Commercialisation – Government Relinquishes Control to Autonomy and Profitability • Corportisation – Formal and Legal Move from Direct Legal Control to a Legal Corporation with Separate Management

  6. Reform Processes • Competition – Introduction of Wholesale Competition and/or Retail Competition • Privatisation – Transfer of Assets to Private Ownership (This could be part or whole of assets)

  7. Experiences of some Countries in Africa • Some African Countries Bid to Attract Investment in Indebted State-run Utilities • In Nigeria, NEPA is Separated into 18 Companies; Scheduled to be Privatized

  8. Experiences (Cont.) • Government Estimated $1.4Billion investment in each Company for Reliability. • NEPA is Burdened with a debt of $3Billion, Making Privatisation Essential Source of Funding. • Privatisation Scheduled to be Completed by 2005.

  9. Experiences (Cont.) • S.A Power Sector Constituting 43% of the Entire Continents is the Largest • The Sector is State-Owned (Eskom) and Generates most of the Country’s Electric Power • Eskom runs a Coal-Fired Power Plant, Nuclear Power Reactor and Hydroelectric power

  10. Experiences (Cont.) • S.A Government is in the Final Stages of Passing Legislation on Power Sector Reform • 30% of Eskom is scheduled to be offered to Investors by 2006 • Government Plans to also Divest its Distribution Assets

  11. Experiences (Cont.) • Egypt is the Second Largest After S.A • Government began Privatisation Processes in 1998 • Investors to Purchase up to 49% of Egyptian Electricity Holding Company • Also Encouraging Private Companies to Construct Electricity Generating Plants

  12. Experiences (Cont.) • Zimbabwe has Begun the Process of its two Major Electric Power Generating Plants, Hwange and Kariba • Two S.A Firms were Chosen as Finalists to Oversee the Sale of the Two Facilities

  13. Experiences (Cont.) • In Uganda, the Government has Estimated an Investment of at Least $450Million to Reach its Goal of Increasing Electricity Access. • The Country has began Privatisation in an Effort to Attract Foreign Investment in its Electric Power Sector.

  14. Ghana’s Experience • The Power Sector was Institutionalised in the Early 1960s as the Electricity Department • VRA was Established to Supply Power in Ghana • The Akosombo Hydro-Electric and the Kpong Hydro-Electric Dams were Constructed

  15. Continuation… • Electricity Corporation of Ghana in 1967 • Under the Provisions of the Statutory Corporations Act, 1993 (Act 461), ECG has since 1997 become a Limited Liability Company called Electricity Company of Ghana.

  16. Regulatory Institutions • The Public Utilities Regulatory Commission (PURC) was established under Act 538 to make Regulations Concerning Utilities • The Energy Commission was also Set up under Act 541 to Work with PURC in Developing Performance Standards.

  17. Power Sector Reforms • Due to Growing Demands and Constraints; Difficulties with Traditional Financing Sources in the Power Sector • World Bank’s Guiding Principles of Transparent Regulations, Commercialisation and Corporatisation, Commitment Lending and Private Investment

  18. Reforms (cont.) • The need to Expand the Existing Capacity and to Attract both the World Bank and Private Investors Forced GOG to start the Sector Reforms. • Ghana would not have started the Reforms if the World Bank had Provided Needed Funds for a Thermal Plant without Insistence on the Reforms (Edjekumhene et al., 2001).

  19. Policy Objectives • Enhancing Transparency • Effecting Structural Changes • Encouraging Private Sector Investment • Minimising GOG Sovereignty • Establishing a Regulatory Framework

  20. Proposed Power Sector Structure • Allow Free Entry to both the Generation and Distribution Levels • Transmission System would be Opened to every Generator • An Economic Load Dispatch Centre would be Created • Generators would Supply Distributors at Regulated Price • Several Distributors would Exist and Compete

  21. Conclusion • Although no Specific Time Frame has been Set by GOG to carry through with the Reforms towards Competition, Significant Inroads have been Made in Terms of Regulations • There are however Impediments that GOG has to Overcome for Smooth Implementation of its Power Sector Development Objectives.

  22. THANK YOU

More Related