Design for Manufacture and Assembly

Design for Manufacture and Assembly. ME 475/476 Some slides in this presentation have been provided courtesy of Emeritus Professor, Dr. Perry Carter, School of Technology at Brigham Young University. Schedule. Assignments.

angeni
Download Presentation

Design for Manufacture and Assembly

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Design for Manufacture and Assembly ME 475/476 Some slides in this presentation have been provided courtesy of Emeritus Professor, Dr. Perry Carter, School of Technology at Brigham Young University

  2. Schedule

  3. Assignments

  4. What Would you Like to Learn About Design for Manufacture & Assembly (DFM/DFA)?

  5. Important Considerations in Product Design • Functionality • Safety • Appearance • Weight • Maintainability • Recyclability • Reliability • Manufacturability • ….

  6. What is the Cost of a Product?

  7. Reduced Production Costs

  8. Four Activities of Manufacturing • Changing the shape of materials • Changing the properties of materials • Assembling materials (as component parts) • Creating or organizing the tools, machines and systems to make the first three mf’g. activities happen

  9. We can Make Anything, Right?

  10. Engineering isa PeopleProfession

  11. “Nowhere in a company is the need for coordination more acute than between the people who are responsible for product design and those responsible for manufacturing.” Harvard Business Review

  12. A Very Helpful Book

  13. The Cost of Design Changes… Time of Change Relative Cost $1 $10 $100 $1,000 $10,000 • During Concept selection and early stages of product & process design • During design testing • During process testing • During test production • During final production

  14. Improving Manufacturability • The single most important principle to improving manufacturability is to want to • The second most significant principle to improving manufacturability is to do it in the early stages of design • A third important principle is to seek to learn from others • A significant additional guideline for improving manufacturability is to strive for Simplicity! • Reduce the number of parts • Reduce tolerances • Use standard parts whenever possible • Reduce number of fasteners & adjustments

  15. Manufacturability (Cont’d) • Seek to learn about the capabilities and limitations of manufacturing processes, equipment, and materialsbeforeyou design the product. • Consider preferred vs. nonpreferredprocesses and materials • Consider manufacturing cost targets for the different parts of the your product

  16. What is DFMA? DFMA (Design for Manufacturability and Assembly) is a structured method for comparingalternative product designs with respect to manufacturability These comparisons are usually based on cost or time…

  17. What are the benefits of DFMA? • Improved communication and decision making • Earlier and fewer design changes • Improved Quality • Reduced production costs • Shorter time to market • Increased market share and profits…

  18. One Example…

  19. Three principle parts of the Porsche manifold Two A’s and one B make up one C

  20. Designing for the Process

  21. Mf’g. Processes Reference Guide • Breaks 125 mfg. processes into three categories: • - Knowledge • - Application • Development • Defines, explains each process • Encourages integration of design and manufacturing to yield better designed products

  22. What Mfg. Process Should I Use?

  23. Tight Tolerances Cost Money! Ken Forester has prepared a nice handout to get you started…

  24. Designing for the Process: Example Ford Air filter cover, initial release

  25. Designing for the Process

  26. Designing for the Process Ford air filter cover after redesign

  27. Design for Assembly • What does DFA accomplish? • What are the basic assembly tasks? • What are the cost drivers associated with these assembly tasks? - Reduce cost!

  28. What are basic assembly tasks? • Handling • Grasping, separating from bulk, orienting… • Insertion • Aligning, engaging, inspection • Fastening • Clamping, threading, plastic deformation, adhesive, etc.

  29. Some Tips… • Design so the Assembly Process can be completed in a layered fashion – preferably from above • Consider easy part handling • Design mating parts that are easy to insert and align • Avoid part designs that will cause tangling with identical parts • Make parts symmetrical to aid in automatic orientation • If symmetry can’t be achieved, exaggerate the asymmetrical features…

  30. Part Handling Effect of Part Size on Handling Time

  31. Part Tangling

  32. Spring Tangling

  33. Insertion Effect of Chamfers

  34. Insertion

  35. Example of Obstructed Access

  36. Alignment

  37. Assembly Time Example

  38. 3. Fasteners

  39. Fastener Costs… • Number; type • High assembly time • Quality may be poor • Higher quality is expensive • Prone to assembly errors • Cost of inventory

  40. Other Methods of Fastening

  41. What is the Cost of Inventory? • Documentation • Inventory space • Inventory cost of h’wd. • Shipping • Incoming inspection • Vendor relations • Vendor qualification • Part certification • Failure replacement Lucent Technologies reports it costs$15,000/year to maintain one electronic part certification and $150,000 for a new part

  42. Product Reliability Improvement Product reliability, that is mean time between failures (MTBF), is inversely tied to part count!

  43. Proof-of Concept vs. Prototype

  44. Watch for Over-Constraint in Design

  45. Avoid Adjustments…

  46. What constitutes a theoretically necessary part? Identify parts that don’t meet theoretical criteria for being separate parts…and eliminate them if possible • Motion • Material • Access

  47. Motion 1.  During the normal operation of the product, does this part moverelative to all the other parts already assembled?

  48. Material 2.   Must this part be of a different material than all the other parts already assembled? (Reasons should be based on fundamental, properties of the material such as electrical conductivity, thermal conductivity, vibration damping, hardness, modulus, etc.)

  49. Access 3.   Must this part be separate from all other assembled parts to allow the assembly of other theoretically necessary parts. This could involve parts that must pass through an opening requiring a door, cover, lid etc. that must be removable to allow assembly of other internal parts.