1 / 12

Status Report on Bonding at Catania

Status Report on Bonding at Catania. Salvatore Costa University and INFN – Catania. Bonding Test # 2. Would like to hear from Karslruhe : test results loop height measurement ( 150 m m or .1 mil ?). Bonding Jig. Have from Filippo Bosi, Pisa, both…

carr
Download Presentation

Status Report on Bonding at Catania

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status Report on Bonding at Catania Salvatore Costa University and INFN – Catania

  2. Bonding Test # 2 • Would like to hear from Karslruhe: • test results • loop height measurement (150 mm or .1 mil ?)

  3. Bonding Jig • Have from Filippo Bosi, Pisa, both… • “Type 1” jig for top side of TIB modules • “Type 2” jig for back side of TIB modules

  4. Test Systems • The recently identified person in charge of ARC has installed it, but the system is not yet fully operational. • CMS-like is fully operational.

  5. Bonding Lab Evolution • We are in the process of moving to a new Physics Department Building. Clean Room will be dismissed sometimes between Aug and Sep and relocated. • In the new location we plan to deploy both Hughes (2nd one from CERN).

  6. Dummy Module Bonding • Received a dummy module assembled partly in Perugia and partly in Bari with 2 CSEM sensors • Module was shipped via DHL courier service • Sensors were found broken (see picture) We believe it happened in transit • Sensor and many a pad surfaces were scratched • High ridge of glue between the 2 Sensors • Wire won’t stick to most SEN-SEN pads • PA-SEN bonding to be attempted next week

  7. Broken Dummy Module

  8. Real Module Bonding • A technician went to Bari last Friday to pickup our first real module • Bonding to be attempted next week, right after dummy

  9. …break…

  10. DataBase Interface Update Salvatore Costa University and INFN – Catania

  11. Interface Dev Status • I’m still working on Version 0.2: • Working version: • Exercise all functions • Will include User’s Manual • Includes people’s comments to v. 0.1 • Center specific defaults and lists (where available) • All data stored in Catania sunct.ct.infn.it/bondingdb/v0.2 (work in progress) • I have prepared the tables and plan to submit them to Didier soon (I’m just tring to make variable names consistent across different tables)

  12. Center “DB Readiness”