Small Scale Projects – Learning from the CDM Paul Soffe

Explore the concept and advantages of small-scale projects in the carbon market. Learn about a dedicated facility providing CERs from small-scale projects and the key factors for their success. Case studies highlight lessons learned and innovative approaches in Honduras and the Philippines.

cirillo
Download Presentation

Small Scale Projects – Learning from the CDM Paul Soffe

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Small Scale Projects – Learning from the CDMPaul Soffe

  2. Small-scale Facility Concept • A dedicated facility providing buyers with CERs from small-scale projects • Facility participants structure their requirements, specifying: • Project type / Countries / Fixed price • Current buy orders from Government of Austria and Japan Carbon Finance • EcoSecurities sources all projects • Direct sourcing + global network • eg. E+Co joint venture (2E Carbon Access) • EcoSecurities prepares all project documentation • PDD, M&V plan etc. • Arranges validation with a DOE • Coordinates and oversees monitoring, verification and issuance • All project developer costs are covered by the facility • PDD, Validation, Registration • Only cost to developer is verification and annual Share of Proceeds after CERs are produced • Track-record – Small-scale Facility has registered 5 projects under CDM. One has issued CERs.

  3. Facility Structure Project #1 Master ERPA Buyer – Govt of Austria and JCF EcoSecurities Project #2 Project #3 Project #4 Individual ERPAs Project #5

  4. Key issues for SSc Project Success under carbon mechanisms • Minimise costs– all costs related with CDM project development, including third party costs for validation and registration have to be minimised • Simplicity - all documentation standardized • Speed – entire process process cannot be too long, SSc developers have limited budgets (time and cost) • Expertise – SSc need access to assistance with process • Financial value-added – prices for ERUs (CERs) for smallest project may need to be higher • Track-record – Demonstrating that JI SSc can work with the rapid approval and development of the first projects is very important

  5. Advantages for Buyers • Small-scale projects with high sustainable development benefits; • High-quality projects that have received business development services, thorough due diligence and assistance reaching financial closure – more likely to reach CER delivery targets; • Projects that have advanced through the CDM Development Process – PDD completed, validated, or registered; • Low transaction costs and high efficiency; and • Optimum equilibrium between high quality project assessment and low transaction costs. • Track-record: Small-scale Facility has registered 5 projects and 2 pending. One has received CERs.

  6. Case Study: La Esperanza Hydroelectric Project • Location: Western Honduras • Project type: Hydroelectric • Installed Capacity:12.73 MW • CO2e per year: 37,031 tons • CER buyer: World Bank • Current Status: Issued CERs • Lessons learned: • Partnerships • Engage with DNA early in the process • Additionality: include early • Start Early

  7. Case Study: Pig projects in the Philippines • Case Study: Small-scale pig projects • Location: Philippines • Project type: Anaerobic Digestion • Installed Capacity: 150 kW each • CO2e per year: 1,500 to 10,000 tons • CER buyer: Austria, JCF, and EcoSecurities • Current Status: Final validation • Lessons learned: • Difficult to keep transaction costs low • Economies of scale possible over time • Methodologies + data availability • Validation costs high

  8. Case Study: Hydro in Honduras • Case Study: Cuyamapa Hydroelectric Project • Location: Western Honduras • Project type: Hydroelectric • Installed Capacity:12.20 MW • CO2e per year: 38,552 tons • CER buyer: EcoSecurities through Austrian Facility • Current Status: 1st Registered Unilateral Project • Lessons learned: • Engage with DNA early in the process • Unilateral Project

  9. Lessons Learned • Bundles of SSc projects an attractive option for buyers to secure a number of projects • Under CDM rules it was possible to develop a large pipeline of projects for the Facilities • Uncertain what problems may be encountered during moniotirng, certification, and issuance stages • Other problems unrelated to CDM Executive Board • price expectations and forecast for CERs • host country approval can take a long time

  10. Conclusions • Make system for SSc projects as simple as possible to reduce transaction costs associated with carbon related aspects of project development • Any charges for by JISC must be kept low • Specify as much of JI cycle in detail ASAP. Clarity is important in building confidence that JI is workable • Do not re-invent the wheel • Utilise CDM baseline meths & additionality tools of SSc • Are any specific meths needed for JI SSc in addition to CDM meths (I do not know). If so develop them – SSc developers will not and cannot (they are by default relatively poor)