1 / 7

PROJECT : IGEM 2016 REPORTING PERIOD : 30/03/2016 – 30/4/2016

Off – serious help needed. PROJECT : IGEM 2016 REPORTING PERIOD : 30/03/2016 – 30/4/2016. Off - attention. On track. Source of Fund: KeTTHA Project Fund: KeTTHA (RM3,480,00million) Fund Utilisation :. Flagship: Green Promotion Project Director: Syireen Rose Project Manager: -

gracek
Download Presentation

PROJECT : IGEM 2016 REPORTING PERIOD : 30/03/2016 – 30/4/2016

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Off – serious help needed PROJECT: IGEM 2016REPORTING PERIOD: 30/03/2016 – 30/4/2016 Off - attention On track Source of Fund: KeTTHA Project Fund: KeTTHA (RM3,480,00million) Fund Utilisation: Flagship: Green Promotion Project Director: Syireen Rose Project Manager: - Project Leader: - Project Background • Organiser: KeTTHA, Co-organizer: GreenTech Malaysia & Strategic Partner: MES • The region’s largest green technology and eco products exhibition • Size – 500 to 600 booths • Theme – Green Business for Sustainability • First inception in 2010 & this is the 7th edition Objective • Provideplatform for stakeholders to showcase GT development and generate commercial opportunities for GT • Promote green purchasing / procurement & greening the supply chain and facilitate establishment of green standards, certification & legislation. • To accelerate the development of eco-prenuership & green economy and encourage partnerships & technology transfer in GT. • To make Malaysia as the green hub for Green Technology by bringing in exhibitors globally. Status (%) • *On going • *On going • Booth Sales 17 from 400 ( 4%) Expected Outcomes • Business leads of RM1.5 billion; • Visitorship 30K; • To achieve sales of booths of least 300 exhibitors. Future Business Potential: • Profit from Sales of booth for 2016 expected to be approximately RM1.5mil, we could achieve more if wecreate more strategic alliances with the industry in future years. • To make the conference as a profit-making platform by creating industry relevant content with strategic partners.. Revision 1.0

  2. PROJECT: IGEM 2016REPORTING PERIOD: 30/03/2016 – 30/4/2016 HIGH LEVEL GANTT CHART Revision 1.0

  3. PROJECT: IGEM 2016REPORTING PERIOD: 30/03/2016 – 30/4/2016 Activities Completed (During reporting period) • Matrade Meeting Complete. Waiting on Proposed List Potential Business Traders. • Meeting with Federal Authority AmateurAthletic Association for Fun Run Complete. • 2 Proposal for OC received. • Letter to invite Water Association Malaysia And Waste Association Malaysia Sent. • Final details of MPIA and MGTC Conference Contract 90% Completed. • JCI CSR Golf Collaboration pending proposal from JCI Lead Tropicana Activities Planned (For next reporting period) • Meeting with MYCEB • Updates on Investor Meet in India • Contract Status for IGEM • Updates on Opening Ceremony • GreenTech Pavilion • Proposal from AXA Affin Insurance Run • Meeting with JCI Lead Tropicana to finalized Gold Tournament • Finalize and execute A&P Revision 1.0

  4. PROJECT: IGEM 2016REPORTING PERIOD: 30/03/2016 – 30/4/2016 Photos of activities (During Reporting Period) • Challenges • Internal: • Limited resources • Synching calendars of events with other VPs to align message for IGEM • Actions or support needed • Internal: • Sharing and updates from VPs that IGEM can leverage for awareness and publicity purposes • External: • Budget allocation from KeTTHA took sometime for confirmation. External:

  5. PROJECT: IGEM 2016REPORTING PERIOD: 30/03/2016 – 30/4/2016 Financial

  6. PROJECT: IGEM 2016REPORTING PERIOD: 30/03/2016 – 30/4/2016 SYIREEN ROSE (Project Director) (Project Leader) FARAH NIJIDA (Team Member) MOHD FAIZ (Team Member)

  7. PROJECT: IGEM 2016REPORTING PERIOD: 30/03/2016 – 30/4/2016 Status Economic • Team up with MIDA ,Matrade & Might for Business Matching. • Confirmation of MyHijau Pavilion in hall 1 to showcase Green Product. Environment • Invite participation from Association that related on industry, Water Association,Waste Association and MPIA Social • Plan to participate in a AXA Affin Insurance Run on September as CSR Partner to create BUZZ on IGEM Expected Impact (2016) Economic • Creating business opportunities for “Green” technology • Green procurement will be advanced in Malaysia Environment • Increase in the creation of green technology for industries with the greatest environmental impact • Increase demands for greener products and services from market to producers Social • Creating the awareness on Green Technology • Enhance the interest among public to understand the market of Green in Malaysia. Revision 2.0

More Related