1 / 60

GNIRS Quarterly Review August 15, 2000

GNIRS Quarterly Review August 15, 2000. Overview. Project management Systems engineering Optics design and fabrication Mechanical design and fabrication Electronics design and fabrication Software Procurement Images. Project Management. Project Management. Project Summary

kalb
Download Presentation

GNIRS Quarterly Review August 15, 2000

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GNIRS Quarterly Review August 15, 2000

  2. Overview • Project management • Systems engineering • Optics design and fabrication • Mechanical design and fabrication • Electronics design and fabrication • Software • Procurement • Images

  3. Project Management

  4. Project Management • Project Summary • Review Committee Concerns and Responses • Status and Plans • Problems and Concerns • Planning • Milestones, Cost and Manpower • Budget and Expenditures to date • Organizational Changes

  5. Project Summary • Current activities • Prototyping • Bench design and analysis • Mechanism design • Mechanism fabrication • Electronics design • Software coding • Prototyping • Optical, Rotary and Linear Prototyping effort is complete • Enough data collected to justify proceeding with mechanism design • Bench design and analysis • Bench deflection analysis is complete • The manufactured bench should meet deflection requirements • Bench drawings will go to vendors this week for fabrication bids • Bench fabrication is scheduled to start with the OIWFS bench on 9/5/00 • All benches scheduled for release for fabrication by 9/29/00

  6. Project Summary • Mechanism designs in process • Filter wheel assembly • Starting 2D detailing • Camera turret assembly • Two of 4 camera barrels through 3D solid model design • This work is currently on hold • Camera drive and hub in 3D design • Key design element requiring some development testing • Results will be propagated to the Grating and Prism Turrets • Acquisition mirror assembly • 2D design, currently on hold • Focus mechanism assembly • 3D design starts on August 15 • Slit/Decker assembly • 2D detailing in process

  7. Project Summary • Mechanism fabrication • Environmental cover assembly • Motor drive assemblies • Camera turret assembly • Some parts in fabrication • Electronics design • Mechanism and dewar functional simulator • For software debug and checkout • Dewar and mechanism wiring definition • Array interface wiring definition • TE wiring design • Software coding activity • Components controller • System software (thin EPICS layer)

  8. Review Committee Concerns and Responses • It is premature to assume that the aggressive 0.1 pixel flexure per 15º attitude change specification will be met by this design. • The bench analysis presented here predicts low image degradation due to flexure of the pre and post slit bench structures. • Further develop the fall back plan of active flexure compensation. Identify an optimal compensator in the system. Determine if adequate space/mass budget is available to retrofit a mechanism. • A fall back plan has been adopted, namely correction at the collimator (as suggested by Tom O'Brien). We are not pursuing the implementation unless and until evidence shows it is needed. • Consider running ultimate lifetime tests using the prototypes. • We have decided not to run the lifetime tests on the prototypes, on the ground that the prototypes are not representative enough of the real mechanisms for the tests to be helpful. We have carried out inspections on the mechanisms (disassembly) and have seen no wear problems for use that represents >10% of a "lifetime".

  9. Review Committee Concerns and Responses • Go straight to rotary prototype #2. • We are working on the camera turret design, with the idea that it is not a prototype. We are accelerating fabrication and test of the camera hub to ensure we have time to detect and remedy and deficiencies. • There is no need for additional prototype testing of the lens mount. We recommend contacting Klaus Hodapp to understand what difficulties he has had with this design. • We have finished these tests and are proceeding. Klaus's design is somewhat different. • If NOAO wants to pursue the idea of IfA installing elements in this module and testing it as a unit, that should be explored quickly. • We are pursuing this. Klaus wants to see how NIRI does at the telescope before proceeding much further. • Consider the use of invar bushings on the bolts that “permanently” connect parts of the main bench. • We are following this suggestion.  We are incorporating partially compensating collars in the bench design.

  10. Review Committee Concerns and Responses • We expect that the (software) architecture described will meet existing ICDs and support all key functionality. (The software) must conform to all principal system interfaces. • We acknowledge these comments and are proceeding accordingly. • Clarify what will be delivered in the (software) engineering system. • At this time, we do not envision delivering a system which would require any special software licenses. It may be desirable to use an improved version of the EPICS display manager, or to incorporate some new TCL code. However, we will neither deliver nor require any software that is not a part of the standard Gemini environment without approval from Gemini. • Thoroughly document the S/W that operates below the proposed “thin EPICS layer” to permit long-term support. • The software maintenance manual manual will contain a thorough documentation of the software.

  11. Review Committee Concerns and Responses • Rectify the discrepancy between CAS and Neil’s costs, by reporting in real dollar values. Specifically, reconcile the difference between accounting for scientists’ time between the cost schedules maintained. •  We are struggling to do this. We have subtracted out all scientist labor charges from our planning to better reflect what the actual charges represent. We are still working with CAS on a more permanent solution. • Release some parts for fabrication to (1) test the entire off-site fabrication process with a vendor and (2) stimulate a change in the psychology of the team, from one of only designing to actually building the instrument. • The prototype fabrication was intended to "test the process". We are releasing parts as ready and have completed the environmental cover. • Use an engineer independent of the GNIRS team to double check drawings that depict key interfaces between the main bench and mechanisms and optical assemblies. • We have effectively done this using our “new” mechanical engineer. Also, one of the points of the 3-D modeling is to avoid the dependence on building up the ray-trace from individual drawings.

  12. Statement of Work to IFA for OIWFS integration and test • Install all OIWFS components onto the provided optical bench. • This bench is especially designed to receive the Gemini provided components and to fit into the GNIRS Instrument. • Perform a mechanical and optical alignment of these components. • Connect and test the OIWFS using the actual electronics and boards that will be delivered to the GNIRS Project. • Checkout and test the integrated OIWFS as a subsystem • IFA is uniquely qualified to do this work • IFA possesses the needed test cables, equipment and software needed to do this work. • Conduct an acceptance test which will demonstrate basic operation of the OIWFS as a subsystem, preferably in a vacuum and at representative cryo temperatures which will be seen in actual operation. • Pack and ship the completed OIWFS subsystem in a suitable shipping container to the GNIRS Project at NOAO, Tucson.

  13. Plans for Next Review • The Next Quarterly Review will be held in the November-December timeframe. • The project expects to make significant progress in fabrication. • All benches should be to vendors • Several mechanisms will be in fabrication • 3D designs of all remaining mechanisms will be complete • Focus, prism turret, grating turret, camera assembly, acquisition mirror • Lens delivery should be complete; all optics on order/delivered • Work will have started on several fixed assemblies • Electronics fabrication will have started • OIWFS components integration will be underway

  14. Status and Plans • The project is 29% complete overall • We have completed 29 of 208 scheduled milestones • The planned Systems Engineering effort is 97% complete • Software low-level code development is 56% complete • Mechanism design is underway for several mechanisms • Procurement of optics, mirrors, filters, gratings, materials, etc., is proceeding per plan • Currently qualifying additional vendors for outside fabrication

  15. Progress from August ’99 Overall project 29% Management & Reporting 35% Systems Engineering 97% Mechanical 16% Benches 16% Mechanisms 24% Fixed Assemblies 1% Electronics 4% Software 27% Integration 0% Procurement 31% Status and Plans

  16. Problems and Concerns • Bench solid models and details for fabrication • Contracting for bench fabrication • Contractor selection • Work start and schedule/cost • Aluminum billet cutting & distribution • Complete by 9/5, start of vendor fabrication • Electronics technician shortage • The software effort is outpacing the electronics build schedule needed to support software checkout.

  17. Project Planning

  18. Summary Plan

  19. Project Plan

  20. Critical Path • There is no one assembly on the critical path • We review the schedule on a continuing basis • critical path changes as a function of time • We periodically adjust priorities and resources

  21. Fabrication Schedule

  22. Project Milestones

  23. Milestones by Quarter

  24. Milestones since PFR

  25. Project Costs

  26. Project Costs • Baseline Estimate (Jan 99 to completion) • Labor $3,391,232 • Capital $ 836,462 • Total $4,227,694 • Current Forecast (revised 7/31/00) • Labor $3,309,187 • Capital $ 877,842 • Total $4,187,029 • Performance ratios • BCWS = $ 1,181,581 (budgeted cost of work scheduled) • BCWP = $ 816,464 (budgeted cost of work performed) • ACWP = $ 846,211 (actual cost of work performed) (source: CAS) • CPI = 0.96 (BCWP/ACWP) • SPI = 0.69 (BCWP/BCWS)

  27. Project Costs This report is given to Gemini monthly.

  28. GNIRS WBS • WBS Elements shown to 3rd level

  29. Planned vs Actual Expenditures WBS Title Total Planned Actual Plan to date to date 5.0 GNIRS Total $3,752,409 $928,845 $888,283 5.1 Management $1,148,014 $285,982 $281,710 5.2 Systems Eng $ 225,686 $213,472 $236,524 5.3.1 Mechanisms $ 904,104 $238,409 $196,130 5.3.2 Bench Assemblies $ 301,081 $ 50,915 $ 50,393 5.3.3 Fixed Assemblies $ 501,174 $ 13,800 $ 9,852 5.4 Electronics $ 150,014 $ 4,135 $ 11,586 5.5 Software $ 95,122 $ 40,291 $ 27,161 5.6 Integration $ 201,960 $ 0 $ 0 5.7 Deliverables $ 37,164 $ 0 $ 0 5.8 Procurement $ 188,090 $102,469 $ 95,364

  30. $800,572 $759,192

  31. Director, NOAO S. Wolff Project Assistant D. Eklund (.5) Project Scientist, Systems Engineering J. Elias Gemini Projects Project Manager N. Gaughan Administrative Assistant M. Bowersock Mechanical Engineers E. Hileman G. Muller Electrical Engineer J. Penegor Optical Engineer M. Liang Procurement & Vendor Liaison A. Davis Software R. Wolff Staff Added: No changes Staff Transferred: No changes Support Scientists D. Joyce* B. Gregory** Mechanical Designers J. Andrew D. Rosin E. Downey R. Robles Electrical Technicians S. Nguyen Organization

  32. Systems Engineering

  33. Systems Engineering • Two Main Areas: • Analyses • Thermal analysis (completed 5/00) • Flexure analysis (completed 8/00) • Prototyping • Motor testing (completed 12/99 [report 5/00]) • Lens mount tests (completed 5/00) • Rotary prototype (completed 7/00, except final report) • Linear prototype (completed 8/00, except final report)

  34. Analyses • Thermal Analysis • Thermal design presented 5/00 • Additional analysis as required in support of design (not systems engineering - e.g. wire cold-station details) • Structural Analysis • Flexure analysis interacts with bench design • Specific analyses were used to support prototype design • Prototype results confirm mechanism analyses • Additional structural analysis in support of design (e.g, dewar shell) • Flexure Analysis Results • Bench appears to perform adequately • XY control could be implemented at collimator

  35. New Prototype Results • Rotary Prototype Final Results • Drive mechanism meets repeatability, torque, wear specifications • Pre-load redesigned to meet flexure specifications; early testing of most demanding implementation (camera) to confirm performance • Linear Prototype Final Results • Multiple design changes - either tested or straightforward • Drive mechanism will meet repeatability, torque, wear requirements • Motor isolation mount meets requirements (<10% of heat into structure) • Mechanism will meet flexure requirements • Design Changes Implemented

  36. Optics Design and Fabrication • Lenses and Windows • large lenses & windows in fabrication with RMI; 11 of 18 accepted • small lenses (2) will be fabricated by RMI • Mirrors • Powered mirrors (3) delivered by II-VI (accepted); Alumiplate surface delivers required low scattering (<40Å rms, require 50Å) • Flat mirrors to be ordered as individual mechanism design proceeds; 2 aluminum substrates & 7 glass substrates • Gratings • Master rulings (3) completed and measured • Replicas will be done when turret 3-D design nears completion • Filters • 7 filters ordered through UH consortium; 2 fail spec and should be replaced • Prisms • Preliminary quotes on prisms; will initiate procurement once 3-D design of prism turret nears completion (9/00)

  37. Mechanical

  38. Mechanical • Overview • Work in the Mechanical WBS element has primarily concentrated on the bench structures, mechanisms and mechanism interfaces to the benches • Starting August 15th we will finish mechanism 3D design definition in order to release the benches for fabrication • This will include the focus, grating turret, and prism turret mechanisms • Bid packages for the three benches will be released to four vendors and our own Instrument Shop in the week of August 14th

  39. Mechanical Design and Fabrication • Mechanical design • Bench detail design • Pre-slit, Post-Slit, OIWFS benches • Mechanisms • Filter wheel • Camera barrels • Camera hub assembly • Slit/Decker assembly • Mechanical fabrication • Environmental cover assembly • Motor drive assembly • Bench assembly bid packages

  40. Problems and Concerns • Fabrication times are internal estimates • Actual fabrication times for the benches is an unknown at this time • We will use multiple vendors to insure that mechanical fabrication supports our schedule commitment. • Multiple vendors and in-house fabrication may affect the estimates

  41. Electronics design and fabrication • Design activities • Mechanism Motor Simulator for software testing • Dewar, mechanisms and WFS cabling • Fabrication • The software simulation tool is fabricated and ready for test/checkout. • Fabrication of the deliverable electrical hardware will start in September.

  42. Software • Software is under control • Not on the critical path. • The software schedule includes a several month period, for test and debug using the real electronics, prior to going into the project integration phase. • Status • Low level (Component Controller) code 56% complete • High level (EPICS) code 5% complete

  43. Procurement Status • Optics Status • RMI – 8 Parts left including two pupil viewers • Filters – Received 6 of 7 Filters • 3 Master Rulings Have Been Ordered • Benches • All 3 benches out for bid this week • Future procurement • Flat Mirrors • Prisms • CRYO Heads/Lines • Electronics connectors/boards