1 / 12

Project Management

Project Management. Planning Techniques Project manager responsible for developing project implementation plan. Duties includes: Defining tasks Making estimates (cost and timing) Preparing schedules Preparing budgets. Project Management. Recall the house construction example:

kmaas
Download Presentation

Project Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Management Planning Techniques Project manager responsible for developing project implementation plan. Duties includes: • Defining tasks • Making estimates (cost and timing) • Preparing schedules • Preparing budgets

  2. Project Management Recall the house construction example: Task Definition: DescriptionDuration(days)Precedence Step A: Prepare site. 5 - Step B: Build foundation. 8 A Step C: Frame walls and roof. 15 B Step D: Rough in Plumbing 12 C Step E: Rough in Electrical 10 C Step F: HVAC Venting 8 C Step G: Drywall 11 D,E,F Step H: Finish Electrical 5 G Step I: Finish Plumbing 4 G Step J: Finish HVAC 2 H Step K: Install Kitchen 8 H,I Step L: Install Baths 14 H,I Step M: Paint 5 J,K,L Step N: Landscape 5 J,K,L

  3. Project Management Precedence Diagram Tasks must sometimes be performed in series, or may at times be performed in parallel. For the house example, let each arc represent a project task/job. Each arc is identified by a job letter and duration. Note the dummy jobs indicating precedence that jobs H and I must complete before K or L begins. J,2 H,5 7 M,5 D,12 K,8 0 A,5 B,8 C,15 G,11 E,10 11 1 2 3 4 5 6 9 10 0 L,14 N,5 F,8 I,4 8

  4. Project Management Timing – Gantt Chart Tasks and task durations are often represented as Gantt Charts. With task precedence knowledge.

  5. Project Management Critical Path J,2 H,5 7 M,5 D,12 K,8 0 A,5 B,8 C,15 G,11 E,10 11 1 2 3 4 5 6 9 10 0 L,14 N,5 F,8 I,4 8

  6. Project Management • Exercise – Task Definition • Define tasks, duration and precedence for the Term Project. • DescriptionDuration(days)Precedence • Form teams and select leader 1 -

  7. Project Management Exercise – Precedence Diagram Create precedence diagram for the Term Project, and identify critical path. A,1 1 2

  8. Project Management Exercise – Schedule/Gantt Chart Create a schedule in the form of a Gantt chart for the Term Project.

  9. Project Management • Exercise – Cost Estimation / Resource Allocation • Estimate cost and define/allocate resource requirements for the Term Project. Note, your costs will be in time not $’s. • DescriptionCostResources • Form teams and select leader .25 hours All

  10. Expediting/CrashingCPM – Critical Path Method • Can normal task times be reduced? • Is there an increase in direct costs? • Additional manpower • Additional machines • Overtime, etc… • Can there be a reduction in indirect costs? • Less overhead costs • Less daily rental charges • Bonus for early completion • Avoid penalties for running late • Avoid cost of late startup • CPM addresses these cost trade-offs.

  11. CPM – Critical Path Method Example: Overhead cost = $5/day

  12. CPM – Critical Path Method Enumerative Approach: Reduce job H by 1 day: Total Cost improves by $5 - $4 = $1. Reduce job A by 2 days: Total cost improves by $10 - $8 = $2. Reduce job A by an additional day, and job B by a day? Total cost improves by $5 - $4 - $2 = -$1. Therefore do not take this action. Reduce job A by an additional day, and job C by a day? Total cost improves by $5 - $4 - $2 = -$1. Therefore do not take this action. Evaluate combinations of reducing path 3-4-6 and 3-5-6 by one day. D & E = $5 - $3 - $3 = -$1 F & E = $5 - $5 - $3 = -$3 D & G = $5 - $3 - $1 = $1 F & G = $5 - $5 - $1 = -$1 Therefore, reduce job D & G by 1 day: TC improves by $5 - $3 -$1 = $1. Overall improvement: $1 + $2 + $1 = $4.

More Related