Current RMGRR Timeline

Current RMGRR Timeline. 6/6/2006 ERCOT posts the TAC Action Report. Effective Date 7/1/2006 or as otherwise specified by TAC. 3/15/2006 MP submits a new RMGRR. 3/22/2006 ERCOT posts the RMGRR. 5/15/2006 ERCOT posts the RMS Recommendation Report. 21 calendar days comment period.

lynton
Download Presentation

Current RMGRR Timeline

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Current RMGRR Timeline 6/6/2006 ERCOT posts the TAC Action Report Effective Date 7/1/2006 or as otherwise specified by TAC 3/15/2006 MP submits a new RMGRR 3/22/2006 ERCOT posts the RMGRR 5/15/2006 ERCOT posts the RMS Recommendation Report 21 calendar days comment period 5 Business Days comment period 5/10/2006 RMS consideration 6/1/2006 TAC consideration

  2. RMGRR Timeline (RMGRR033) (no system impacts) Effective Date 8/1/2006 or as other wise specified by the TAC 3/15/2006 MP submits new a RMGRR 3/22/2006 ERCOT posts the RMGRR 5/15/2006 ERCOT posts the RMS Recommendation Report 7/11/2006 ERCOT posts the TAC Recommendation Report 5 Business Days comment period 21 calendar days comment period 7/6/2006 TAC consideration 6/14/2006 RMS reviews the Impact Analysis 7/18/2006 TAC Chair reports approved RMGRR to the BOD 5/10/2006 RMS consideration

  3. RMGRR Timeline (RMGRR033) (system impacts) 6/27/2006 ERCOT reposts the RMS Recommendation Report including PRS vote Effective Date 9/1/2006 or as otherwise specified by the BOD 7/11/2006 ERCOT posts the TAC Recommendation Report 3/15/2006 MP submits new a RMGRR 5/15/2006 ERCOT posts the RMS Recommendation Report 3/22/2006 ERCOT posts the RMGRR 5 Business Days comment period 21 calendar days comment period 6/14/2006 RMS reviews the Impact Analysis and CBA 6/22/2006 PRS recommends a priority for all projects 7/6/2006 TAC consideration 8/15/2006 BOD review 5/10/2006 RMS consideration

  4. Urgent RMGRR Timeline (RMGRR033) (no system impacts) 3/22/2006 ERCOT posts the RMGRR 3/15/2006 MP submits new a RMGRR 4/3/2006 ERCOT posts the RMS Recommendation Report 4/12/2006 ERCOT posts the TAC Action Report Effective Date 5/1/2006 or as otherwise specified by the TAC 3/27/2006 RMS grants urgency 3/29/2006 RMS consideration of the RMGRR and review of an IA (special meeting) 4/7/2006 TAC consideration

  5. Urgent RMGRR Timeline (RMGRR033) (system impacts) 5/9/2006 ERCOT posts the TAC Recommendation Report 4/26/2006 ERCOT reposts the RMS Recommendation Report including PRS decision 4/17/2006 ERCOT posts the RMS Recommendation Report 3/22/2006 ERCOT posts the RMGRR 3/15/2006 MP submits new a RMGRR Effective Date 6/1/2006 or as otherwise specified by the BOD 4/12/2006 RMS consideration of the RMGRR and review of the IA and CBA 4/21/2006 PRS recommends a priority for all projects 5/16/2006 BOD review 3/27/2006 RMS grants urgency 5/4/2006 TAC consideration