1 / 17

AWIPS II Status Update

AWIPS II Status Update . NWS Staff Meeting November 30, 2010. Events Since Last CB Brief. Sep. 23 - CB Brief Oct. 18 - DUS Brief Approved re-baselined schedule Commitment to No-Later-Than Q1 FY12 deployment NWS Target: Deployment Start Q4 FY11

madison
Download Presentation

AWIPS II Status Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AWIPS II Status Update NWS Staff Meeting November 30, 2010

  2. Events Since Last CB Brief • Sep. 23 - CB Brief • Oct. 18 - DUS Brief • Approved re-baselined schedule • Commitment to No-Later-Than Q1 FY12 deployment • NWS Target: Deployment Start Q4 FY11 • Oct. 18 –> 22 – Forecaster Initial Testing (FIT) #14 • Localized to Salt Lake City • Oct. 27 – Don Berchoff sponsored telco with RD’s on AWIPS II & local apps • Oct. 29 – Commerce IT Review Board (CITRB) Brief • New schedule formally briefed and accepted • Closely watching progress • Status update due in March ‘11 • DR’s down almost 500 • 932 Open impact 1-3’s as of 11/19 v.s. 1428 on Sep. 23

  3. Actions Status Update

  4. Overview • AWIPS II steadily improving • Raytheon DR fixing productivity increasing • Avg. 110 fixes per week over last three weeks • 4 weeks of schedule margin • Regions scrub of local apps reduced critical list by 324 (19%) • 5 critical remaining to complete for entry into Phase II of System OT&E • Currently, no blocking DR’s • Training still a risk • Application Focal Point modules are the biggest challenge • Acceptable drafts by April 15, for Field OT&E • New approach for FFMP expected to show success in December • Small team of focused experts for each module • Focus on differences between AWIPS I and AWIPS II • Training Division staff to provide training development technique, mission oriented focus and AWIPS I expertise • Raytheon to provide targeted AWIPS II expertise from individual developers on an application by application basis • Use as model for remaining modules • Next FIT (Dec 6  17) is critical for entrance into Phase II of System OT&E • Testing service backup • Testing fully localized RFC • Stability • 12 day stability assessment • No more than 15 minutes total of system downtime • WarnGen performance key

  5. DR Progress Tracking Open Planned v.s. Actual (11/19/10) # of Open DR’s System OT&E Test Periods FIT Tests Actuals as of (11/19/10) • 0% rework rate (0 failed DR’s out of 11 tested) • 9% wk. ending 11/12 28% wk. ending 11/5 • 22 DR’s Discovered last week Avg. 27/wk, last 3 wks • 13 DRs wk ending 11/12, 47 DRs wk. ending 11/05 • 104 net DR decrease, (v.s. 44 planned) 3 wk. rolling avg. = 104 (decrease) • 2.69 DR’s per person per week, for current wk. • 2.46 wk. ending 11/12, 3.28 wk. ending 11/05 • Raytheon staff: 39 (unchanged from wk. ending 6/28) • 105 DR’s fixed last week. Avg. 110/wk, last 3 wks. • 96 wk. ending 11/12, 128 wk. ending 11/5 5

  6. Local ApplicationsBefore System OT&E Phase II Start Phase II System OT&E 6

  7. Local Application Migration Status5 Remaining Critical Local Apps 7

  8. Local ApplicationsBefore Field OT&E Regional Inventory Review Start Phase II System OT&E Start Field OT&E 8

  9. Local ApplicationsBefore Deployment Regional Inventory Review Start Phase II System OT&E Start Field OT&E Start Deployment 9

  10. Training Progress Application Focal Point Training Target: Acceptable Drafts of All Modules Complete by April 15, 2011

  11. AWIPS II Schedule

  12. ADAM Status • AWIPS II Data & Application Migration (ADAM) platform: • a standalone, workstation platform (leveraging scalability of AWIPS II software) using “baseline AWIPS II software” enables sites to migrate local data BEFORE AWIPS II installation, and migrate local applications prior to system deployment to mitigate technical and schedule risk. • 45 sites have been identified as Beta sites • 19 sites installed so far – ingesting data successfully • Delivered with November software release (R1G1-5) • Draft localization documents on track to be delivered Dec 1 • Sites can begin localizing • Once localized, sites can begin migration activities immediately with platform as is i.e. no software upgrade needed • Existing DR’s in baseline functionality will not prevent local apps from being migrated • New DR’s could be found that will prevent some local apps from being migrated • These will be prioritized appropriately by Test Review Group for resolution by Raytheon • Local apps that can be immediately migrated will not have to be re-done later • Raytheon NCF will take trouble calls and support • ADAM is non-operational so Trouble Tickets are will be lower priority than operational tickets and will be worked as resources are available • AWIPS II DR’s can be written but must be filtered for duplicates and ADAM specific issues • Raytheon will update software periodically • depending on local apps and site migration needs

  13. NCEP NAWIPS Migration Status • Vendor missed key hardware delivery date of 11/4 • On track to meet new delivery date of 11/24 • Vendor agreed to significant compensation for missed delivery • Impact to schedule Impact #1: SIB will not have time to test software on Test Bed prior to software handoff to RTS scheduled for December 13 Impact #2: This will extend OTE for NCEP

  14. Summary • Continue to support FIT’s and follow-on System OT&E Test Periods with field personnel • Once ADAM is installed and localized, expect sites to begin local apps and site migration activities • Support training development • Support new small-team expert approach to get training materials in good enough shape for Field OT&E • April 15th target

  15. Backup

  16. Preliminary Results of Regions Scrub of Local Apps (11/12/10) 16

  17. AWIPS II System OT&E Phase 2 Entrance CriteriaStatus

More Related