1 / 1

Accelerated Bridge Construction Bunker Creek Bridge, Durham NH

Accelerated Bridge Construction Bunker Creek Bridge, Durham NH. Bunker Creek. NEXT D Beams. Columns. Drilled Shaft 1 ft outside of current roadway. Cast in place with early high strength concrete.

myron
Download Presentation

Accelerated Bridge Construction Bunker Creek Bridge, Durham NH

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Accelerated Bridge Construction Bunker Creek Bridge, Durham NH Bunker Creek NEXT D Beams Columns • Drilled Shaft 1 ft outside of current roadway. • Cast in place with early high strength concrete. • Shaft will need to extend to +40’ in order to create a moment connection to bedrock. Surrounding soil is clay/silt mixture. • 4- 10’ wide NEXT 32 D beams will be used. Due to Flange width, no additional concrete is needed for deck. • Beams will be prestressed, precast off site. Oyster River • Background: • Originally built in the 1930’s • Various repairs through the year • Substructure mostly original • Considerations: • High Traffic Volume/Truck Route • Long Detour • Environmentally Sensitive Area Project Concepts Use ABC methods to complete project as quickly and efficiently as possible using mostly precast/prestressed concrete members Pilecaps • Precast offsite • Current NH truck limit for 8 or more axles is 150 kips without special permits. • Design without cutout was 176 kips, but with cutouts is 148 kips (using 7 ksi concrete) Durham NEXT 32D RT 4 Portsmouth Shear connections between the four NEXT 32 D beams will be accomplished with a Tongue and Groove Shear Key that is sealed with a polymer. CROSS SECTION Post tensioning will be done using DYWDAG bars. Due to 2% hunch needed in roadway, a coupler will be cut/welded to match the slope. Computer modeling foresees negligible stresses across the center from the hunch, however laboratory tests still need to be accomplished. • Initial Site Work - minimal daily lane closures • Site Preparation • Column Installation • Bridge Replacement – Full Road Closure • 5 to 14 days • Remove current bridge • Install new bridge • Post Site Work- minimal daily lane closures • Stone Wall Installation • Shoulder Widening on roadway SIDE VIEW Roadway Widening • Granite blocks stacked vertically and tied into bank in order to create a steeper slope that remains within current bank width. • Area will be filled in using geotextiles. • After compaction, a wider shoulder can be added and guard rails moved outwards. Carbon Fiber-Reinforced Polymer (CFRP) grid will be used on top and bottom of flange in place of traditional Temperature and Shrinkage Steel. By: Elizabeth Kinney Advisor: Dr. Charles Goodspeed

More Related