Procurement. David Dale Procurement Manager CFAC Status Meeting May 8, 2008. Outline. Contractor Outreach Conventional Construction Informational Meeting Ring Building Procurement Schedule Conventional Construction Procurements Procurement Support to CF Conclusion.

pete
Download Presentation

Procurement

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Procurement David Dale Procurement Manager CFAC Status Meeting May 8, 2008

  2. Outline • Contractor Outreach • Conventional Construction Informational Meeting • Ring Building Procurement Schedule • Conventional Construction Procurements • Procurement Support to CF • Conclusion

  3. Ring Building Contractor Outreach • Construction Outreach Expression of Interest issued to the top 50 construction firms 12/14/07 • Eight firms with appropriate qualifications have expressed interest in bidding on the Ring building as a General Contractor. Four of the firms are local • E.W Howell, Dematteis, Torcon, J.Kokalakis (local firms) • Pike Company, Shaw Group, Washington Group, and J.E Dunn

  4. Conventional Construction Informational Meeting • 3/20/08 Project Presentations to Construction Firms • Representatives from 6 General Contractors • Shaw, Torcon, Dematteis, E.W.Howell, Washington Group, J. Kokolakis • Representatives from 3 Subcontractors • Eldor (electrical), Roger & Sons (concrete), G&M Earthmoving (excavation) • Excellent feedback from contractors • Burns & Roe has expressed interest as of 3/25/08 • Pike and J.E. Dunn have dropped out

  5. Ring Building Procurement Schedule • 1/08 Expression of interest • 2/08 Project Workshop ,Procurement, ESSH, Construction • 3/20/08 Project presentations to contractors • 4/10/08 Draft RFP issued to consultant, inside/outside legal review • 5/01/08 Draft evaluation criteria to DOE/BHSO • 5/15/08 Draft RFP to industry • 6/09/08 Final RFP issued to DOE/BHSO • 9/08 DOE reviews /approves RFP and proposed contract • 9/26 RFP Issued to contractors • 2/09 Contract Award

  6. Conventional Construction Procurements • A/E Procurement Ring Building (HDR) • Title III negotiations to begin in May 08 ( Est $3.6M) • Estimated award September 08 • Site Preparation • IFB Issuance scheduled for August 08 (Est $1M) • Estimated award October 08

  7. Procurement Staffing

  8. Conclusion • Successful Contractor Informational meeting • CF working closely with Procurement on RFP • Ring Building Procurement on schedule • Procurement team focused