Grid25: An Enabler for Regional Development. County Mayor’s Conference 2011. Dermot Byrne Chief Executive, EirGrid. Transmission Grid. Motorways of power!. 1830 km. 440 km. 4000 km. 400 kV. 220 kV. 110 kV. Wind Capacity Statistics. ROI NI (MW) (MW) Installed Wind: 1425 340

peyton
Download Presentation

County Mayor’s Conference 2011

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Grid25: An Enabler for Regional Development County Mayor’s Conference 2011 Dermot Byrne Chief Executive, EirGrid

  2. Transmission Grid • Motorways of power! 1830 km 440 km 4000 km 400 kV 220 kV 110 kV

  3. Wind Capacity Statistics ROI NI (MW) (MW) Installed Wind: 1425 340 Planned Wind: 1150 350 Gate 3 / Future: 3900900 6475 1590

  4. Wind farm locations Gate1:Blue Gate2:Red Gate 3:Green

  5. GOLAGH GILRA WATERFORD AGHADA RAFFEEN Wind Applications MW 271 204 TRILLICK SORNE HILL BUNBEG KILTOY LETTERKENNY MEENTYCAT TO STRABANE DRUMKEEN MID DONEGAL NORTHERN BINBANE IRELAND CATHALEEN'S CLIFF FALL LISDRUM TO ENNISKILLEN SLIGO 1071 103 TO TANDRAGEE 112 14 TAWNAGHMORE CORDERRY SRANANAGH Totals: Gate 2 ≈1,300 MW Gate 3 ≈ 4,000 MW CORRACLASSY 275kV BELLACORICK CUNGHILL GORTAWEE MOY ARIGNA DUNDALK SHANKILL RATRUSSAN LOUTH CARRICK MULLAGHARLIN -ON- MEATH SHANNON HILL TONROE ARVA FLAGFORD CASTLEBAR 70 13 DRYBRIDGE DRYBRIDGE NAVAN RICHMOND GORMAN DALTON 772 LANESBORO PLATIN KNOCKUMBER STEVENSTOWN MULLINGAR CORDUFF WOODLAND BALTRASNA GLASMORE HUNTSTOWN CLOON KINNEGAD KILMORE GRANGE ATHLONE CAMUS FINGLAS NORTH WALL MACETOWN COLLEGE RB POOLBEG PARK DUNFIRTH MAYNOOTH DERRYIRON RINAWADE SHELLYBANKS GH IRISHTOWN CASHLA INCHICORE THORNSBERRY BLAKE CUSHALING 532 159 COOKSTOWN SHANNONBRIDGE GALWAY CARRICKMINES SOMERSET MONREAD KILTEEL FASSAROE TYNAGH GREAT CONNELL NEWBRIDGE CHARLESLAND DUNSTOWN POLLAPHUCA DERRYBRIEN OLDSTREET Also conventional generation in Gate 3 DALLOW TURLOUGH HILL BALLYBEG 88 118 121 66 ATHY AGANNYGAL PORTLAOISE STRATFORD IKERRIN ARBANK SHELTON ARKLOW ENNIS ABBEY CARLOW BOOLTIAGH KELLIS NENAGH LISHEEN ARDNACRUSHA DRUMLINE TULLABRACK THURLES AHANE MUNGRET PROSPECT BANOGE SEALROCK MONETEEN KILLONAN MONEYPOINT KILKENNY CASTLEFARM TARBERT LODGEWOOD AUGHINISH LIMERICK CRANE BALLYWATER BALLYCUMMIN RATHKEALE TIPPERARY TRIEN ATHEA 689 594 DOON CAHIR WEXFORD BALLYDINE ANNER CHARLEVILLE CLAHANE TRALEE GREAT ISLAND KILLOTERAN CULLENAGH GLENLARA BUTLERSTOWN 62 MALLOW OUGHTRAGH KNOCKEARAGH BARRYMORE DUNGARVAN 61 2 COOMACHEO KNOCKRAHA CLONKEEN CLASHAVOON COOMAGEARLAHY KILBARRY INNISCARRA GLANLEE 101 44 MACROOM MARINA COOLROE TRABEG HARTNETT’S CARRIGADROHID CROSS WHITEGATE BRINNY BANDON BALLYLICKEY DUNMANWAY

  6. Demand Forecast (All-Island Generation Capacity Statement 2011-2020) All-Island

  7. The Market for Renewable Energy Home Market limited Extensive resource available (on-shore wind, off-shore wind, marine, etc.) Opportunities for Export?

  8. Home Market Challenges(Power System Transformation) Carbon Neutrality Electrification of Transport and Heating Sectors • Smart Grids • Renewables Integration • Grid Development Deregulation Competition and Customer Choice Time

  9. Infrastructure Challenge - Drivers 40% renewable target Interconnection with Europe All Island Market Increase in demand for electricity Regional Development

  10. The Infrastructure Challenge • Access • Interconnection • Grid Development • Off-shore Grid Off-shore Grid Study Gate 2/3 Grid25 EWIC

  11. Connecting Ireland and Great Britain

  12. €4 bn Grid Development Strategy- Grid25 2,200 km Upgrades 1,150 km New Build €4 billion

  13. Grid25 Strategic Options Security & Reliability Balance Costs & Efficiency Community & Environment Build New 400 kV HV AC Overhead Upgrade 220 kV HV DC Underground

  14. Primary Corridors for Reinforcement *

  15. Transmission Projects in Progress • September 14

  16. Transmission Projects Under Analysis • September 14

  17. GRID25 Network Development – In pre planning phase Moneypoint Devlopment TOEM Kilpadogue Moneypoint - North Kerry ATHEA DROMADA North Kerry CLOUGHBOOLA CLAHANE KERRY KNOCKACUMMER CORDAL East Kerry/North Cork KIPPALOCK Millstreet BOGGERAGH GARROW KILGARVAN Clashavoon - Dunmanway BARNADEVINE

  18. GRID25 Network Development – Under Construction Killonan 4th Transformer Tarbert - Tralee 2 CLAHANE Killonan – Knockraha Knockraha 3rd Transformer + Busbar Glanagow - Raffeen

  19. GRID25 Network Development – Construction starting 2011 CLAHANE Cullenagh – Knockraha Coolroe - Kilbarry Bandon - Dunmanway

  20. Challenge

  21. Public Acceptability

  22. Transforming the Power System Carbon Neutrality Electrification of Transport and Heating Sectors + Exports Smart Grids Renewables Integration and Grid Development Deregulation Competition and Customer Choice Time