Test facilities: Present and Future

Test facilities: Present and Future. J. Mekki on behalf of the R2E project. Outline. Introduction What to test for and where ? How do we do radiation tests ? Overview of the different facilities Pros and cons A New “in-house” facility – CHARM Operation and representativeness Conclusion.

roxy
Download Presentation

Test facilities: Present and Future

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Test facilities: Present and Future J. Mekkion behalf of the R2E project

  2. Outline • Introduction • What to test for and where ? • How do we do radiation tests ? • Overview of the different facilities • Pros and cons • A New “in-house” facility – CHARM • Operation and representativeness • Conclusion

  3. What to test for and where ? See Giovanni’s presentation Single Event Effects Stochastic effect (chip level, system impact etc …) Facilities: Mixed field, Proton, Neutron and Heavy Ion Effects in the Device

  4. What to test for and where ? See Giovanni’s presentation Effects in the Device TID Cumulative effect Lifetime → non shielded area Facilities: Mixed field, Proton, Co-60 gamma source

  5. What to test for and where ? See Giovanni’s presentation Effects in the Device Displacement Damage Cumulative effect Tunnel locations Mainly optical devices, and very accurate components (e.g. Voltage reference) Facilities: Mixed field, Proton, Neutron, Nuclear Reactor

  6. What to test for and where ? See Giovanni’s presentation Single Event Effects Stochastic effect (chip level, system impact etc …) Facilities: Mixed field, Proton, Neutron and Heavy Ion → High-Energy tail of Spectrum (e.g. important for SEL) Effects in the Device Displacement Damage Cumulative effect Some important locations as … Mainly optical devices, and very accurate components (e.g. Voltage reference) Facilities: Mixed field, Proton, Neutron, Nuclear Reactor TID Cumulative effect Lifetime → non shielded area Facilities: Mixed field, Proton, Co-60 gamma source → Accelerated radiation test → ELDRS not tested

  7. Test Facilities • CERN • CNRAD (stopped after LS1) • H4IRRAD (could be used but limited) • Towards CHARM → July 2014 • PSI • CEA reactor • Fraunhofer • Heavy Ions facilities (Done through external companies → e.g. TRAD) • Thermal neutron facilities (Prague, Oslo, Rome)

  8. Size Matters? TEST COMPONENTS/CARDS: 5 cm beam diameter OR EVEN TEST THIS: (W)HOW ??? HERE

  9. CNRAD Radiation test area • Mixed radiation field similar to the one expected in LHC • Measured quantities: • Dose (SiO2) • Hadron>20MeV fluence • 1MeV neutron eq. fluence • Test of entire equipment • Extensive Monitoring: • RadMons • Compared to BLMs • Gold Foils, TLDs,… • Detailed FLUKA Simulations for: • TID (air), Hadron>20MeV fluence • 1MeV neutron-equivalent fluence • Particle-Energy Spectra, Thermals,… • Hottest test location (Target area) • HEH fluence ≈ 3×1012 cm-2/week • Dose ≈ 500Gy/week • Low Flux locations (TSG46) • HEH fluence ≈ 2×1010 cm-2/week • Dose ≈ 3 Gy/week

  10. H4IRRAD Radiation test area • Mixed radiation field similar to the one expected in LHC • Internal/External zone: • RadMons • Compared to BLMs • Gold Foils, TLDs,… • Detailed FLUKA Simulations for: • TID (air), Hadron>20MeV fluence • 1MeV neutron-equivalent fluence • Particle-Energy Spectra, Thermals,… • For small to bulky equipment • Measured quantities: • Dose (SiO2) • Hadron>20MeV fluence • 1MeV neutron eq. fluence • Hottest test location (downstream target – 2012) • HEH fluence : 6×1010 cm-2/week • Dose: 40 Gy/week • External Zone – 2012 • HEH fluence : 8×109 cm-2/week • Dose: 3 Gy/week • Test of entire equipment

  11. Mixed field facilities • Good reproducibility of shielded area and tunnel environment K. Roeed (2011)

  12. PSI – PIF facility • Monoenergetic proton beam from 30 – 230 MeV • Beam time available via special agreement (since 2011) • Beam spot < 9 cm • → (5 cm uniformity ≈ 90 %) • Maximum Flux at 230 MeV • → 1.5×108 p/cm2/s • TID and Displacement Damage (DD) tested at the same time • Accelerated radiation test • (ELDRS not tested) • Limited availability in 2014/2015 • Measured quantities: • Dose (SiO2) • Proton fluence • Displacement Damage

  13. Others • Neutron facilities: • NRI (Czech Republic), PTB (Germany), IFE (Norway), ILL (France) • Neutron/gamma facility: • CEA Valduc (France) • Gamma – Co-60 facilities: • ESTEC (Netherlands), Fraunhofer institute (Germany), IRA (Switzerland)

  14. Pros and cons of “in-house” facilities

  15. Pros and cons of “external” facilities

  16. Pros and cons of “external” facilities • For both: • Availaibility: Very uncertain and more and more complicated • Shipping and recovering the samples: very difficult

  17. To summarize … • CERN experimental test areas: • CNRAD and H4IRRAD: • During the last years, increasing up to 56 groups/projects • Outside CERN: • PSI: • Since 2010: 37 test campaigns. Framework contract • Other (CEA, ESTEC, Fraunhofer, PTB …) : • Since 4 years: ≈ 15 test campaigns • Total → more than 100 test campaigns Huge amount of radiation tests

  18. To summarize … • CERN experimental test areas: • CNRAD and H4IRRAD: • During the last years, increasing up to 56 groups/projects • Outside CERN: • PSI: • Since 2010: 37 test campaigns. Framework contract • Other (CEA, ESTEC, Fraunhofer, PTB …) : • Since 4 years: ≈ 15 test campaigns • Total → more than 100 test campaigns • Beyond LS1, according to the huge amount of test in the coming years: • Power converter, QPS, NanoFIP, BLM, RF, BPM, Cryogenics, Collimation, SPS/PS Interlock, PS Ventilation access, LIU/SPS, CLIC, ISOLDE, LHC Upgrade, Cables, fibers, magnets, collimators, IT equipments, RadMON sensors/new version, etc… • The stop of the CNRAD activity • The limitation of H4IRRAD • PSI availability (stop “mid 2014 → 2015”) Huge amount of radiation tests • Needs to have a new in-house facility

  19. New Facility Required CHARM CernHigh Energy AcceleRatorMixed Field/Facility • We’d also Other Good Options, … But • CHER (French = expensive)(CernHigh Energy Radiation Facility)

  20. List of groups/projects for the future • Beam Instrumentation • SPS trajectory and orbit system (front-end electronics) • PSB orbit system (front-end) • SEM loss monitor (front-end amplifier) • Wire scanner • Cameras • TE/EPC (e.g Power converters) -> Development up to 2018 • EN/EL (e.g UPS) -> Development up to 2016 • QPS • LHC experiments • Cryogenics • Beam Position Monitor • EN/STI (e.g. component tests, RadMON V6) • Beam Loss Monitors • EN/ICE • From Outside (Universities, laboratories, industrials: e. g. radiation tests with particle spectra representative of atmospheric/ground environments) • And others ….

  21. The High-E Accelerator Environment • Radiation fields originated by very high energy particles interacting with different elements (collimators, gas, targets, etc.) • Wide range of intensities! HEH/cm2/yr Dose (Gy/y)

  22. East Area Facilities 24 GeV/c proton beam

  23. East Area Facilities 24 GeV/c proton beam IRRAD proton facility PH/DT 24 GeV/c proton beam LHC experiments

  24. East Area Facilities 24 GeV/c proton beam CHARM R2E Project

  25. East Area Facilities 24 GeV/c proton beam Technical local Connection to the radiation area

  26. East Area Facilities 24 GeV/c proton beam Control room Dry run test

  27. Main Elements 24 GeV/c proton beam

  28. Patch Panel – Cable list

  29. Approach: Test Positions 24 GeV/c protons 4x40 cm movable shielding

  30. Varying Radiation Field Radiation levels during one week test campaign Beam Positiontarget in:HEH: >1.7×1014cm-2TID: >17 kGy target out:HEH: >1.7×1015cm-2TID: >1 MGy D+H Longitudin. Lateral Positions HEH: 1.7×1011cm-2 – 1.7×1014cm-2TID: 17Gy – 17kGy (gradients to be considered) Full racks, crates, set of cards, componentsHEH: 1.7×1010cm-2 – 1.7×1013cm-2, TID: 1.7Gy – 1.7kGy

  31. Varying Radiation Field 1 year of injectors operation → Max. 1 week at CHARM Beam Positiontarget in:HEH: >1.7×1014cm-2TID: >17 kGy target out:HEH: >1.7×1015cm-2TID: >1 MGy D+H Longitudin. Lateral Positions HEH: 1.7×1011cm-2 – 1.7×1014cm-2TID: 17Gy – 17kGy (gradients to be considered) Full racks, crates, set of cards, componentsHEH: 1.7×1010cm-2 – 1.7×1013cm-2, TID: 1.7Gy – 1.7kGy

  32. Comparison with previous test areas • Intensity reachable for 1 year (220 days) of beam operation in comparison to previous experimental test areas • Before LS1: CNRAD and H4IRRAD • Beyond LS1: CHARM • 2013/2014: Design commissioning • > Mid-2014: Large amount of test requirements, needs of an efficient coordination/operation

  33. Test positions: -> Spectra Impact on intermediateenergies Different thermal behavior Different high energy (HE) contributions

  34. Shielding Configuration: -> Spectra Scoring in Rack 4 Iron/Iron/Concrete/Concrete Concrete/Concrete/Iron/Iron

  35. Representative Test Locations Accelerator Tunnels 90% of the particles

  36. Representative Test Locations Accelerator Shielded Areas 1 99% of the particles

  37. Representative Test Locations Accelerator Shielded Areas 2 90% of the particles

  38. Facility Design Targets • Contrary to other facilities: • Setup needs to be radtol • Large distance: ≈ 30 m of cables. Designer needs to integrate in their design the possibility to measure short signal (e.g. short transient “few ns”) and also to work at high speed. • But … • Numerous representative radiation fields • Mixed-Particle-Energy • Direct beam exposure • Large range of fluxes and dose ranges(covering accelerator, but also other applications)

  39. Facility Design Targets • Possibility for large volumes/high number of components or full systems • Easy usage • Dedicated preparation area • Cables pre-installed + patch panel • Conveyer systems • Detailed, on-line andhigh-accuracy monitoring (CERN RadMon system)

  40. Conclusions • Contract with Fraunhofer (TID/DD) optimized • PSI contract (to be adjusted after 2015) • Critical collaborations with other institutes (help and support) • External companies → To be taken with care (standards components → OK complex systems → To be checked) • Costs are mainly covered by R2E project (whenever operation impact) • Campaigns are coordinated (optimized) through RadWG • Strong collaboration with all the users/groups

  41. Conclusions • Testing complex systems or many components can be important/useful • BI request → First planning ? • Because: • Huge amount of tests in the coming years • CNRAD activity stopped • H4IRRAD activity limited • PSI not available mid-2014/2015 (at least for 4 months) • A new test facility will soon be available at CERN (mid-2014) • In view of the amount of test requirements at CHARM →Need of an efficient coordination/operation