An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CYPRESS CREEKAquatic Ecosystem Restoration Feasibility Study U.S. Army Corps of Engineers, Mobile District And The City of Montgomery, Alabama 6 Sept 2012

  2. MONTGOMERY, ALABAMA

  3. CYPRESS CREEK STUDY AREA Inlet Cypress Creek - approx. 5,042 feet

  4. REACH 1 Reach 1 – approx. 1,295 feet

  5. REACH 2 Reach 2 - approx 1,970 feet

  6. REACH 2

  7. REACH 2

  8. REACH 3 Reach 3 – approx. 807 feet

  9. REACH 4 Reach 4 – approx. 970 feet

  10. REACH 4

  11. RAILROAD EMBANKMENT

  12. CYPRESS INLET

  13. PROJECT AUTHORITY • Section 206 of the Water Resource Development Act of 1996, as amended • Aquatic Ecosystem Restoration Project • Federal Funding Limit $5,000,000

  14. COST SHARE • 100% Federal – Initiate Background Study to determine Federal interest • 50/50% Federal and non-Federal - Feasibility Phase Study • 65/35% Federal and non-Federal - Design and Construction Phases

  15. TWO PART PLANNING PROCESS • Feasibility • Define problems and opportunities; identify potential solutions. • Estimate benefits and costs of solutions to determine prospects for an implementable project. • Determine Federal interest in potential solutions. • Estimate costs of feasibility study. • Corps and non-Federal sponsor must agree to share equally in the cost of the feasibility study. (50% Federal / 50% non-Federal)

  16. TWO PART PLANNING PROCESS (Continued) • Feasibility Phase • More detailed planning and evaluation of alternative solutions to water resources problems. • Determine what plan(s) merit Federal participation. • Complete the feasibility report recommending solutions for implementation. • Non-Federal sponsor provides a letter of intent. • Coordination of feasibility report with Federal, State and local agencies. • Feasibility Report Approval

  17. TWO PART PLANNING PROCESS(Continued) • Design & Implementation • The non-federal sponsor and USACE sign Project Partnership Agreement agreeing to 65% Fed / 35% non-Fed cost share • Prepare Designs • Designs go out for bid by Contractors • Construction

  18. TWO PART PLANNING PROCESS(Continued) • Monitoring • Begins after construction is complete • Biological monitoring occurs until ecological success is achieved • Cost shared under construction for up to 10 years • If needed after 10 years it becomes 100% non-federal cost

  19. GENERAL INFORMATION & PROBLEMS • Cypress Creek: Approximately 5,042 ft. in length • Lack of native fish species due to lack of riffle/pool habitat & barriers to fish passage • Lack of meanders to due channelization of the creek • Low flow within the creek • Significant debris along Cypress Creek and at the mouth of Cypress Inlet • Invasive Plant Species • Reach 3 is underground • Lack of fluvial exchange with the Alabama River and Cypress Inlet • Increased sedimentation due to lack of floodplain and channelization of creek

  20. GENERAL INFORMATION & PROBLEMS(Continued) • Disrupted riparian corridors and lack of mature native tree canopy • Lack of woody debris inputs, stream shading, refuge habitats and streambank stability

  21. LACK OF FLUVIAL EXCHANGE

  22. SEVERAL IMPOUNDMENTS

  23. CULVERTS/UNDERGROUND SECTION

  24. HISTORIC STRUCTURES

  25. RAILROAD TRACKS

  26. TRASH

  27. DEBRIS

  28. LACK OF RIPARIAN

  29. SEDIMENTATION WITHIN CHANNEL

  30. LACK OF VEGETATION

  31. INVASIVE SPECIES

  32. OPPORTUNITIES • Improve hydrologic connectivity • Restore the surface water connection between Cypress Creek and the Alabama River • Reduce nuisance flooding by improving structures at stream crossings • Increase native species • Improve aquatic habitat • Restore riffle/pool habitats and remove barriers to native, sensitive aquatic species, and increase species richness/evenness • Restore natural flow regimes and reconnect the stream to the floodplain

  33. OPPORTUNITIES(Continued) • Reduce sedimentation and preventing further habitat embeddedness • Increase in-stream food availability, refuge, and stream shading by removing invasive vegetation and adding woody, native vegetation in currently disturbed riparian areas.

  34. DELIVERABLES BY OCT 2012 • Updated Project Management Plan • Survey data • Write up detailing HEC-HMS and HEC-RAS models and results for existing and future without conditions. • Background of socio-economic conditions • Draft Real Estate Plan • Phase 1 Environmental Site Assessment – HTRW • Initial Coordination letters to other Federal/State agencies (USFWS, ADEM, etc.)

  35. DELIVERABLES BY OCT 2012(Continued) • Write up of environmental model factors • Fish Sampling Report • Problems Area Report • Conceptual model • Initial Cultural Resources letters (Tribal, SHPO) • Write up of geotechnical analysis

  36. WHAT’S NEXT? • Receive additional funding (Federal and non-Federal) • Continue developing Environmental Benefits Model • Inventory and Forecast Future with project conditions • Formulate Alternative Plans • Evaluate Effects of Alternative Plans • Compare Alternative Plans • Select Recommended Plan • Report Approval • DI Phase

  37. QUESTIONS? Contact Information: Kerry Gates, Planner 251-694-3809