An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Ministerul Transporturilor si Infrastructurii Compania Nationala de Autostrazi si Drumuri Nationale Dezvoltarea infrastructurii rutiere Septembrie 2012

  2. 2 Sumar Care sunt cerintele in domeniul infrastructurii rutiere? Care este stadiul actual al retelei? 2 ROADS

  3. Reteaua de drumuri publice Lungime = 78,182 km (exclusiv reteaua de strazi) si se clasifica in : 1. Drumuri nationale 15,968 km; 2. Drumuri judetene 34,914 km; 3. Drumuri comunale 27,300 km. Reteaua de drumuri nationale este administrata de Compania Nationala de Autostrazi si Drumuri Nationale din Romania, unitate functionala sub autoritatea Ministerului Transporturilor si Infrastructurii. Reteaua de transport din Romania este structurata astfel : autostrazi 504 km drumuri nationale europene 5.938 km drumuri nationale principale 4.383 km drumuri nationale secundare 5.384 km

  4. Coridoare Pan – Europene de Transport CorIdor IV L=3258 km BERLIN DRESDA NUREMBERG PRAGA BRNO VIENA BRATISLAVA GYOR BUDAPESTA ARAD CRAIOVA BUCURESTI CONSTANTA SOFIA PLOVDIV SALONIC ORMENIO ISTAMBUL Coridor IX L=6500 km HELSHINKI ST. PETERSBURG MOSCOVA KALINGRAD KIEV ODESA CHISINAU BUCURESTI VILNIUS KRAIPEDO MINSK ALEXAN-DROPOLIS DIMITROGRAV ORMENIO Romania este amplasata in partea de SE a Europei si este traversata de 2 coridoare pan – europene: IV si IX

  5. Coridorul Pan - European nr. IV permite asigurarea unei conexiuni directe la Marea Neagra, respectiv cu granita romano – bulgara prin ramura sudica a Coridorului.

  6. Coridoare Pan – Europene de Transport ALBITA NADLAC Coridorul Pan – European nr. IV • NADLAC – TIMISOARA – LUGOJ – BUCURESTI – CERNAVODA - CONSTANTA LUGOJ Coridorul Pan – European nr. IX GIURGIU – BUCURESTI - ALBITA Serbia Coridorul Pan – European nr. IV – ramura sudica • LUGOJ – CRAIOVA - CALAFAT CRAIOVA BUCURESTI CONSTANTA CALAFAT GIURGIU

  7. Care este scopul CNADNR? • Modernizarea şi reabilitarea drumurilor naţionale şi podurilor; • Construirea de variante ocolitoare pentru oraşele cu volum mare de trafic; • Construirea de autostrăzi noi şi variante de ocolire cu profil de autostradă • Reproiectarea şi redimensionarea structurii rutiere a reţelei existente de drumuri naţionale pentru încărcarea pe osie de 11,5 tone; • Încadrarea în normele de protecţie a mediului şi armonizarea acestora cu normele europene; • Întărirea capacităţii administrative în domeniul infrastructurii rutiere;

  8. Cadrul Legal – Legea nr. 363/ 2006privind “Amenajarea Teritoriului National – domeniul rutier” - cadrul de referinta pentru viitoarele proiecte din domeniul infrastructurii rutiere

  9. Cum se clasifica proiectele de infrastructura rutiera? Autostrazi Drumuri europene Drumuri nationale principale Drumuri nationale secundare

  10. Care sunt caracteristicile vizate? La standarde TEM, TEN-T • Infrastructura conform standardelor • Dotari cu elemente ITS • Parcari moderne

  11. Petea Satu Mare Baia Mare Pascani Iasi Bors Ungheni Oradea Albita Cluj Turda Tg. Mures Nadlac Arad Sighisoara Deva Sebes Sibiu Lugoj Timisoara Orastie Fagaras Focsani Brasov Galati Comarnic Braila Ploiesti Buzau Pitesti Cernavoda BUCURESTI • Legenda • Profil de autostrada • Drumuri expres, • cu Studii de Fezabilitate • Drumuri expres , • In pregatire Craiova Constanta Giurgiu Zimnicea

  12. Reteaua de autostrazi AUTOSTRADA TRANSILVANIA BRASOV - BORS AUTOSTRADA TG. MURES – IASI – UNGHENI UNGHENI Suplacu de Barcau BORS ALBITA GILAU AUTOSTRADA PLOIESTI – COMARNIC - BRASOV TARGU MURES NADLAC BRASOV LUGOJ CORIDORUL PAN-EUROPEAN NR. IX PLOIESTI CORIDORUL PAN - EUROPEAN NR. IV CONSTANTA CRAIOVA BUCURESTI CALAFAT VAMA VECHE

  13. Programul de constructie a retelei de autostrazi va fi implementat in mod profesional, asigurand simultan beneficii in termeni :timp,viteza, economie de combustibil,protectia mediului,siguranta traficului, etc.

  14. STADIUL ACTUAL AL PROIECTELOR DE INFRASTRUCTURA RUTIERA IMPLEMENTATE: 1. CU SURSE DE FINANTARE ASIGURATE – IFI 2. PROPUSE A FI REALIZATE PRIN CONCESIUNE 3. CU SURSA DE FINANTARE ASIGURATA – FONDURI EUROPENE SI GUVERNUL ROMANIEI 4. CU SURSA DE FINANTARE ASIGURATA–Bugetul de Stat

  15. Autostrazi si variante de ocolire la profil de autostrada –in operare, cu finantare BEI/ BERD Varianta de ocolire Arad (12,3 km) 2009-2011 Arad – Timisoara (32,2 km) 2009-2011 Varianta de ocolire Constanta (22,1 km) 2008-2011 Cernavoda – Constanta (50,75 km) 2009-2011 Lungime: 117 km

  16. Autostrazi si variante de ocolire la profil de autostrada – incluse in programul de PPP/ Concesiune pentru asigurarea finantarii executiei Tg Mures-Iasi-Ungheni Lungime: 307 km Comarnic - Brasov Lungime: 58 km Sibiu – Pitesti Lungime: 116,64 km Focsani-Albita Lungime: 155 km Ploiesti-Buzau-Focsani Lungime: 133,00 km By-pass Bucuresti Nord Lungime: 53 km Ploiesti-Comarnic Lungime: 49 km By-pass Bucuresti Sud Lungime: 48 km Lungime: 919 km

  17. Autostrazi si variante de ocolire la profil de autostrada –in executie, cu finantare :Uniunea Europeana si Bugetul de Stat Nadlac – Arad (38,88 km) Timisoara-Lugoj (35,63 km) Orastie-Sibiu si by-pass Sebes (82,07 km) • Cu finantare de la Uniunea Europeana pentru executia lucrarilor Lugoj-Deva (99,50 km) Deva-Orastie ( 32,80 km) Lungime: 289 km

  18. Autostrazi si variante de ocolire la profil de autostrada – cu finantare de la Bugetul de Stat BRASOV – BORS Sectiunea Suplacu de Barcau – Bors (64 km) BRASOV – BORS Sectiunea Campia Turzii – Gilau (54 km) Suplacu de Barcau GILAU BUCURESTI – PLOIESTI Sectiunea Bucuresti – Moara Vlasiei – 13 km in operare In executie – 6 km BUCURESTI – PLOIESTI Sectiunea Moara Vlasiei – Ploiesti (42,5 km)- in operare Lungime: 180 km SERBIA Legenda Obiective in executie Obiective in operare

  19. TOTAL – 2302 km de autostrada, in conformitate cu strategia pe termen scurt, Din care:

  20. Programul de constructie autostrazi LEGENDA Sectiuni in operare In executie Ungheni In licitatie - 2012 Bors Proiecte viitoare Tg. Mures Albita Nadlac Arad Deva Sibiu Brasov Timisoara Orastie Lugoj Ploiesti Pitesti Serbia Constanta Bucuresti Bucuresti Cernavoda Craiova Calafat Constanta

  21. PROGRAMUL DE CONSTRUCTIE DRUMURI EXPRES DRUMUL EXPRES PETEA – SATU MARE – BAIA MARE DRUMUL EXPRES ZALAU – BAIA MARE DRUM EXPRES BRAILA - GALATI DRUM EXPRES SIBIU - FAGARAS DRUM EXPRES ARAD - ORADEA DRUM EXPRES SEBES - TURDA DRUM EXPRES CRAIOVA - PITESTI SERBIA Lungime: 516 km 19

  22. Reabilitarea drumurilor nationale Obiective finalizate

  23. Reabilitare drumuri nationale - Lucrari receptionate ETAPA I Lungime:1031 km Valoare: 334,31 Mil. Euro Finantare:BIRD, BERD, BEI 19 Etapa a II –a Lungime: 782,09 km Valoare: 436,46 mil. Euro Finantare: BIRD, BEI, Buget, PHARE, BERD 19A 17 24 1F 17 28 17 Etapa a III-a Lungime: 659,96 km Valoare: 450,80 Mil. Euro Finantare: PHARE, BEI, ISPA, Buget, JBIC 1 1C 15 1F 12 Etapa a IV-a - receptionat Lungime: 677,24 km Valoare: 596,48 Mil. Euro Finantare: PHARE, ISPA BEI, JBIC 15 13 2 1 6 7 13 69 24 7 12 Etapa a V-a - receptionat Lungime: 310,25 km Valoare: 208,61 mil. Euro Finantare: BEI, PHARE, ISPA, Buget 1 6 2 59 6 1 66 7 Etapa a VI-a - receptionat Lungime: 297,496 km Valoare: 258,63 mil. Euro Finantare: BEI 2 6 7 71 Serbia 1 6 7 2 65 21 6 22C 3 TOTAL KM drumuri nationale reabilitate 3758 km 56A 5 6 3

  24. REABILITARE DRUMURI NATIONALE Proiecte de REABILITARE PRIMARA Drumuri Nationale Variante ocolitoare Lungime: 4.005 km SERBIA

  25. Reabilitarea drumurilor nationale Obiective in executie

  26. 18 15A 15 14 2D 67C 71 Lungime – 984 km Reabilitare DN cu finantare de la bugetul de stat 72 SERBIA Lungime – 1001 km Reabilitare DN cu finantare rambursabila Lungime – 344 km Reabilitare DN cu finantare nerambursabila

  27. MODERNIZARE DRUMURI NATIONALE– cu finantare BEI – Lucrari in executie DN 18, Baia Mare – Sighetu Marmatiei Lungime: 58,7 km Valoare: 226,18 mil. lei Constructor: Aktor SA Stadiu actual: 6,30% DN 1H, Zalau –Rastoci Lungime: 53,38 km Valoare: 172,316 mil. lei Constructor: PA&CO/ Kemna Bau Andrae GmbH Stadiu fizic: 43,40% 18 DN 18, Sighetu Marmatiei - Moisei Lungime: 69,3 km Valoare: 169,19 mil. lei Constructor: Spedition UMB Stadiu actual: 0% DN19/1C, Satu Mare -Baia Mare Livada - Halmeu Lungime: 76,62 km Valoare: 185,96 mil. lei Constructor: V&V JV Stadiufizic: 53,18% DN 76, Stei - Beius Km 102+660 – 133+660 Lungime: 31 km Valoare: 99,59 mil. lei Constructor: Asocierea Azvi – Azcale DN 76 JV Stadiu fizic: 0% DN 24, Crasna –Iasi Lungime: 77,45 km Valoare: 242,01 mil. lei Constructor: UMB Spedition / Tehnostrade Stadiu fizic: 1,89% DN 18, Moisei – Iacobeni Lungime: 88,46 km Valoare: 421,67 mil. lei Constructor: Saphir Struct. Stadiu actual: 2,70% 15A DN 1C, Dej- Baia Mare Lungime: 86,49 km Valoare: 296,038 mil. lei Constructor: FCC Construction Stadiu fizic: 70,7% 15 DN 15A, Reghin – Saratel DN 15, Reghin -Tg. Mures Lungime: 71,5 km Valoare: 202,06 mil. lei Constructor: Strabag Stadiu actual: 26% DN 79, Arad – Oradea Lungime: 103,545 km Valoare: 330,79 mil. lei Constructor: Astaldi S.p.A. Stadiu fizic: 91,7% DN 76, Varfurile - Stei Km 69+350 – 102+660 Lungime: 33,31 km Valoare: 211,87 mil. Lei Constructor: SC Construct Mod SRL Stadiu fizic: 11,54% 14 DN 14, Sibiu – Medias – Sighisoara Lungime: 79,5 km Valoare: 201,943 mil. lei Constructor: Strabag Stadiu actual: 33% DN 66, Bumbesti Jiu - Petrosani Km 93+500 – 131+000 Lungime: 32,50 km Valoare: 185,64 mil. lei Constructor: Copisa Construct. Stadiu fizic: 0% SERBIA DN 56, Craiova – Galicia Mare Km 0+000 – 47+000 Lungime: 47 km Valoare: 187,79 mil. lei Constructor: DELTA ACM 93 Stadiu fizic: 7,13% Lungime: 231 km – etapa V de reabilitare DN Lungime – 770 km - Etapa VI de reabilitare DN DN 56, Galicia Mare - Calafat Km 47+000 – 84+020 Lungime: 37,02 km Valoare: 101,62 mil. lei Constructor: Mochlos SA Stadiu fizic: 0% 24

  28. REABILITARE DRUMURI NATIONALE ETAPA V CU FINANTARE BEI– PROIECTE IN PREGATIRE DN 76, Brad - Ionesti Km 30+436 – km 55+425 Lungime: 19,99 km Valoare: 105,61 mil. lei DN 76, Ionesti - Varfurile Km 55+425 – 69+350 Lungime: 13,93 km Valoare: 70,45 mil. lei DN 76, Soimus – Brad Km 0+000 – 30+436 Lungime: 30,44 km Valoare: 162,55 mil. lei DN 66, Rovinari – Bumbesti Jiu Km 48+900 – 93+500 Lungime: 44,60 km Valoare: 196,41 mil. Lei Constructor: Vegyepszer ZRT Stadiu fizic: contract execute lucrari in curs de semnare SERBIA Lungime: 109 km 22

  29. REABILITARE DRUMURI NATIONALE – CU FINANTARE DE LA BUGETUL DE STAT – PROIECTE IN EXECUTIE Deviere DN 29D, km 18+500 - km 20+816 Consolidare SR DN 18 km 3+522 – km 15+000 Ranforsare SR DN 28 km 69+657 – km 79+927 DN 29, Suceava – Botosani Lungime: 39,07 km Valoare: 84,78 mil. Lei Constructor: Spedition UMB / Tehnostrade / Arcada Comp. / Consitrans Stadiu fizic: 0% Ranforsare SR DN 24 km 191+035 – km 197+040 Reabilitare primara DN 15E km 6+275 – km 45+280 DN 2D, Focsani – Ojdula Lungime: 118,873 km Valoare: 737,19 mil. Lei Constructor: Spedition UMB Stadiu fizic: km 0+00 – 95+000: sector 1: 100% Sector 2: 80% km 95+000 – 118+873: 33% Ranforsare DN 73A km 0+000 – km 19+910 km 20+975 – km 69+340 Consolidare DN 74 km 56+895 – km 57+577 DN 73, Pitesti – Campulung – Brasov Lungime: 103,25 km Valoare: 342,07 mil. Lei Constructor: AZVI SA / Straco Group / Piomar Development / Tractebel Stadiu fizic:0% DN 67C, Bengesti – Sebes Lungime: 142,62 km Valoare: 1103,31 mil. Lei Constructor: Romstrade Stadiu fizic: 87% 2D DN 71, Baldana – Targoviste – Sinaia Lungime: 102,99 km Valoare: 171,89 mil. Lei Constructor: Spedition UMB/ Consitrans / Iptana Stadiu fizic: 0% 67C DN 72, Gaesti – Ploiesti Lungime: 67,197 km Valoare: 245.06 mil. Lei Constructor: Spedition UMB Stadiu fizic: 59% 71 72 Lungime: 768 km Program reabilitare/ modernizare DN DN 67B, Scoarta - Pitesti Lungime: 183,6 km Valoare: 442,26 mil. Lei Constructor: JV Strabag AG & Strabag Buc. & Delta ACM Stadiu fizic: 0% DN 73, Largire la 4 benzi intre km 7+000 si km 11+100 si drum de legatura cu DN 73D Lungime: 7,28 km Valoare: 138,71 mil. Lei Constructor: Genesis & Straco Stadiu fizic:64% Refacere sistem rutier DN 21 Lungime: 216 km Program reparatii capitale DN Refacere sistem rutier DN 22 Tulcea – Ovidiu km 227+000 – km 287+400 30

  30. REABILITARE DRUMURI NATIONALE CU FINANTARE NERAMBURSABILA DN 24 / DN 24B, Limita jud. Galati/Vaslui - Crasna – Albita Valoare: 279,01 mil. Lei Lungime: 101,8 km Stadiu actual: Lot 1: 51,0%; Lot 2: 59,0%; Lot 3: 61,0% DN 1H, Zalau – Alesd, Valoare: 244,10 mil. Lei Lungime: 69,334 km Stadiu actual: Lot 1 : 14,21% Lot 2: 42,43% DN6, Filiasi – Ciochiuta Lungime: 28,52 km Valoare: 82,67 mil. Lei Constructor: Asocierea Puentas Y Calzadas & Contrat Inginieria Y Orbas Stadiu fizic:44,46% • DN 6, Alexandria– Craiova • Valoare: 491,76 mil. Lei • Lungime: 131,99 km • Stadiu actual: • - lot1: 26,85%; • lot 2: 20,41%; • lot 3: 62,43% DN 5, Bucuresti– Adunatii Copaceni Valoare: 80,26 mil. Lei Lungime: 11,647 km Stadiu actual: 23,44% SERBIA Lungime: 315 km (FINANTARE FEDR) Lungime: 29 km (FINANTARE ISPA) 34

  31. VARIANTE DE OCOLIRE LA PROFIL DE DRUM NATIONAL

  32. VARIANTE DE OCOLIRE FINALIZATE JBIC Lungime: 26,67 km Valoare:53,39 MEUR V.O. Iasi Sud Lungime:5,84 km Valoare:20 MEUR ISPA/PHARE Lungime: 49,66 km Valoare: 102,65 MEUR V.O. Oradea Lungime:8,62 km Valoare:29,10 MEUR BUGET Lungime: 69,87 km Valoare: 276,19 MEUR V.O. Cluj Nord Est Lungime: 2,92 km Valoare: 6 MEUR TOTAL: 124,325 km Valoare: 366,29 MEUR Varianta de ocolire Cluj Est Lungime: 19,045 km Valoare: 98 MEUR V.O. Timișoara Sud Lungime: 12,08 km Valoare: 30 MEUR Varianta de ocolire Tecuci Lungime: 5,47 km Valoare: 3,2 MEUR V.O. Lugoj Lungime: 9,5 km Valoare: 29,2 MEUR Centura Ploiești Vest Lungime: 12,8 km Valoare: 30 MEUR V.O. Domasnea Lungime: 3,523 km Valoare: MEUR Fluidizare trafic pe DN1, km 8+100 – 17+100 si Centura rutiera in zona de nord a mun. Bucuresti Lungime: 20,43 km Valoare: 104 MEUR V.O. Caransebes Lungime:12,082 km Valoare:35,97 MEUR V.O. Mehadia Lungime:2,275 km Valoare:7 MEUR V.O. Dr. Turnu Severin Lungime:12,6 km Valoare:20MEUR V.O. Adunații Copaceni Lungime: 4,2 km Valoare: 4,5 MEUR SERBIA V.O. Craiova Lungime:14,10 km Valoare:23,39 MEUR

  33. VARIANTE DE OCOLIRE IN EXECUTIE Variante de ocolire in executie - Bugetul de Stat Lungime: 135 km Constructie variante de ocolire cu finantare ISPA Lungime: 16km Constructie variante de ocolire prin fonduri FEDR Lungime: 72 km 47

  34. VARIANTE DE OCOLIRE IN EXECUTIE-BUGETUL DE STAT Drum de centura in mun. Oradea, etapa a II-a: - Sector 8,62 km, benzile 1+2: Lungime: 8,62 km Valoare: 40,02 mil lei Constructor: Selenia Oradea & Drumuri Bihor Stadiu actual: 93,76% - Sector 8,62 km, benzile 3+4: Lungime: 8,62 km Valoare:75,86 mil. lei Constructor: SC Selenia Oradea Stadiu actual: 92,25% - Sector 5,2 km: Lungime: 5,2 km Valoare: 33,39 mil. lei Constructor: SC Selenia Oradea Stadiu actual: 53% -Sector 1,78 km: Lungime: 1,78 km Valoare: 0,21 mil. lei Constructor: UMB Spedition Stadiu actual: 0% Varianta de Ocolire Suceava Lungime: 14,43 km Valoare:240,45 Mil. Lei Constructor: SC CCF Iasi / Grup COLAS Stadiu actual:76% Varianta de Ocolire Radauti Lungime: 16,58 km Valoare:101,94 Mil. Lei Constructor: Spedition UMB Stadiu actual: 0% Varianta de Ocolirea mun. Iasi - Varianta Sud Lungime: 13,90 km Valoare:264,24 Mil. Lei Constructor: SC Vega 93 Stadiu actual: - tronson I: 100% • Fluidizare trafic pe DN1, km 8+100 – 17+100 si Centura rutiera in zona de nord a mun. Bucuresti • Obiect 5A: • Lungime: 4,65 km • Valoare: 61,16 mil. Lei • Constructor: FCC Construction +Alpine Mayreder Bau GMBH • Stadiu actual:95% • Obiect 6: • Lungime: 2,6 km • Valoare: 85,62 mil. Lei • Constructor: FCC Construction +Alpine Mayreder Bau GMBH • Stadiu actual: 90% • - Obiect 7: • Lungime: 3,10 km • Valoare: 112,48 mil. Lei • Constructor: Viacons / Aktor • Stadiu actual: 91,3% Varianta de ocolire Cluj Est - Tronson I - km 4+575 - 6+900 Lungime: 2,325 km Valoare: - contract 3001: 38,17 Mil Lei - contract 3005: 64,04 Mil. Lei Stadiu actual: contract 3001 -70% contract 3005 – 21% Drum de legatura DN 1A, ocolitoarea mica a municipiului Sacele - platforma Electroprecizie Lungime: 4,22 km Valoare:12,79 Mil. Lei Constructor: Asoc. Vectra Service SRL & Multimal Serv SRL Stadiu actual: 0% CRAIOVA Sud -Vest, DN 56 – DN 55 – DN 6 Lungime: 9,875 km Valoare:90 Mil. Lei Constructor: Asoc. SCT Buc. SA – Doprastav Stadiu actual: 0% Largire la 4 benzi centura Bucuresti Sud intre A1 si A2 Sector 1: Lungime: sector 1: 9,4 km Valoare sector 1: 139,39 Mil. Lei Constructor sector 1: Delta ACM + Tehnologica Radion + SC SIRD Stadiu actual: 30% Sector 2: Lungime: sector 2: 10 km Valoare sector 2: 143,47 Mil. Lei Constructor sector 2: Euroconstruct trading 98 +Romstrade Stadiu actual: 5% Sector 3: Lungime: sector 3: 12,52 km Valoare sector 3: 135,03 Mil. Lei Constructor sector 3: SC Straco Grup + Genesis + Mostobud Stadiu actual: 35% Modernizarea centurii rutiere a municipiului Bucuresti intre A1 - DN 7 si DN 2-A2:Sectiunea A1- DN 7 Lungime: 8,695 km Valoare:132,2 Mil. Lei Constructor: Asoc. SC DELTA ACM 93 & AZVIRT LLC & MAXIDESIGN Stadiu actual: 0% SERBIA Lungime: 135 km 47

  35. CONSTRUCTIE VARIANTE DE OCOLIRE CU FINANTARE ISPA Varianta de ocolire Caransebes Valoare: 35,97 mil. Euro Lungime: 12,08 km Constructor: Copisa Constructora Piranencia SA Stadiu fizic:98% - deschis traficului Varianta de ocolire Plugova Valoare: 57,66 mil. Euro Lungime: 3,5 km Stadiu: fara finantare SERBIA Lungime: 16km 51

  36. CONSTRUCTIE VARIANTE DE OCOLIRE PRIN FONDURI FEDRProiecte in executie Carei Lungime: 10,45 km Valoare: 47,72 mil. lei Constructor: Grupo Empresarial Magenta – Assignia Infrastructuras SA – Transmir SRL Stadiu: 0% Sacuieni Lungime: 7,62 km Valoare: 39,72 mil. lei Constructor: IDECON S.A.U Stadiu: 0% Brasov, Lot I: Tronson 1, DN1-DN11 Lungime: 7,292 km Valoare: 160,81 mil. lei Constructor: ALPINE Bau GmbH Stadiu: 13,7% Lot II, Tronson 3, DN11-DN13 Lungime: 6,34 km Valoare: 121,01 mil. lei Constructor: Vectra Service Stadiu: 37% Tecuci Lungime: 6,945 km Valoare: 60,78 mil. lei Constructor: Sociedade de Construcoes Soares Da Costa S.A. Stadiu: 0% Craiova Sud-Est Lungime: 6,285 km Valoare: 44,53 mil. lei Constructor: SECOL SpA / SECOL Romania Stadiu: 2,4% Caracal Lungime: 10,35 km Valoare: 55,15 mil. lei Constructor: Romstrade Stadiu: 9,21% Alexandria Lungime: 13,27 km Valoare: 65,52 mil. lei Constructor: Shapir Structures 1991 Stadiu: 40,2% Mihailesti Lungime: 3,18 km Valoare: 33,39 mil. lei Constructor: CONTRAT INGENIERIA Y OBRAS Stadiu: 0 SERBIA Lungime: 72 km 53

  37. CONSTRUCTIE VARIANTE DE OCOLIRE PRIN FONDURI FEDR –CU STUDII DE FEZABILITATE SI HOTARARI DE GUVERN Campulung Moldovenesc Falticeni Bistrita Pascani Targu Frumos Alesd Nord Vatra Dornei Toplita Husi Dej Roman Gheorghieni Alesd Sud Bacau Stei Huedin Miercurea Ciuc – Ciceu - Siculeni Sighisoara Adjud Targu Mures Barlad Fagaras Tusnad Timisoara Sud Galati Pucioasa Titu Targoviste Buftea Targu Jiu SERBIA Budesti Filiasi Rosiorii de Vede Mangalia Lungime: 406 km 55