1 / 26

Professor Rudi Klein, Barrister Chief Executive, Specialist Engineering Contractors’ Group

Professor Rudi Klein, Barrister Chief Executive, Specialist Engineering Contractors’ Group. Society of Construction Law Oxford Region. 23 April 2009. “Construction Act Reforms”. How did we get here?.

Rita
Download Presentation

Professor Rudi Klein, Barrister Chief Executive, Specialist Engineering Contractors’ Group

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Professor Rudi Klein, Barrister Chief Executive, Specialist Engineering Contractors’ Group Society of Construction LawOxford Region 23 April 2009 “Construction Act Reforms”

  2. How did we get here? • March 2004: Gordon Brown (as Chancellor) announces review of Construction Act against background of continuing payment problems. • Original proposal was for an RRO. • Formal consultations in 2005 & 2007.

  3. Draft Construction Contracts Bill published for consultation in July 2008. • Revised Bill receives 1st Reading in the House of Lords on 4 December 2008 (some changes from original draft)

  4. “Our amendments….will create greater certainty and clarity of cash flow for all in the construction supply chain” (emphasis added). Baroness Andrews in 2nd Reading debate in House of Lords on 17.12.2008

  5. AMENDMENTS TO THE PAYMENT PROVISIONS

  6. CURRENT WEAKNESSES • S.110(1)(a) Contracts must have adequate mechanism for determining what payments become due and when • This is essential for operating ss.111 & 112 (withholding and suspension)

  7. “The absence of….a means for resolving deadlock….renders inadequate the machinery for determining when payments are due”. Lord Macfadyen in Maxi Construction v Merton Rolls [2001] CILL 1784

  8. Likelihood is that majority of contracts do not have an adequate mechanism Scheme not helpful: there is only a list of what may be included in interim payments together with due dates and final payment dates CURRENT WEAKNESSES

  9. THE CHANGESNEW S.111 PAYER MUST PAY NOTIFIEDSUM ON OR BEFORE THE FINAL DATE FOR PAYMENT

  10. NOTIFIED SUM • The sum specified in notice issued by: • Payer • Payee • Payee, where payer fails to issue notice

  11. Notices must comply with new s.110(A) – replacing s.110(2) requiring payer to issue payment notice

  12. NOTICE REQUIREMENTS • Contracts to indicate which party to issue notices • Notices to be issued no later than 5 days after payment due date • Amount of sum considered due must be stated together with basic calculation

  13. PAYER’S FAILURETO ISSUE NOTICE • Payee can issue notice instead but final date for payment extended from expiry of 5 days • But final date for payment intact if payee issues application before payment due date (provided such application is required/ permitted by contract)

  14. NOTICE TO PAY LESS • Payer can issue notice of intention to pay less than notified sum • Notice must indicate sum payer considers due on date notice is served and basis of calculation • Must be given no later than the “prescribed period” before date for payment

  15. Payment ProcedureOption A Notified sum to be discharged (on/before final day for payment Payer/payee to issue notified sum 5 days Final Date for payment Payment due date

  16. Payment ProcedureOption B Payer/payee issues notified sum Payer issues Reduction Notice Reduced notified sum discharged 5 days Prescribed period Payment due date Final date for payment

  17. Payment ProcedureOption C Extended by 3 days Payee operates default procedure Payer fails to issue notified sum 5 days 3 days Final date for payment Payment due date

  18. CONDITIONAL PAYMENT PROVISIONS Adequate mechanism requirement not satisfied where payment made conditional on performance of obligations under another contract or decision by any person as to whether such obligations have been performed [New sub-section 110(1)A]

  19. CONDITIONAL PAYMENTPROVISIONS (2) • Will 110(1)(A) actually outlaw pay-when-certified clauses? • Will 110(1)(A) conflict with current s.113? • Pay-when-paid exemption in s.113 not removed

  20. OTHER CHANGES • No requirement to pay sum due where payee became insolvent after prescribed period and contract permits payer not to pay sum due in this event (prompted by Melville Dundas case) • Improvement to suspension (s.112) allowing payee to recover reasonable compensation for “costs and expenses reasonably incurred” during suspension • Payee can suspend any or all of his contractual obligations

  21. AMENDMENTS TO ADJUDICATION PROVISIONS

  22. S.107 – REQUIREMENT FOR CONTRACTS TO BE IN WRITING(RJT Consulting Engineers v DM Engineering (2002) BLR 217 • S.107 repealed: oral or oral/partly written contracts within scope of Act • BUT provisions relating to adjudication (8 “compliance points”) must bein writing to comply with s.108

  23. SLIP RULE(New s.108(3)A) • Contracts must include provisions that adjudicator has power to correct and clerical/ typographical error arising by accident/omission • What about time limits on exercise of power?

  24. COSTS IN ADJUDICATION(New 108A) • Agreement allocating “costs relating to the adjudication” ineffective unless made in writing after giving notice of intention to refer the dispute to adjudication • This also refers to the fees and expenses of the adjudicator

  25. VERDICT • Payment provisions “getting there” but are very complex and still “lean” towards payer • Abolition of s.107 welcome • Abolition of Bridgeway v Tolent welcome • What about adjudicator’s fees and costs? • Need for single adjudication procedure but is this too intrusive into freedom of contract?

  26. Professor Rudi Klein, Barrister Chief Executive, Specialist Engineering Contractors’ Group Society of Construction LawOxford Region 23 April 2009 “Construction Act Reforms”

More Related