SPS Upgrade Plans.
E N D
SPS Upgrade Plans The invaluable input from E.Shaposhnikova, G.Rumolo, M.Meddahi, R.Garoby, K.Cornelis, J.M.Jimenez, M.Taborelli, E.Montesinos, Y.Papaphilippou, W.Höfle, L.Jensen, T.Bohl, R.Losito, M.ArruatM.Gourber-Pace, S.Mathot , H.Bartosik, D.Manglunki and all other members of the LIU project is gratefully acknowledged. B.Goddard for the LIU-SPS team List of actions and planning of implementation Studies Impact on other users SPS performance for LHC and other users in the different scenarios Potential risks
Overview • Targets and assumptions • Baseline hardware modifications • Design studies • Key milestones, decision points and planning • Technical issues • 2012 MD and activities • Expected performance potential for LHC and other users • Potential risks • Ions • Conclusion
p+: Targets from HL-LHC Target: 250-300 fb-1 per year O.Brüning, HI-LUMI event 16-18 November 2011
Extracted from SPS • Requires slightly more: LHC losses and blowup • 2.2×1011 p+/b in 2.3 mm at 25 ns • 3.6×1011 p+/b in 2.7 mm at 50 ns
Assumed deliverables from SPS • For 2012 • Towards ultimate intensity for 50 ns, in smaller than nominal emittance • Nominal intensity for 25 ns, in nominal emittance • Studies above ultimate intensity with 50 ns • Studies with small emittance, nominal intensity for 25 ns • Period LS1-LS2 • Towards lower emittances for nominal intensity for 25 ns • Towards lower emittances for twice nominal intensity for 50 ns • Period LS2-LS3 • Recover pre-LS2 performance in Y(LS2+1) • Towards 2.3x1011 p+/b and 3.2 mm emittance for 25 ns beams • Towards 2.7x1011 p+/b and 2.7 mm emittance for 50 ns beam • Studies with lower emittances/higher intensities • After LS3 • Approach HL-LHC requirements for both 25 and 50 ns beams
Planned baseline upgrades • Double power of 200 MHz RFsystem (LSS3, BA/BB3); • Electron cloud mitigation – in-situ aC coating of all dipole and quadrupole vacuum chambers; • Major upgrades of MOPOS and BLMs, plus other new or upgraded BI systems; • New High Bandwidth transverse feedback system; • Upgraded pickups for present high power damper system; • Upgraded passive protection devices in extractions and transfer lines TI 2 and TI 8 (relocation plus new devices); • Improved vacuum sectorisation – arcs and near critical equipment; • Complete the impedance reduction of MKE and dump kickers.
Studies and decision dates • Full review of ecloud mitigation option: end 2012 • Review measurement, technology and simulations • Decided and endorse full aC coating of machine • Change to low gamma-transition Q20 optics: end 2012 • May need extra bumpers for LSS1 injection chicane • New scraper design study: end 2012 • Localise losses and improve reliability • New MKE/extraction study/prototyping: mid 2013 • Further reduce kicker impedance with totally new kicker and extraction design • Beam dump design study/prototyping: mid2013 • Safe absorption of higher brightness beams • Removal/mitigation of operational limitations
LIU-SPS related consolidation • MOPOS and wirescanner consolidation • Take into account LIU-SPSrequirements, shared resources • MKDV switch and generator consolidation • Coordinate with eventual beam dump upgrade • 200 MHz driver/controls & Faraday cage consolidation • Coordinate with 200 MHz upgrade, LL upgrades • 800 MHz upgrades • Coordinate with beam dynamics needs and 200 MHz upgrade • Possible main dipole coil consolidation • Coordinate with aC vacuum chamber coating • Other high impact consolidation activities to consider • LV/control recabling campaigns • Infrastructure work
Assumed constraints and planning • Constraints (working assumptions) • Injectors OFF in 2013, for 12 months • Injectors OFF in 2018, for 12 months (min. for SPS 200 MHz) SPS aC coating, 200 MHz upgrade completed PSB H- injection could be available to install IEFCWS 2012 Linac 4 ready LS1 for injectors LS2 for injectors 2019 2012 2013 2014 2015 2016 2017 2018 Injectors commissioned
Outline of LIU-SPS planning LS1 LS2
Outline of LIU-SPS planning LS1 LS2
Technical issues and progress • ecloud– amorphous carbon coating • Feasibility of Hollow Cathode method demonstrated in 2011 • Confidence in lifetime, handling and static vacuum behaviour • Treatment of vacuum chambers inside magnets – no magnet opening • Definition of extra sectorisation completed • For 2012, explain dynamic pressure rise (test zone installed) • Beam induced heating/outgassing of components • Still limitationfor high duty factor MD/LHC filling cycles • Complete MKE serigraphy should help (after MKE conditioning...) • Reviewing general impedance reduction (kickers & other elements) • 200 MHz: good progress with building, services and amplifiers • Shorter main couplers needed to fit new layout in LSS3 • Design needs to be launched, prototyped and validated • Transverse damper relocation to LSS3 not possible. Stays in LSS2. • No space available with 200 MHz rearrangement
Technical issues and progress • Beam instrumentation • Specifications for upgrades being defined (dynamic ranges, bunch by bunch, presently foreseen upgrades/new instruments, LIU requirements) • Half-day review of BI deliverables with LIU plus experts (April 2012) • OP and other SPS users requirements being taken into account • Dump limitations for MDs and high duty factor operation • Outgassing of TIDVG affecting MKP, and forbidden zone 37-105 • Extra differential pumping and sectorisation planned • Not very strong limitation for LIU – to be studied in 2012-13 • Exit windows and TEDs • Intensity/transverse emittance limits to be defined (I, e) • Compensation of injection doglegs for Q20 optics • Test of principle in 2012; finalise requirements for any additional bumpers • High bandwidth damper development • Need to demonstrate closed-loop and damping of head-tail instability in 2012 • Then specification and prototype construction (HBW pickups and dampers). Short timescales to be ready for end 2014.
MD studies for 2012 • Scrubbing tests in week 13 • Key question: can we scrub SPS below SEY1.3; can scrubbing replace coating? • Efficiency of scrubbing with uncaptured beam • Most interesting techniques not available(5 ns or 10+15 ns spacings from PS) • Monitor and qualify scrubbing under different beam/chamber conditions • Validate simulation models on scrubbing times (like for LHC) • Some new setups for validation of aCcoating • Beam dynamics and beam quality • Q20 optics deployment • Q20 beam transfer, including injection into LHC • Longitudinal instabilities in a double RF system • Split tunes (20, 26), coupling correction • Instabilities (TMCI, ECI) • Space charge and working point studies • PS-SPS transfer studies • High bandwidth feedback (close feedback loop and damp head-tail modes) • Impedance identification • Emittance preservation (across injector complex and LHC) • Some optimisation of MD time proposed with respect to 2011 • MD follow-up meetings and prioritisations in frame of SPSU-BD WG • More frequent (shorter) MD blocks more continuous effort on Q20 optimization • 5 day dedicated block for scrubbing studies
Expected performance potential • Longitudinal instabilities & beam loading: after upgrade, expect factor 2 intensity possible w.r.t. 2011 • 2.3×1011 p+/b for 25 ns, and >3.4×1011 p+/b for 50 ns • Main unknown is beam stability with high intensity (combination of single- and coupled-bunch effects) • ecloud: should be solved after LS2 with aC coating of main magnets • HBW feedback could help fight against vertical ECI • Heating of extraction kickers: should be solved after LS1 • Expect limit to be at least twice present beam power (2.3×1011 p+/b for 25 ns) • Outgassing of dump and impact on injection kickers MKP vacuum • Effect mainly limitation for scrubbing and setting up, rather than LHC filling • TMCI • Measured to be above about 3.5×1011 for single bunch on Q20 optics • HBW damper as possible additional mitigation • Space charge limits • Expect to be able to exceed DQv of -0.15: 3.5×1011 p+ in 2.8 mm emittance
Expected situation after upgrade • If all upgrades work as planned, SPS fairly well matched to requirements • SPS should not be a limit for 25 ns beam for HL-LHC • Need to increase DQv above -0.15 towards -0.2 for 50 ns beam
Upgrade impact on other users • Mandate is to “not reduce performance for other users” • No negative impact on any other users identified to date • Many positive effects expected: • Extra RF 200 MHz power • New/upgraded beam instrumentation (other beams being considered in specifications) • Vacuum sectorisation • Impedance reduction • HBW feedback and damper upgrade • Possibly also Q20 or split-tune optics
Risks and concerns • ZS sparking (LSS2 electrostatic septum) • Interference with slow extracted FT beams; • Difficult to solve – ‘ppm’ main voltage modulation being studied; • Test ZS tank in LSS6 – now equipped with extra impedance shielding; measurements to make in 2012; • Last resort would be ZS off and retracted during LHC beam, which strongly impacts beam to North Area. • Dynamic vacuum behaviour of aC coating • 16 m test chambers just installed; studies in 2012 to answer this • Unexpected problems with heating of other elements • New study/analysis to be made in 2012 using updated beam parameters • Planning of LS2 ‘big bang II’ shutdown • Already concern about accumulation of activities (e.g. magnet coating and LSS3 RF 200 MHz) – planning starting • Project resources – securing manpower • Large ramp-up in activity and spending needed from 2013 onwards
Key 2012 LIU-SPS activities • 200 MHz upgrade • Civil engineering studies: in progress • Amplifier market survey: launched • New main coupler: to start • ecloud: prepare for aC coating in LS1 (4 half-cells) • Industrialisationof aCon MBA chambers: continuing • Answer question of dynamic pressure rise: in progress • Kicker impedance reduction/ beam induced heating • Preparation (serigraphy) of final 1 MKE: in progress • Impedance/heating review and benefit analysis: to do • High bandwidthfeedback • Closed-loop damping studies and design report: to complete (LARP) • Existing transverse feedback upgrade • Technical specification on new pickups: to define • BI upgrades • Specifications with BI group and experts: to finalisefollowing specification review, to have clear milestones for LS1 and LS2 • Implementation: to start • Transfer line protection systems upgrade • Design study: in progress • Other design studies • New scraper: in progress • Beam dump, new MKE/extraction: to start • 2012 MD
Ions • Production scheme moved away from original ‘bunchlet’ baseline • IBS and space charge effects less serious than anticipated • Focus is now on increasing number of bunches for Pb-Pb • 50 ns bunch spacing • Rise time of SPS injection kicker MKP to be minimised – possible upgrade? • Issues in SPS also include RF Noise, IBS & DQ on flat bottom • First batch suffers 40 more seconds on flat bottom: lower intensity/bunch, transverse emittance blowup • Ions also being considered explicitly in all BI upgrades • New ion species also to be considered: Ar, deuterium • LLRF may require some upgrade
Conclusions • LIU-SPS upgrade baseline well defined for p+ • Majority of work in tunnel for LS2 • Implementation started for RF 200 MHz system • Other technical aspects progressing reasonably well • Co-existence with other activities and consolidation work to organise and manage carefully • LS2 shutdown planning a key aspect: possible bottlenecks like transport to investigate • Main planning defined to 2019 • Some changes inevitable as progress/delays/design choices occur • 2012 key activities identified • Performance potential from upgrade • For LHC, approaches HL-LHC requirements but does not yet meet them • For other users, will be positive in many respects • Risks and concerns • ZS sparking, understanding of aC coating vacuum behaviour, beam induced heating, LS2 planning, adequate manpower
Known limitations E.Shaposhnikova, Chamonix 2011
ecloud mitigation • HC sputtering to deposit amorphous carbon (aC) layer • Large reduction of SEY below ecloud threshold • Coating in dedicated workshop (ECX5) 4-6 magnets per day
SPS longitudinal instabilities • Longitudinal stability: 25 ns beam unstable at 2-3e10 p+/b • Presently mitigated with long. emittance blowup (0.6 eVs) and 800 MHz • Need 0.9 eVs for 25 ns stability with twice nominal Ib (Q26) • Maybe gain from lower impedance (200 MHz and kickers), x2 800 MHz V • Would be very beneficial to transfer longer (e.g. 1.8 ns) bunches to LHC (but need to mitigate capture losses in LHC) -> MD studies needed • Q20: instability thresholds higher, but need smaller el to get same bunch length for given VRF • After upgrade, expect factor 2 intensity possible wrt 2011 • 2.3×1011 p+/b for 25 ns, and >3.4×1011 p+/b for 50 ns • Main unknown is beam stability with high intensity (combination of single- and coupled-bunch effects)
SPS beam loading • SPS 200 MHz: x2 power, 46 (shorter) cavities, -20% impedance • Will allow 10 MV at extraction for 3 A RF current (now 1.5 A) • Need to operate existing power plants in pulsed mode (0.751.05 MW) • After upgrade: same voltage available as now (if pulsed) for 2.3e11 p+/b (25 ns) and 4.6e11 p+/b (50 ns). • With larger emittance more VRF needed for same bunch length • Will anyway have 10% longer bunches for 2x nominal I, with 10 MV E.Shaposhnikova
RF 200 MHz reorganisation • Increase power to 6 MW into 6 shorter cavities (from present 4) to give 10 MV required at ultimate intensity • Needed for longitudinal stability (increase emittance from 0.6 eVs) • Reduces impedance by 20% • Big job: new BC3 building, new LSS3 layout, 26.5 MCHF over 7 years