Introduction of theEUSO-BALLOON 9th Progress MeetingNaples, November the 9th, 2012 Guillaume Prévôt, Sylvie Dagoret and Peter vonBallmoos EUSO-BALLOON, 9th progress Meeting 2012
first light / first flight first flight in spring 2014 from Timmins (48°34' N, 81°22' W) CNES campaign starts March 1st 2014 => EUSO BALLOON is to be flight-ready in Timmins by end of february flight scenarios have been elaborated by Jean Evrard for the december flight review => we can make it, but must stay on tight schedule
Timmins EUSO-BALLOON, 5th progress Meeting 2012
the lenght of the astronomical night at Timmins (48°34' N, 81°22' W)
EUSO-BALLOON Dashboard 9.11.2012meet dec DR PDM - MAPMT - EC : Front Boards OK , EC-Units OK, Proto M OK - EC ASIC - EC Proto - HVPS 1&2 / SWITCHES : prototypes under test - PDM Board - meca : Top: manuf.. Bottom follows, modif ok except HVPS DP- CPU, CCB, and communication (CLOCK) : OK - HK, testsDP / HK - LVPS and interfaces - S/W CPU : Low level protocol and interfaces, other S/W Architecture - Electrical : "interior"/"exterior", design frozen - Mechanical, design frozen, study on struct. integrity going - Thermal, ongiong, first results Lenses - manufacturing on track AIT/AIV - planning started IRCAM - position on gondola, safety constraints Documents - 1st versions for dec DR have been read by Pascale
EUSO-BALLOON Dashboard 12.10.2012meet dec DR PDM - MAPMT : Gain measured - EC : Front Boards OK , EC-Units OK, Proto M OK - EC ASIC : brazing process suspected - EC Proto E waiting for Matra - HVPS 1&2 / SWITCHES : prototypes under test - PDM Board under tests in Corea, expected at LAL mid-Nov - meca : Top: manuf.. Bottom follows, modif ok except HVPS DP- CPU, CCB, and communication (CLOCK) : OK - HK, testsDP / HK - LVPS and interfaces - S/W CPU : Low level protocol and interfaces, other S/W ? Architecture - Electrical : "interior"/"exterior", design frozen - Mechanical, design frozen, study on struct. integrity going - Thermal, ongiong, first results Lenses - manufacturing on track AIT/AIV - planning started IRCAM - position on gondola, safety constraints, Documents - very little is written up for the december DR
EUSO-BALLOON Dashboard 9.11.2012meet dec DR PDM - MAPMT - EC : Front Boards OK , EC-Units OK, Proto M OK - EC ASIC - EC Proto - HVPS 1&2 / SWITCHES : prototypes under test - PDM Board - meca : Top: manuf.. Bottom follows, modif ok except HVPS DP- CPU, CCB, and communication (CLOCK) : OK - HK, testsDP / HK - LVPS and interfaces - S/W CPU : Low level protocol and interfaces, other S/W Architecture - Electrical : "interior"/"exterior", design frozen - Mechanical, design frozen, study on struct. integrity going - Thermal, ongiong, first results Lenses - manufacturing on track AIT/AIV - planning started IRCAM - position on gondola, safety constraints Documents - 1st versions for dec DR have been read by Pascale
Since the last progress meetingAPC Paris, October the 12th • The electrical prototype has been received by LAL (beforepotting) • EC ASIC cardhas been sucessfullytested (before data transmission tests) • Wefixed the design of PWP • The delivery of 19 missingMAPMTs+ UV filterson going (december 2012) • Cockroft Walton and switches prototypes have been testedat APC (and a bit modified to beadapted to MAPMTs) • PDM boarddelay : 6 PCBsproduced and partiallytested, deliveryat LAL isscheduled for end of November, we are tryingnow to organize EC-ASIC/PDM Board communication tests • DP tests are undergoingin Naples • Thermal analysis has been done • Thedocumentation iswell-advanced (architecture documents, Technicalspecification for CPU software , PAIE, updates of Phase A documents, ICD, etc.) EUSO-BALLOON, 9th progress Meeting 2012
Since the last progressmeeting (2) • PWP design defined See Hector Prieto’s presentation • Ec_ASICs electrical tests has been done See Pierre B.’s presentation • CW and switches tests has been done See PhGoro.’s presentation • Writing of the electrical architecture Document See Michel’s presentation • Writing of the mechanical architecture Document See Peter’s presentation • Thermal architecture analysis (Document on going) See Gustavo’s presentation • Tests of HK & LVPS communication • Phase A documents actualized See Andrea‘s presentation • Writing of the CPU software Document See Francesco’s presentation EUSO-BALLOON, 9th progress Meeting 2012
Since the last progressmeeting (3) • Interfaces Control Document has been defined and commenced See Sylvie’s presentation • PAIE Document (about integration) well advanced See Sylvie’s presentation • Verification matrix to the technical requirements has been defined See Guillaume’s presentation • List of the steering committee’s actions See Guillaume’s presentation EUSO-BALLOON, 9th progress Meeting 2012
The work to bedone • Ending the work on the interfaces and writing the related documentation (mechanics I/F, cables, pinoutassignment, etc.) • Ending the communication tests • Performing the HK / LVPS Boardscommunication tests beforemid-december • Performing the CCB / PDM Board communication tests beforemid-december • Organizing and performing the EC-ASIC / PDM Board communication tests beforemid-december • Defining the software specifications • Testingon the EC electricalprototype before end afterpotting • Writing the last versions of the documents EUSO-BALLOON, 9th progress Meeting 2012
Questions and Problems • Expected progresses on PDM board ‘stand alone’ tests • Expected progresses on PDM board / Ec-ASIC communication tests • Expectedprogresses on PDM board/ CCB communication tests EUSO-BALLOON, 9th progress Meeting 2012
The Goal of this meeting • Discussing the last programmatic aspects before CDR Review • Discussing the expectation of the different documents written for the CDR Review • Listing actions EUSO-BALLOON, 9th progress Meeting 2012