An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Early Offshore Petroleum Development Cost Estimates Using GIS Narmina Lovely, GEOG 596A Advisor: Patrick Kennelly

  2. Outline • Introduction – the Business Challenge • Summary of Discovery to Development Process • Spatial Characterization of Prospects and GIS Methodology • Engineering Characterization of Prospects • Integration of GIS with Other Applications • Presentation of Results • Conclusion and Future Steps

  3. The business challenge • Estimate petroleum development costs to guide exploration program • Automate, standardize and codify engineering cost estimation

  4. The business challenge While X has bigger volume, Y might be a better value 50$ a barrel 15$ a barrel TD: 20000 WD: - 4964 VOL: 250 AGE: Miocene Pressure: 24480psi HC Type: Oil TD: 25000 WD: - 5365 VOL: 310 AGE: Miocene Pressure: 28378psi HC Type: Oil

  5. Appraisal well Exploration well Exploration well Appraisal well Discovery to Development Process Exploration • Exploration prospect inputs • Outline of prospect area • Well location • Reserve Size • Water Depth • Target Depth • Fluid Type • Expected Pressures • Output is well cost and well timing Appraisal • Number of appraisal wells determined by reserve size • Output is well cost(s), seismic cost, and timing Field Development • Based on logic from tool which will be seen in upcoming slides • Output is all development costs and production forecast for life of field

  6. 3000 feet 30o Spatial characterization of developments • Well Spacing Calculation • Bottom Holes Placement • Maximum Drill Reach Calculation • Drill Center Distribution • Gathering System Alignment for Multi- drill Center Scenarios • Generation of Tie-Back Options

  7. Spatial characteristics of developmentsWell Spacing Calculation INPUTS: Hydrocarbon type Prospect Area and Shape Maximum Volume per Well

  8. Spatial characteristics of developmentsBottom Holes Placement

  9. 3000 feet 30o Spatial characteristics of developmentsMaximum Drill Reach Calculation INPUTS: Target Depth Water Depth Maximum drill reach Spatial Well Distribution

  10. Spatial characteristics of developmentsDrill Center Distribution

  11. Spatial characteristics of developmentsGathering System Alignment for Multi-drill Center Scenarios INPUTS: Center of the Prospect Drill centers Spatial Distribution

  12. Spatial characteristics of developmentsGeneration of Tie-Back Options • INPUTS: • Hydrocarbon Type • Platforms Spatial • Distribution

  13. Engineering characterization of prospects Engineering characterization of developments • a. Drilling performance and well types • b. Completion technologies and configurations • c. Production facilities and tie-backs • d. Additional production parameters

  14. 3000 feet 30o Engineering characterization of prospectsDrilling Performance and Completion Technologies • Drilling performance (days to drill 10,000ft) • Varies by geologic target • Well tangibles vary by geologic target • Drill rig day rates ($/day) – company rates • Rig type • MODU or Platform Rig • Type of Well • Exploration, appraisal, or development • Completion type • Wet tree or dry tree • Maximum drill reach • Establishes number drill centers required

  15. Typical Wet Tree Development Engineering characterization of prospects Production Facilities and Tie-backs • Wet Tree Local FPS host cost a function of: • Peak field production • Water injection requirements • Number of wells • Shut in Tubing Pressure • Water depth • Subsea tie-back to existing FPS host • Oil – 25 mile radius • Gas – 75 mile radius • Subsea cost a function of: • Number of wells • Number of drill centers • Distances between drill centers • Shut in Tubing Pressure • Dry Tree local FPS host cost a function of: • Peak field production • Water injection requirements • Drill rig requirements (Dry tree development only) • Number and type of wells • Shut in Tubing Pressure • Water depth

  16. Engineering characterization of prospects Additional Production Parameters • Field production forecast is the sum of individual wells brought online per drilling and completion schedule. Well forecasts utilize initial rate, reserves per well, and decline by geologic age. • Water injection wells are the ratio of producing wells with well depth consideration. • Optimize facility options (dry tree versus Subsea tie-back) based on number of wells at each drill center • Export pipeline cost included to existing FPS’s within 30 miles or nearest one • Matches facility cost spending profile with first oil date • Facility abandonment and salvage cost included

  17. Presentation of results Organization of results Engineering characterization of developments Spatial characterization of developments ArcGIS & ET GeoWizards MS Excel MS Access PowerPoint VBA Automation GIS and Information Technology applied Flow of Automation

  18. A Organization of results

  19. BP CONFIDENTIAL Indicators(NRI) Success Risked Ps: 25% IRR % NPV7 ($m) % Disc. payback (yrs) IE (NPV/WI capital) Capital ($m): Gross WI:9% E&A Drilling: 607 57 Dev drilling: 11,788 1,107 Facilities: 3,853 362 Cap OH: Total: 16,248 1,525 Subsurface Data: Gross recoverable mmboe 250 Net recoverable mmboe 63 Reserves per well mmboe/well 9 Number of producers 27 Number of injectors 9 ProspectXSS Development w Semi Host

  20. Conclusions • Manual process was automated for a batch of prospects • Took days for each prospect manually, a matter of minutes automatically with favorable results • ARCGIS was a key technology to automate the calculation • Integration of GIS Technology with Access, Excel and PowerPoint • Generated results for hundreds of prospects for comparison purposes: 800+ prospects, 2,300+ development options • Future Steps: • Incorporate an economic model for the output • Simplify cost estimate updating • Incorporate portfolio analysis toolkit

  21. Acknowledgements • BP Engineering Team - Engineering Characterization of developments • Charles Fried - Flow of Automation between GIS and Excel Engine • Patrick Kennelly – Penn State Program Advisor