220 likes | 231 Views
Learn about NDOT's Pioneer Program addressing transportation funding and innovative delivery projects like DB, CMGC, and P3. Understand the guidelines, processes, and benefits of traditional vs innovative delivery methods.
E N D
Pioneer Program • The Pioneer Program is a result of NDOT’s efforts to find solutions to our transportation funding shortfall and to meet the state's growing needs • All innovative delivery projects • Design Build (DB) • Construction Manager/General Contractor (CMGC/CMaR) • Public Private Partnerships (P3 - DBF, DBFOM, etc)
Unsolicited Proposal Advisory Committee Director Pioneer Program Director Deputy Director–Chief Eng Pioneer Program Manager (Project Management Chief) External Consultants Technical, Legal, and Financial Project Manager Project Manager Organizational Structure Transportation Board Project Review Team Development Team Implementation Team
Pioneer Program Guidelines • Detailed internal project development and delivery processes • Delivery method selection • Procurement: process, roles and responsibilities and required approvals (Board, FHWA, Director, etc) • Stipend criteria
Traditional vs Innovative Delivery Construction Preliminary Design Final Design Bid DBB Preliminary Design Procurement Final Design (Risk & constructability) Legend DB Construction NDOT Contractor Preliminary Design Procurement Final Design CMGC Contractor Input (Risk & constructability) Construction Time Savings
NRS 408Design Build • Costs less than another method; or • Completed sooner than another method; or • Project is unique, highly technical and complex • Transportation Board/FHWA approvals required • One project per fiscal year between $5 - $20 Million
ProjectsDesign Build • NDOT design build contracts • I-15 North Las Vegas - Complete • I-15 South Las Vegas – Under construction • I-15 ITS - In procurement • I-15 Mesquite - In procurement • I-80 Reno - In procurement
Construction Manager / General Contractor (CMGC) Plan NDOT Design NDOT Design Consultants Contractor Negotiate GMP GMP Not Achieved Build Contractor Bid Build
CMGC Process Max Price Partnering
NRS 338.169CMGC • Enabling legislation exists • Public Works Board • Local cities & counties • Excludes NDOT • UDOT, ADOT, CalTrans • FHWA – Every Day Counts Initiative • Assembly Bill 69
Design & Constructability • Improve constructability, improve quality, reduce change orders and overruns, identify risk and assign an owner • Less time/detail required to communicate design (DB) • NDOT owns/controls design (CMGC)
Innovation • NDOT can select innovation independent of contractor experience or abilities • Contractor participation is expected to encourage innovation • Contractor participation is expected to moderate the risk of new technology innovations
Schedule • Procurement takes time • Overall less time in design and construction • Design is tailored to contractor’s abilities • Construction can begin before design is complete • Good for long lead items • Phased contract • MOT improves with contractor input
Risk • Contractor will help identify and manage risks • Transfer some risks to contractor & shared risks • Allocation of risk is based on party that is best equipped to handle that risk
Public Relations • Faster delivery time • Improved Quality • Greater opportunities for innovation • Reduced impacts to the traveling public
Cost • Contractor input into MOT and utilities should reduce cost • Risk transfer comes with a cost • We are paying for contractor involvement during design phase • Stipend costs
The P3 Spectrum Fully Public Fully Private Build-Operate-Transfer Design-Build-Finance Operate-Maintain Design-Build Finance Operations & Maintenance
How are P3s Different?Public Private Partnerships • Delivered in different ways • Design, Build, Operate, Maintain, Finance • Long term agreements • Tolling • Risk transfer • Payment structure • Unsolicited vs solicited proposals • Senate Bill 83
Why is the Pioneer ProgramImportant to you? • Coming to a project near you • Different roles and responsibilities for everyone
Future StepsPioneer Program • Obtain approval of state legislators this Spring to utilize CMGC, solicit for P3 projects and allow tolling • Immediately move forward with the next stage of project development (pending legislative approval) • Scoping, screening, approval, procurement, etc.