1 / 32

Commonwealth of Kentucky Transportation Cabinet Department of Highways - District 5

Commonwealth of Kentucky Transportation Cabinet Department of Highways - District 5 The Slow Uphill Climb Matt Bullock, P.E. Chief District Engineer. Highway Maintenance Work District 5. Signs Pothole Patching Lighting Mowing Guardrail Striping Drainage Signals

alida
Download Presentation

Commonwealth of Kentucky Transportation Cabinet Department of Highways - District 5

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Commonwealth of Kentucky Transportation Cabinet Department of Highways - District 5 The Slow Uphill Climb Matt Bullock, P.E. Chief District Engineer

  2. Highway Maintenance Work District 5 • Signs • Pothole Patching • Lighting • Mowing • Guardrail • Striping • Drainage • Signals • Agreements with Local Agencies (Non-Interstate)

  3. Panel Sign Installation Guardrail Repair Lighting Mowing Street Sweeping Pothole Patching Striping

  4. Highway Construction Work District 5 • 2008 Recommended Highway Plan • Formally - “Six Year Plan” • Programs the funds for the next two years • The “Biennium” • Approximately $70 million Federal Stimulus • For Dist. 5 road projects • Approximately $23 million Federal Stimulus • - For projects in the KIPDA Planning area

  5. Westport Road / Interchange • Widen Westport between Hubbards Ln. and Watterson • Full Interchange at the Watterson • Single Point Urban Interchange (Bardstown Rd.) • Hall Contracting • Fall 2008 to May 2010 • $47 Million

  6. I-65 Major Rehab • Complete removal of Concrete Sections • Replace With Asphalt • Traffic Control • Contractor????? • December 2009 Completion • Approx. $30 Million • Stimulus Funded

  7. Cable Rail Installation • Installation on KY 841 from I-65 to Dixie Highway • I-65 in Bullitt, Hart, and Barren Counties • Gibraltor System – (4 wires) • RMD Holdings • Fall 2009 Completion • $3.1 Million

  8. I-65 Patching & Diamond Grinding • Patch Bad Concrete Areas from MP 118.5 to 127.5 • Grind Surface • Faulkner Construction • Fall 2009 Completion • $5.7 Million • Stimulus Funded

  9. I-64 Widening • Widen I-64 between I-265 and Shelby Co. Line • 3 Lanes in each direction – Barrier Median • Gohmann Asphalt & Construction • Fall 2010 Completion • $34 Million

  10. Eastern Parkway • “Road Diet” and Pedestrian Safety • Bridge over Floyd and Brook Streets Rehab • Warnock Ramp Reconfiguration • Over-Height Truck detection system • MAC Construction (Low bid – not yet awarded) • January 2010 Completion • $7.1 Million

  11. Preston Highway (KY61) • 4-Lane Widening • From Jefferson County Line to John Harper Highway • One of Four Sections • Stimulus Funded • Flynn Brothers Contracting • January 2010 Completion • $6.2 Million

  12. Shawnee Expressway Bridge • I-264 West to I-64 West Bridge • Mainly for Rehab • Lane Configuration stays the same • Faulkner Construction • May 2010 Completion • $5.6 Million

  13. QUESTIONS? Transportation.ky.gov Matt.Bullock@ky.gov (502) 210-5400