An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Provisional Timing Campaign I (focus for hourly measurements): • Setup: 16 & 17 Feb 2009 • Measurement: 18 Feb – 19 March 2009 • Take-down: 20 March 2009 (Easter: 12/13 April) Campaign II: • Setup: 31 Aug & 1 Sep 2009 • Measurements: 2 Sep – 1 Oct 2009 • Take-down: 2 Oct 2009

  2. Measurement Emphasis • Repeat of 2006 / 07 measurement programme • Improve mass closure (incl. mineral dust, especially Mediterranean countries) • Increased focus on denuder gas measurements (HNO3, NH3, SO2, NO2) • EC/OC measurements by reference technique • Vertical gradients (Lidar, balloon, towers, aircraft) • Levoglucosan (Feb), 14C • More hourly measurements (MARGA / AMS)

  3. Planning Timetable • Now 07: Preliminary dates at present • May 07: Communication with EUCAARI & NitroEurope communities • End of May 07: Finalise dates • Sep 07: Approval by EMEP Steering Body • Oct 07 workshop: Tighten up measurement programme (in response to analysis of 2006/07 measurements) • June 08: Final plan submitted to EMEP Steering Body

  4. Use of Data of Hourly Measurements • The data are meant to be used, e.g. for model validation • But: • These were often generated by other projects • Please involve data providers in interpretation • To recognise limitations of the data • For acknowledgements

  5. Model inter-comparison based on 2006/07 data • Data ratification and full submission: aim for July 2007 • European-scale inter-comparison activity in 2008? • Joint TFMM / ACCENT activity? • Who to organise? Who to take part? • Announcement at ACCENT meeting Urbino July 2007