PRJ480 Mastering the Management of Iterative Development v2

PRJ480 Mastering the Management of Iterative Development v2. Module 3: Phase Management - Inception. Module 3 Objectives. As a project progresses through phases and iterations, describe the changing emphasis of Project Management by:

bernadinen
Download Presentation

PRJ480 Mastering the Management of Iterative Development v2

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PRJ480 Mastering the Management of Iterative Development v2 Module 3: Phase Management - Inception

  2. Module 3 Objectives As a project progresses through phases and iterations, describe the changing emphasis of Project Management by: • Understanding Inception objectives, milestones, and evaluation criteria. • Understanding the basics of estimation. • Understanding principal Inception tasks and artifacts, and their uses. • Understand that the software management team must specifically determine the scope of the project.

  3. Inception Primary Objectives: • Establishing the project’s software scope and boundary conditions • Determining the critical use cases of the system and the primary scenarios of operation • Demonstrating at least one candidate architecture against some of the primary scenarios • Estimating the cost and schedule for the entire project • Estimating potential risks Essential Activities: • Formulating the scope of the project • Synthesizing the architecture • Planning and preparing a business case

  4. Review: Coarse-Grained Versus Fine-Grained Plans Project Plan Phase Plan Iteration Plan (current) • Phases and major milestones • What and when • Iterations for each phase • Number of iterations • Objectives • Duration • Work Breakdown Structure Iteration Plan (next) Roadmap Coarse-grained Plan Fine-grained Plans

  5. Inception Considerations • Phase Focus • Project Scope/Requirements • Phase Plan • Risks • Business Case • Stakeholder Support • Development Process and Tools

  6. Inception Considerations • Measurements • Progress 5% • Expenditures (rate) Low • Staffing Small team • Stability Volatile • Modularity 50%-100% • Adaptability Varying • Maturity Prototype

  7. Inception Artifact Decisions In Inception, you will need to: • Decide: • Which artifacts to use in your process • How formally they will be treated • Where they fit into the lifecycle • What tools are used to author them • What roles are responsible for authoring them • Consider explicitly how to review each artifact • Refine the outline for each artifact • Decide what reports to use

  8. Inception Essential Artifacts • Development Case • Vision • Risk List • Software Development Plan • Iteration Plan • Development Process • Development Infrastructure • Glossary • Use-Case Model (Outlined) Optional Artifacts • Domain Model (a.k.a. Business Analysis Model) • Prototypes

  9. Artifact: Development Case • The responsibility of the Process Engineer role • Describes: • Which disciplines to use • Phases and milestones • Which artifacts to use • How to use artifacts • Which activities to perform • Additional activities • How to work in each discipline • Iteration Plan descriptions Development Case

  10. Development Case Extract for Project Management BusCase.doc ItAssess.doc ItPlan.doc RiskList.doc RskMgtPln.doc SDP.doc SDP.proj StatAssess.doc

  11. Development Cases Levels of Usage Informal 5-10 page overview 20 pages Typical, see the sample Development Case 100+ pages Avoid extensive Development Cases becausethey are difficult to maintain

  12. Vision Vision • Outline • Product Description • Problem Statement • Stakeholders and End Users • Features • Constraints • Quality Measures Features, constraints, and a problem statement are used to gain stakeholder agreement on scope.

  13. Software Development Plan Software Development Plan • Outline • Project Overview • Project Organization • Organizational Structure • External Interfaces • Roles and Responsibilities • Management Process • Project Estimates • Project, Phase, and Iteration Plans • Project Monitoring and Control • Technical Process and Supporting Process plans • Additional Plans

  14. Risk List • A list of known project risks • Description • Ranking • Impacts • Indicators • Mitigation Strategy • Contingency Plan • Timing • Initial version by end of Inception • Updated per iteration Risk List

  15. Other Risk-Related Artifacts Risk Management Plan Quality Assurance Plan Requirements Attributes

  16. Review: RUP Effort and Time Distribution by Phase This distribution is typical for new software projects

  17. Inception % Management 14 Environment/CM 10 Requirements 38 Design 19 Implementation 8 Assessment 8 Deployment 3 Total 100 RUP Distribution of Skills by Phase Percentage of effort by activity for the Inception phase.

  18. Inception Evaluation Criteria • Do all stakeholders concur on the scope definition, and the cost and schedule estimates? • Are requirements understood by stakeholders? • Are the cost and schedule estimates, priorities, risks, and development processes credible? • Do the depth and breadth of an architecture prototype (if needed) demonstrate the preceding criteria? • Do you have an iteration plan for the next iteration?

  19. Inception Phase Management Issues • Let’s get started, we’ll decide where to go later • Fixed-price bidding in inception

  20. Inception Phase Recommendations • Quantify project risks: • Business risks • Technical risks • Development risks • Capture the vision in written form • Make sure everyone on the project reads and understands it • Don’t overstaff • Better to have few people and the right people • Maintain the appropriate level of abstraction • The focus is scope definition, not the completion of detailed requirements

  21. Exercise: Collegiate Sports Case Study Refer to the Exercises section of your workbook and complete: Exercise 2: Artifact Completion Exercise 3: Work Allocation

  22. Module 3 Review • The main objective of Inception is establishing the scope of the project and achieving stakeholder concurrence. • Some form of a Development Case can help you keep track of your artifact decisions for the project. • Estimation can help you plan. Time and effort can be controlled by making project adjustments that affect relevant cost factors. • Essential artifacts are: • Vision • Risk List • Software Development Plan • Iteration Plan/Assessment • Work Breakdown Structure