End Project. Begin Project. Welcome to the SR 530/US 192 Highway Improvement Project Informational Meeting Thursday, February 8, 2007. Technical Coordinating Team. Florida Department of Transportation Mr. Joel Marmie, P.E. – Project Manager. Authority.
E N D
End Project Begin Project Welcome to theSR 530/US 192 Highway Improvement Project Informational MeetingThursday, February 8, 2007
Technical Coordinating Team • Florida Department of Transportation • Mr. Joel Marmie, P.E. – Project Manager
Authority • The Financial Project Number for the project is: 239304-1-52-01 • This public meeting is being held in accordance with Chapter 120, Florida Statutes.
Authority (Continued) This project is being developed in accordance with the Civil Rights Acts of 1964 and 1968. Under Title VI and Title VIII of the Civil Rights Acts, any person(s) or beneficiary who believes they have been subjected to discrimination because of race, color, religion, sex, age, national origin, disability, or familial status may file a written complaint with the FDOT's Equal Opportunity Office, 605 Suwannee Street, MS 65, Tallahassee, Florida 32399-0450. (850)-414-4747.
PROJECT DESCRIPTION • Completes the missing segment of the four lane to six-lane widening project between the Orange/Lake County line and Secret lake Drive.
PROJECT DESCRIPTION • Two ponds within the limits of the project will be enhanced and upgraded.
PROJECT DESCRIPTION • Two ponds within the limits of the project will be enhanced and upgraded.
Project-SpecificRecommendations: • Swales on the outside right-of-way
Project-SpecificRecommendations: • Curbs and gutters in the median
Project-SpecificRecommendations: • Sidewalks will be constructed on both sides of the highway.
Project-SpecificRecommendations: • A new traffic signal at Secret Lake Drive
Project-SpecificRecommendations: • A new traffic signal at Secret Lake Drive
Median Opening Modifications Camping Connections RV Store • From Full Median Opening to EB/WB Directional Opening
Median Opening Modifications West Driveway of Westside Development • WB Directional to EB/WB Directional
Median Opening Modifications Osceola County Firestation • Full Opening to WB Directional, with full access for emergency vehicles; No EB U-Turns
Median Opening Modifications Howard Johnson Maingate Resort • Close full access
Median Opening Modifications Pizza Hut/Lighthouse Key • Close full access
SR 530/US 192Highway Improvement Project FIN: 239304-1-52-01 Florida Dept. of TransportationFOR ADDITIONAL INFORMATION ABOUT FDOT PROJECTS AND PROGRAMShttp://www.dot.state.fl.us