1 / 16

EUROGAS CORPORATION

EUROGAS CORPORATION. Annual & Special Meeting June 14, 2011. Eurogas Corporation Corporate Organization. Castor Underground Gas Storage Project. Details of Castor Project. 1.3 bcm of working gas 25 MM m 3 per day withdrawal rate € 1.6 billion including financing costs

bikita
Download Presentation

EUROGAS CORPORATION

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EUROGAS CORPORATION Annual & Special Meeting June 14, 2011

  2. Eurogas CorporationCorporate Organization

  3. Castor Underground Gas Storage Project

  4. Details of Castor Project • 1.3 bcm of working gas • 25 MM m3 per day withdrawal rate • € 1.6 billion including financing costs • Syndicate of 19 banks to provide €1.3 billion • Term of loan: 10 years • European Investment Bank to provide €600 million • Security: CLP pledges its equity ownership in Escal UGS SL • Debt / equity ratio: 85 / 15 - ACS provides equity until project start-up - ACS provides bank guarantees for cost over-runs & other commitments

  5. 2010-11 Activities at Castor UGS Offshore • positioned wellhead platform and commenced drilling August 2010 • scheduled to complete drilling 12 wells by November 2011

  6. 2010-11 Activities at Castor UGS (con’t) Offshore • began construction on main platform • plan to set platform on location in November 2011 • designed 30-inch offshore pipeline for December 2011 completion

  7. 2010-11 Activities at Castor UGS • Onshore • construction completion of plant by December 2011 • commission plant during Q1 2012 • complete construction of pipeline by July 2011

  8. 30-inch pipeline landing

  9. Summary of the Castor Project Overall project completion at 70% Costs incurred to March 31, 2011 at € 800 million Mechanical completion early 2012 Commence cushion gas injection over remainder of 2012 Castor Project operational in first half of 2013

  10. Ontario Oil & Gas Assets Toronto Niagara Falls 65,000 acres 902,000 acres Detroit

  11. Ontario Asset Acquisition Acquisition price $129 million (before adjustments) Effective date March 1, 2010 Closing date June 29, 2010 Funding of acquisition Cash of $65 million Bank debt of $64 million

  12. Offshore fleet of barges & supply boats

  13. 2010 Operating Results for 6 months Production Gas 10.4 MMcf/d Oil 688 bpd Proved reserves to Dec 31, 2010 Gas 59.7 bcf, RLI of 15.5 years Oil 1.7 million bbl, RLI of 7.1 years Net operating cash flow $ 1.8 million per month Netbacks Gas $ 2.42 per mcf Oil $ 48.49 per bbl

  14. 2011 Capital Exploration Program Capital Expenditure $9.0 million Offshore Well abandonment program – 15 wells Drill 3 wells: two horizontal Workovers Well monitoring devices Onshore Drill 4 wells: one horizontal Up to 12 workovers Acquire 3-dimensional seismic

  15. 2011 Social Responsibility Program Focused on • childhood education • environment • community activities

More Related