Proton Plan Status September Report

Proton Plan Status September Report. Eric Prebys. Agenda. Operations Report/Technical Progress – Prebys Answers to Review Comments – Prebys/Sims Cost/Schedule Report – Sims. Operations Report. Operational Issues. NuMI Has been running well Demonstrated slip stacked beam to target

cdemetrius
Download Presentation

Proton Plan Status September Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Proton Plan Status September Report Eric Prebys

  2. Agenda • Operations Report/Technical Progress – Prebys • Answers to Review Comments – Prebys/Sims • Cost/Schedule Report – Sims

  3. Operations Report

  4. Operational Issues • NuMI • Has been running well • Demonstrated slip stacked beam to target • MiniBooNE • MiniBooNE has benefited from NuMI’s misfortunes • Other than that, same old, same old.

  5. FY06 Total Booster Output Falling a bit behind

  6. NuMI FY06

  7. MiniBooNE FY06 Need to do better

  8. Technical Progress

  9. Progress • Technical Progress Linac • 1.01.01 PA Vulnerability – • Three new tubes delivered since last PMG (record?) • Four total (plus seven ordinary spares) • More or less on schedule • 1.01.02 Quad Power Supplies • Design of replacement cards proceeding. • 1.01.04 LLRF Upgrade • RF Groups has assigned manpower to the project • Beginning modeling and preparing for tests with test station • Plan extensive system testing planned during shutdown. Booster • 1.02.01 Determine rep. rate limit • Still trying to nail down all the numbers for 15 Hz • 1.02.02 Orbump (+ 400 MeV line) – • All six magnets complete • Two magnets tested • Miscellaneous fabrication on schedule for shutdown

  10. Progress Booster • 1.02.03 Correctors – • Moving Ahead with Prototype • Finalizing electrical spec (some questions about acceptable slew rate) • Working on prototype measurement and QA procedure • Preparatory water work put on list for shutdown • 1.02.04/05 30 Hz/Gamma-t – • Progress kind of stalled. • Some manpower diverted by stacking RRT • Hope to move things along and still make some decision in January • 1.02.11 Booster Dump Relocation • Settled on 6.8E18 protons per year as dump limit (twice what we typically send to present dump) • Everything else on track for shutdown. • 1.02.13 Booster RF/ Rep. rate Improvements • Orders out for transformers and switch gear • On “A” list for shutdown • Still need to coordinate with operations (1 week power outage for each gallery)

  11. Progress Main Injector • 1.03.01 Large Aperture Quads – • Still planning to install all 7 during shutdown • 1.03.02 Collimation – • Design complete. • All reqs out (except perhaps marble) • Fabrication proceeding (see picture) • 1.03.03 NuMI MultiBatch Operations – • 2+5 operation more or less at design levels • High intensity (2 batch) slip stacking demonstrated to NuMI, as per review recommendation. • Low intensity multibatch slip stacking at 8 GeV (3+3 stacking) • Initial tests of MI-10 kicker mods had some problems • Effort increasing • Mech. Supp. Confident we can get at least the tunnel work done in the shutdown. • Modeling work continues

  12. Progress (cont’d) • 1.5 Stage II • After a long hiatus, activity has started again • Reduced scope to just Recycler retasking • Hope to have report by Christmas

  13. ORBUMP Magnet (w/o side and end plates) Girder

  14. Correctors First thermal model Design

  15. MI-8 Collimator Progress

  16. Responses to Review Recommendations