1 / 6

AST Portfolio Review

AST Portfolio Review. Tom Statler , NSF/AST AAAC Telecon , 11 May 2012. Why a Portfolio Review?. ?. From “Introduction to the AST Portfolio Review ”, http ://www.nsf.gov/mps/ast/portfolioreview/introduction_to_the_ast_portfolio_review.pdf. Two-Phase Committee Charge .

cisco
Download Presentation

AST Portfolio Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AST Portfolio Review Tom Statler, NSF/AST AAAC Telecon, 11 May 2012

  2. Why a Portfolio Review? ? From “Introduction to the AST Portfolio Review”, http://www.nsf.gov/mps/ast/portfolioreview/introduction_to_the_ast_portfolio_review.pdf AAAC

  3. Two-Phase Committee Charge Recommend the critical capabilities needed over the period from 2015 to 2025 that would enable progress on the science program articulated in the Astronomy & Astrophysics and Planetary Decadal Surveys. (Not only observational capabilities, but also theoretical, computational, laboratory, research support, workforce, education) Recommend the balance of investments in new and in existing, but evolved, facilities, grants programs, and other activities that would deliver the needed capabilities within the constraints of each of the provided budgetary scenarios. (May include closure or divestment of facilities, termination of programs and other activities.) AAAC

  4. Progress to Date • Weekly full-committee telecons since Sep 2011 • 1st face-to-face meeting Oct 21-23 • Numerous working-group telecons since Oct • Facilities submitted updated Long-Range Plans and Vision Statements in Jan • Community briefed at Jan AAS Town Hall • 2nd face-to-face meeting Jan 12-14; Phase 1 completed • Community Input accepted by Email from Oct 26 to Jan 31; ~102 messages received, categorized, assimilated • Many working-group telecons Jan – Apr for Phase 2 • Additional input solicited from OIR and RMS observatories, received in March • 3rd face-to-face meeting Apr 12-14; Phase 2 completed • Current: report 1st draft being written AAAC

  5. Future Timeline • Report delivery to AST ~July • Report acceptance by MPSAC ~ late summer • Internal MPSAC reviewers before MPSAC telecon • MPSAC acceptance is required before plan can be made public or be acted on • AST implementation plan available ~ November • AST implementation working group has been formed (AST Program Staff), and is working on producing: • a strategy for implementing the PR recommendations, which identifies the issues that must be addressed • a management plan for implementation, including roll-out of the report, • a plan for carrying out the implementation. AAAC

  6. Implementation Issues • Legal, Policy, & Financial • Stakeholder Relations • AST staff • Other NSF – OLPA, PHY, AGS • Upper NSF – MPS (MPSAC) & OD • NSB • OSTP, OMB • Congress • Astronomical Community • AST facilities • Other Gov Agencies – NASA, DoE, USAF, etc. • CAA & AAAC • International and National Partners • Feedback to PR Committee • Impact of planning on the form/nature of recommendations • Ensure all recommendations are justified • Review of draft PR Report for fact checking • Process for deciding implementation • Roll-out of PR Report • Maintain confidentiality of PR report up to release • Risk Assessment & Risk Management • Operational Implementation • Observatory management competitions Portfolio Review website: http://www.nsf.gov/mps/ast/ast_portfolio_review.jsp AAAC

More Related