Harelbeke Herinrichten Plein Eiland

Harelbeke Herinrichten Plein Eiland. Algemene Projectgegevens. Bouwheer : Stad Harelbeke Infrax Rio Aannemer : NV Wegenbouw Ockier, Kuurne Studiebureau : NV Plantec, Oostende Aanbestedingsbedrag : 645.000 € (incl. BTW). Concept. Riolering :

Download Presentation

Harelbeke Herinrichten Plein Eiland

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Harelbeke Herinrichten Plein Eiland

  2. AlgemeneProjectgegevens • Bouwheer : Stad Harelbeke Infrax Rio • Aannemer : NV Wegenbouw Ockier, Kuurne • Studiebureau : NV Plantec, Oostende • Aanbestedingsbedrag : 645.000 € (incl. BTW)

  3. Concept • Riolering : • Aanleg van gescheiden rioleringsstelsel • Vuilwaterleiding DWA Ø300 • Regenwaterleiding RWA Ø400 – 500 – 600 • Iedere woning : 2 nieuwe huisaansluitingen

  4. Concept • Wegenis : - Rijweg in uitgewassen betonverharding - Voetpaden in glinstergrijze betonstraatstenen formaat 20x20 cm - parkeerzones in glinstergrijze betonstraatstenen 20x10 cm - groenaanleg

  5. Planning • Aanvang nutsleidingen : 04/03/2013 • Aanvang rioleringswerken : na bouwverlof • Uitvoeringstermijn infrastructuurwerken 100 werkdagen - 2 fasen : • FASE 1 : rioleringswerken + rijweg + voetpad en parkings zijde woningen – GEEN plein (eind 2013) • FASE 2 : afwerken pleinverharding