An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MICE Updates Target • MICE Hall • Quadrupoles • Target • Decay Solenoid • TOF I installation • Other MICE News • Spectrometer Update • Aspirational Schedule BM2 BM1 Decay Solenoid Terry Hart, NFMCC Friday Meeting, December 19, 2008 NFMCC Friday Meeting

  2. Phase One nearing completion • Shield walls complete and painted • All mezzanines & galleries are complete • False floor making good progress • All fabrication is complete and delivered • Installation in Hall is about 30% done – a few minor hold-ups with drilling the floor • Aim to complete early January (not critical path) • Rolling platforms 1 & 7 are complete, tested and delivered • Smoke detection, lighting upgrade and fire alarms delayed, regrettable, but not critical • Work is currently under tender by BPG • Hope to get started in January • Main door replacement crucial for PPS installation • ISIS have reservations – urgently need to understand! • Two RF amplifiers are on their way from CERN to DL NFMCC Friday Meeting

  3. MICE Beamline Quadrupoles Target • Leaking quadrupoles fixed • Quadrupoles seem fine after many problems in October BM2 BM1 Decay Solenoid Target: Titanium paddle dipped into ISIS proton beam to produce pions Decay Solenoid: Focuses muon beam coming from pion decay BM1, BM2: scintillating fiber beamline monitors GVA1, GVA2: scintillating paddle beamline monitors NFMCC Friday Meeting

  4. MICE Beamline Target Target • Mechanical redesign • Shaft to be made of cylindrical sections • Stay with titanium • Improve coating adhesion • Install accelerometers • FEA shows resonance excitation • Magnetic concerns • Field measurements validate model • Need to measure off-axis radial forces • Electronics redesign • Target orientation studies • Internal review, documentation coming soon BM2 BM1 Decay Solenoid Target: Titanium paddle dipped into ISIS proton beam to produce pions Decay Solenoid: Focuses muon beam coming from pion decay BM1, BM2: scintillating fiber beamline monitors GVA1, GVA2: scintillating paddle beamline monitors NFMCC Friday Meeting

  5. MICE Beamline Target Decay Solenoid • Cooldown and fault analysis ongoing • All 10 coils appear to be superconducting • Problem with quench protection circuitry • Shutdown plan: • Continue cooling and diagnosis over Christmas • Train “semi-experts” and work with ISIS crew • Cold mass removal to proceed and planned BM2 BM1 Decay Solenoid CKOV A,B Target: Titanium paddle dipped into ISIS proton beam to produce pions Decay Solenoid: Focuses muon beam coming from pion decay BM1, BM2: scintillating fiber beamline monitors GVA1, GVA2: scintillating paddle beamline monitors NFMCC Friday Meeting

  6. TOF I (2nd set) Installation • Installation from Dec. 9 – 12 great milestone for MICE Step I • Initial data taken; more needed • Limited debugging with electron, pion beams; need muon beam for full debugging • Cable length calibration, time offset determinations underway • Would like DAQ readout • TOF 0 and TOF 1 • Calorimeter • 2 taggers behind calorimeter NFMCC Friday Meeting

  7. TOF2 status TOF2 counters assembled, but not still wrapped out TOF2 PMTs under repair at Hamamatsu: delivery expected by mid January 09 ARMCO steel for local PMTs shielding procured at CERN and now in house final design of KL+TOF2 trolley under way final design of TOF2 mechanics + local shielding done M. Bonesini - VC 18-12-08 NFMCC Friday Meeting

  8. Other MICE News • Calorimeter working fine • Tracker cassette characterization done at FNAL • Next steps: • Test spare boards • Test and run full tracker 2 readout system • Ship to RAL, aiming for late January NFMCC Friday Meeting

  9. Spectrometer Update • A few problems found, understood, caused about couple week delay • Shipment to FNAL likely around late January • After setup, start magnetic field mapping (Ben Freemire’s talk) NFMCC Friday Meeting

  10. MICE Schedule as of December 2008 m STEP I Repair DKsol Q1 09 Run May09 Deliv SSI Apr09 Run July09 STEP II Deliv SSII Aug09 Run Dec09 STEP III/III.1 Deliv FCI Nov09 Run Apr10 STEP IV STEP V RFCCI deliv Apr10 Run Sep10 STEP VI RFCC deliv Q4 2010 Run 2011 NFMCC Friday Meeting