An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Update on the Davis-Woodland Water Supply Project Agency Board July 15, 2013

  2. Upcoming Activities/MilestonesJune - July 2013 PROJECT FUNDING • Continue to pursue SRF low interest loan and grant funding opportunities • Project added to Clean Water SRF Project funding list • West Side IRWMP approved • DWWSP highly-ranked • $10m in State grant funding for Joint Intake included in approved State Budget

  3. Upcoming Activities/MilestonesJune – July 2013 (cont’) LAND AND ROW ACQUISITIONS • Continue work with Yolo County regarding encroachment permits/road construction • Meeting with Yolo County on July 9 • Complete acquisition of Heidrick/McGinnis, Lillard, Turner, and Oates easements • Complete land and easement agreements with City of Davis • Continue eminent domain actions on 3 parcels PLANNING, DESIGN, AND CONSTRUCTION • Receive priced DBO proposal July 30th

  4. Updated 30 mgd Project Costs(April 2013 million dollars) Construction Costs(a) Capital Costs, 2009-2016 (a) Includes DBO contract design and construction costs, design-bid-build construction costs, and Agency design review, construction management, engineering services during construction, environmental construction monitoring, and environmental mitigation, permitting and incidental costs.

  5. Project Schedule Milestones Updated: 07/15/13

  6. Questions