1 / 9

MPSB: 2GEV project New Layout and Losses Calculation

MPSB: 2GEV project New Layout and Losses Calculation. TE-EPC Group Meeting 26 of June 2009. Fulvio Boattini. New Layout proposal for b245. Cooling water for Main power converters. MPS Unit N 1. MPS Unit N 2. MPS Unit N 3 spare. Cooling water for quadrupole power converters. QP Unit N 1.

Download Presentation

MPSB: 2GEV project New Layout and Losses Calculation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MPSB: 2GEV projectNew Layout and Losses Calculation TE-EPC Group Meeting 26 of June 2009 Fulvio Boattini

  2. New Layout proposal for b245

  3. Cooling water for Main power converters MPS Unit N 1 MPS Unit N 2 MPS Unit N 3 spare

  4. Cooling water for quadrupole power converters QP Unit N 1 QP Unit N 2 QP Unit N 3 Spare

  5. Cooling water for Output Filter MPS filter Unit N 1 MPS filter Unit N 2 MPS filter Unit N 3

  6. Proposed hydraulic filter layout Dedicated cooling unit with deionised water. Flow regulation to be done inside each cabinet by appropriated means. Mechanic filter 250um (as presently used in POPS)

  7. New Layout proposal for b245

  8. New Layout proposal for b245

  9. New Layout proposal for b245

More Related