1 / 28

CS 501: Software Engineering

CS 501: Software Engineering. Lecture 4 Project Management. Administration. Projects Announcements by project teams Quiz 1 Quiz 1 is next Thursday. Information is posted on the web site. Office hours • No office hours on Tuesday, February 5. OS 360.

delta
Download Presentation

CS 501: Software Engineering

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CS 501: Software Engineering Lecture 4 Project Management

  2. Administration • Projects • Announcements by project teams • Quiz 1 • Quiz 1 is next Thursday. Information is posted on the web site. • Office hours • • No office hours on Tuesday, February 5.

  3. OS 360 The operating system for the IBM 360 was two years late. Question: How does a project get two years behind schedule? Answer: One day at a time! Fred Brooks Jr., The Mythical Man Month

  4. The Aim of Project Management To complete a project: • On time • On budget • With required functionality • To the satisfaction of the client • Without exhausting the team To provide visibility about the progress of a project

  5. Aspects of Project Management Planning • Outline schedule during feasibility study • Detailed schedule at the beginning of a project or phase of a project Progress tracking • Regular comparison of progress against plan Final analysis • Analysis of project for improvements during next project

  6. Terminology Deliverable Work product that is provided to the customer (report, presentation, documentation, code, etc.) Milestone Completion of a specified set of activities (e.g., delivery of a deliverable, completion of a process step)

  7. Terminology Activity Part of a project that takes place over time (also known as a task). Event The end of a group of activities. Dependency An activity that cannot begin until some event is reached Resource Staff time, equipment, or other limited resources required by an activity.

  8. General Approach to Project Planning Identify deliverables and milestones Divide project into activities (tasks) For each activity estimate: • time to complete from when activity begins • dependencies on events before beginning • resource requirements Build a model that uses this data to create a work-plan, including schedule, resource allocation, and flexibility

  9. Project Planning Methods Critical Path Method, Gantt charts, Activity bar charts, etc. • Build a work-plan from activity data. • Display work-plan in graphical form. Project planning software (e.g., Microsoft Project) • Maintain a database of activities and related data • Calculate and display schedules • Provide progress reports

  10. A Simple Gantt Chart Source: Microsoft using Excel

  11. Gantt Charts • Dates run along the top (days, weeks or months). • Each row represents an activity. Activities may be scheduled sequentially, in parallel or overlapping. • The schedule for an activity is a horizontal bar. The left end marks the planned beginning of the task. The right end marks the expected end date. • The chart may be updated by filling in each activity to a length proportional to the work accomplished. • Progress to date can be compared with the plan by drawing a vertical line through the chart at the current date.

  12. A More Complex Gantt Chart Source: SmartDraw

  13. Activity Graph A scheduling technique that emphasizes dependencies An activity (task) A dummy activity (dependency) An event A milestone

  14. Example: Activity Graph for a Distance Learning Course Script TV Plan TV Write 1 Edit 1 Make TV START Typeset 1 Plan 1 Print Mail Plan 2 Typeset 2 Write 2 Edit 2 Document Software Write Software Plan Software Prototype Software

  15. Scheduling: Background PERT Program Evaluation and Review Technique introduced by the U.S. Navy in 1957 to support the development of its Polaris submarine missile program. PERT/Time Activity graph with three time estimates (shortest, most probable, longest) on each activity to compute schedules. PERT/Cost Added scheduling of resources (e.g., facilities, skilled people, etc.)

  16. Critical Path Method Uses Activity Graph with single time estimate for each activity to estimate: earliest start date -- every activity begins at first possible time latest start date -- every activity begins at the last possible time slack -- difference between the latest and earliest start dates A standard method for managing large construction projects. On big projects, activity graphs with more than 10,000 activities are common.

  17. Time Estimates for Activities (Weeks) 4 1 3 2 6 3 1 1 12 3 12 3 2 2 8 4 4

  18. 15 24 22 25 17 17 Earliest Start Dates Earliest start dates in red All activities beginning at a given event have the same earliest start date. 1 4 1 5 3 2 6 17 12 23 3 20 1 12 23 1 0 15 3 12 3 2 19 2 12 8 4 8 4 4

  19. 19 17 0 17 17 Latest Start Dates Latest start dates in blue Each event must be achieved by the date shown or the final date will not be met. 11 4 1 20 3 2 6 12 15 3 10 1 12 23 24 25 1 3 12 18 3 2 20 2 14 8 4 22 4 13

  20. Critical Path Critical path in orange Every activity on the critical path must begin on the earliest start date. 1/11 12/12 15/15 17/17 25/25 22/23 23/24 0/0 12/14 17/17 19/20 4/13 17/17

  21. 1/11 0/0 Slack Slack in purple Slack of activity = (latest start)end - (earliest start)begin - (time estimate) 10 4 10 1 12/12 15/15 17/17 6 2 25/25 3 0 2 0 3 22/23 3 23/24 0 12 1 0 1 1 1 12 1 12/14 17/17 19/20 2 3 3 2 1 2 5 0 2 8 4 9 0 4/13 17/17 4 9

  22. Estimating the Time for an Activity • With experienced staff, estimating the actual time to carry out a • single task is usually fairly accurate, but ... • The little bits and pieces are underestimated • The time from almost "done" to completely "done" is much longer than anticipated. (There's just one thing to tidy up. I need to put the comments into better shape. I really should get rid of that patch.) • The distractions are not planned for. (My system crashed and I decided to upgrade the software. My child's school was closed because of snow. I spent the day showing visitors around.) • Some things have to be done twice.

  23. Start-up Time On a big project, the start-up time is typically three to six months: • Personnel have to complete previous projects (fatigue) or be recruited. • Hardware and software has to be acquired and installed. • Staff have to learn new domain areas and software (slow while learning). • Clients may not be ready.

  24. Final Analysis with Critical Path Method Administrative computing department at Dartmouth used the Critical Path Method for implementation phase of major projects (plan developed after project was well-understood). Experience: Elapsed time to complete projects was consistently 30% to 40% longer than predicted by model. Analysis: • Some tasks not anticipated (incomplete understanding) • Some tasks had to be redone (change of requirements, technical changes) • Key personnel were on many activities (schedule conflicts) • System ZZZ (non-billable hours)

  25. Adding Resources to Activity Graph or Gantt Chart Each activity is labeled with resources, e.g., Number of people (e.g., 2 Java programmers) Key personnel (e.g., chief system architect) Equipment (e.g., 3 servers with specified software) Facilities (e.g., video conference center) Each resource is labeled with availability, e.g., Hiring and training Vacations Equipment availability

  26. Using Critical Path Method for Resources Assume every activity begins at earliest start date: In each time period, calculate: resources required resources available Identify shortage / surplus resources Adjust schedule acquire extra staff (e.g., consultants) rearrange schedule (e.g., change vacations) change order of carrying out activities The earlier that a problem is known, the easier it is to fix.

  27. Key Personnel: The Mythical Man Month In computing, not all people are equal • The best are at least 5 times more productive. • Some tasks are too difficult for everybody. Adding more people adds communications complexity • Some activities need a single mind. • Sometimes, the elapsed time for an activity can not be shortened. What happens to the project if a key person is sick or quits?

  28. The Project Manager • Create and maintain the schedule. • Track progress against schedule. • Keep some slack in the schedule (minimize risk). • Continually make adjustments: Start activities before previous activity complete Sub-contract activities Renegotiate deliverables • Keep senior management informed (visibility). The project manager needs the support of the head of the development team and the confidence of the team members.

More Related