ABC/PBES specifications, contract drawings and details. by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer). Learning Outcomes. Identify resources for examples of various ABC/PBES
E N D
ABC/PBES specifications, contract drawings and details by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)
Learning Outcomes • Identify resources for examples of various ABC/PBES • Acquire specifications, contract drawings, and details for various ABC/PBES projects • Describe issues concerning regional and national details and standards • Describe seismic considerations and research
Resources for ABC/PBES Specifications, Contract Drawings, and Details • FHWA prefabricated bridges website • HfL projects website • ABCT website • ACTT website • ABC Center • PBES Connection Details Manual • PBES Cost Study • State DOT bridge websites • FHWA SPMT Manual • UDOT ABC SPMT manual & guide • NCHRP domestic scan report • NCHRP & other research • ABC Manual • SHRP2 R04 Final Report
FHWA Prefabricated Bridges Website 50+ Projects View Projects • All projects • By Specific Elements or Systems: ◦ Partial-Depth Deck Panels ◦ Full-Depth Deck ◦ Panels Beams: More Efficient Shapes ◦ Pier Cap, Column, and/or Footing ◦ Abutment Wall, Wingwall, and/or Footing ◦ Superstructure ◦ Substructure ◦ Total Bridge http://www.fhwa.dot.gov/bridge/prefab/projects.cfm
FHWA Prefabricated Bridges Website 50+ Projects • Location • State • Completion Date • Contact Person • Description • Project Photo • ABC/PBES Type • Advantages • Related Documents http://www.fhwa.dot.gov/bridge/prefab/projects.cfm
FHWA Prefabricated Bridges Website Related Documents • Contract Drawings • Detail Sketches • Construction Photos • Construction Process Description http://www.fhwa.dot.gov/bridge/prefab/projects.cfm
FHWA Prefabricated Bridges WebsiteContract Drawings Precast Bent Cap Construction Notes – Examples: • Identify which construction specification items to build in accordance with; • Describe how caps are to be handled; • Specify concrete mix design and grouting requirements; • Specify construction process, with note that says what contractor must do if deviating from those requirements
FHWA Prefabricated Bridges WebsiteDetail Sketches NHDOT Epping Bridge
FHWA Prefabricated Bridges WebsiteOngoing Updates • Contact information updated • Recent projects added • More project details included, e.g.: • Specifications • Contract Drawings • Contracting Strategies • Costs http://www.fhwa.dot.gov/bridge/prefab/projects.cfm
HfLProjectSummaries http://www.fhwa.dot.gov/hfl/summary/projects_summary.cfm
Center for Accelerated Bridge Construction at Florida International University http://www.abc.fiu.edu/
General Topics • Superstructure Connections • Substructure Connections • Foundation Connections • Connection Design Examples • Proprietary Products • Sample Construction Specifications • Case Studies http://www.fhwa.dot.gov/bridge/prefab/if09010/
Cost-competitive projects • Reduced onsite construction time • Construction cost less than engineer’s estimate • Project details • Project owner contacts • Other contacts, e.g.: • Contractor • Design Engineer • Prefabricator http://www.fhwa.dot.gov/bridge/prefab/successstories/091104/
FHWA PBES Cost Study • Case studies of nine projects • Project description • Project size / dimensions • ABC/PBES types • Fabrication/construction details • Construction photos • Contract requirements • Cost – engineer’s estimate vs. bid • Contact information http://www.fhwa.dot.gov/bridge/prefab/successstories/091104/
State DOT Websites – UDOT http://www.udot.utah.gov/main/f?p=100:pg:0:::1:T,V:1991,
State DOT Websites – UDOT • Full-Depth Precast Concrete Deck Panels Manual • Precast Approach Slab Manual • Precast Box Culvert Manual • Precast Bulb Tee Girder Manual • Precast Substructure Elements Manual • SPMT Process Manual and Design Guide • Master Process for Bridge Moves Using SPMTs http://www.udot.utah.gov/main/f?p=100:pg:0:::1:T,V:2090,
State DOT Websites – TxDOT http://www.dot.state.tx.us/insdtdot/orgchart/cmd/cserve/standard/bridge-e.htm
Example Standard included in • Guide to Bridge Standard Drawings: • Decked Slab Beam (ABC) • 20-in. & 23-in. depth • 6.5-ft, 7-ft, & 8-ft width • 30-ft to 60-ft span lengths To access TxDOT bridge standards & guide: http://www.dot.state.tx.us/insdtdot/orgchart/cmd/cserve/standard/bridge-e.htm, or Google “TxDOT Bridge Standards”
TxDOT Guide to Bridge Standard Drawings • Description of Component • Standard Drawing Location • Standard Drawing Features • Standard Drawings Needed for Bridge Details • Additional Drawings Needed to Complete Bridge Details • Restrictions on Use of Standard Drawings • Special Considerations • Specific Bridge Layout Requirements To access TxDOT bridge standards & guide: http://www.dot.state.tx.us/insdtdot/orgchart/cmd/cserve/standard/bridge-e.htm, or Google “TxDOT Bridge Standards”
FHWA Manual on Use of SPMTs to Remove & Replace BridgesAppendices • App. A: Example User Cost Model Spreadsheet • App. B: Example Plan Sheet Details for Cast-in-Place Deck Closure Pour Option to Facilitate Span Fit-Up • App. C: Example Calculations for Comparing Total Bridge Weight and Estimated Cost Premium for Normal-Weight Concrete and Lightweight Concrete Bridge • App. D: Example Specification for SPMT Equipment • App. E: Example Plan Sheet for Contractor Alternatives • App. F: Example Specification for Lightweight Aggregate • App. G: Example Specification for Incentive/Disincentive and Bonus Used in Conjunction with App. E
FHWA Manual on Use of SPMTs to Remove & Replace Bridges Appendices, cont’d. • App. H: Example Specifications for Incentive/Disincentive • App. I: Example Specifications for Bonus • App. J: Example Specifications for Lane Rental • App. K: Example Specification for Value Engineering • App. L: Examples of Partnering Provisions • App. M: Example Plan Sheets for Traffic Control Plans • App. N: Example Specification for Settlement Report for Temporary Shoring on Shallow Foundations • App. O: Example Diagrams for Path and Motion http://www.fhwa.dot.gov/bridge/pubs/07022/
FHWA Manual on Use of SPMTs to Remove & Replace BridgesFDOT I-4/Graves Avenue Case Study • Project Description • Bridge Removal with SPMTs • Bridge Construction and Erection with SPMTs • Time Savings • Initial Construction Costs • Delay-related User Cost Savings • Net Cost Savings from Use of New Technology • Participants • Post-Installation Interviews – Contractor & Subcontractor • Lessons Learned
Preconstruction Process http://www.udot.utah.gov/main/f?p=100:pg:0:::1:T,V:2090,/
Construction & Transport Process http://www.udot.utah.gov/main/f?p=100:pg:0:::1:T,V:2090,
NCHRPDomestic ScanProgram Domestic Scan on Best Practices in Accelerated Construction Techniques March 2009 http://onlinepubs.trb.org/onlinepubs/nchrp/docs/NCHRP20-68A_07-02.pdf
National Cooperative Highway Research ProgramProjects Related to ABC
Panels designed • per NCHRP 12-65 • – no post-tensioning • or overlay Full-Depth Deck Panelsper NCHRP 12-65 TxDOT Live Oak Creek Bridge – 2008 86 full-depth, full-width deck panels, totaling 22,400 sq ft View shows blockouts for shear studs & transverse connection rebar Erection of deck panels over shear studs on beams
NCHRP 12-74 Project Objectives Develop design methodologies, connection details, and design and construction specifications for precast bent cap systems in all seismic regions • Systems and methodologies for entire U.S. • Practical, cost-effective connection details • Design examples • Design and construction specifications with commentary in AASHTO LRFD format Source: Eric Matsumoto, California State University, Sacramento http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_rpt_681.pdf
Grouted Duct and Cap Pocket Details Grouted Duct Section Isometric View of Joint Elevation Cap Pocket Plan Cap Pocket, Full Ductility (CPFD) Elevation Cap Pocket, Limited Ductility (CPLD)Elevation Ref.: NCHRP 12-74
NCHRP 12-74 Lateral Load-Displacement for All Specimens Source: Eric Matsumoto, California State University, Sacramento
NCHRP 12-74Hysteretic Response Cast-in-place Grouted Duct Cap Pocket, Full Ductility
NCHRP 10-71 – PrecastComposite Slab Span System (PCSSS)based on French Poutre Dalle System from 2004 FHWA International Scanning Tour • Span to Depth: 1/28 - 1/30 • Span lengths 20 to 60 ft • (45 ft span – 20 in depth) • Minimum CIP depth 6 in • Place ~12 beams in 4 hours Reference: NCHRP 10-71, C. French, C. K. Shield, Univ of Minnesota; & Z. J. Ma, Univ of Tenn - Knoxville http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_w173.pdf
NCHRP 10-71PCSSS Initial Implementation Horizontal and Vertical Shear Reinforcement Inverted T Precast Sections Roughened Surfaces 8 to 22” Chamfered Corners Constant 6” CIP thickness Variable w/ span length Constant 3” Constant Prestressing Tendons 90oTransverse Hook to facilitate “drop-in” cage
NCHRP 10-71 Construction Center City Bridge (3 span: 22-27-22 ft)
Longitudinal and Transverse Joints in DBTs and Precast Deck Panels Reference: NCHRP 10-71, C. French, C. K. Shield, Univ of Minnesota; & Z. J. Ma, Univ of Tenn - Knoxville http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_w173.pdf
chloride penetrability 7-day and Overnight Cure Closure Pour Materials shrinkage bond freeze-thaw durability Ref.: NCHRP 10-71
National Cooperative Highway Research ProgramProjects that Facilitate the Use of ABC
National Cooperative Highway Research Program2011 Project Related to ABC * Funded as a synthesis project to review related past & ongoing research, define what is missing, & make recommendations for future research as a “Program of Work.”