1 / 103

Panel Meeting 196

Panel Meeting 196. 12 April 2012. Apologies. Andrew Pinder. 12 April 2012. Report on Progress of Modification Proposals. Adam Lattimore. 12 April 2012. Modifications Overview. Modifications Overview. 196/04 November Release Date. Colin Berry. 12 April 2012. Introduction.

dick
Download Presentation

Panel Meeting 196

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Panel Meeting 196 12 April 2012

  2. Apologies Andrew Pinder 12 April 2012

  3. Report on Progress of Modification Proposals Adam Lattimore 12 April 2012

  4. Modifications Overview

  5. Modifications Overview

  6. 196/04 November Release Date Colin Berry 12 April 2012

  7. Introduction • BSC Release dates: • LastThursday in February • LastThursday in June • First Thursday in November • November 12 Release date would be 1 November 2012 • Seeking to change Release date to allow technology upgrade

  8. Technology Upgrade • BSC Systems Technology upgrade: • Initially developed and tested in 2011 • Significant Oracle defects found – delayed implementation • Oracle has fixed defects now • Cannot restart technology upgrade before June 12 Release work completes • Technology upgrade complete in September 2012 • Required to ensure BSC Systems fully supported

  9. November 12 Release • Scope of Release: • No Approved Modifications to date • No approved Change Proposals to date • P278 targeted at Release • Four Change Requests • P278 • Impacts SAA software • Requires 10 week project • Earliest implementation date 29 November • November 12 Release date – propose change to 29 November

  10. November Release: Recommendations The BSC Panel is invited to: • NOTE the rationale to change the November 12 Release implementation date • AGREE that the November 12 Release implementation date be changed to 29 November 2012

  11. 196/05 P275: ‘Extending Performance Assurance’ Melinda Anderson 12 April 2012

  12. P275: Issue and solution Issue: • P275 argues that the Code implies the PAB acts only for Trading Parties • This would mean that PAB would not resolve issues for BSC Parties that are not Trading Parties (e.g. LDSOs) even though they rely on Settlement data and processes for a number of business purposes • This is not the case Solution: • P275 solution is to add a paragraph to Section Z to clarify the relationship between the PAB and all PAPs with respect to Z1.6.1 • Code-only change; scope of Performance Assurance unaffected

  13. P275: Panel’s initial views • No impact on Applicable Objectives (a), (b), (c) and (e) • The Panel unanimously agreed with the Workgroup’s majority view that P275 would better facilitate Objective (d) because increased BSC clarity promotes efficiency in the BSC arrangements • Unanimously agreed legal text • Unanimously agreed Self Governance • Unanimously supported implementation dates • 16WD if Self Governance or • 10WD following Authority decision

  14. P275: Report Phase Responses • No new arguments were presented • Majority support for Panel’s initial recommendation • Unanimous support for Implementation Date • Unanimous support for Self Governance • One comment on legal drafting • It does not deliver the original intent of Modification but delivers the eventual intention

  15. P275: Recommendations (1 of 2) The BSC Panel is invited: • NOTE Draft Modification Report • CONFIRM views on Applicable BSC Objectives • CONFIRM that P275 meets Self-Governance Criteria • APPROVE P275

  16. P275: Recommendations (2 of 2) • APPROVE Implementation Date: • 16 WD after approval or • 10WD after Authority decision • APPROVE BSC legal text • APPROVE Self-Governance Modification Report • NOTE appeal window closes 15WD after ELEXON’s notification of the Panel’s decision (3 May 2012)

  17. 196/06 P277: ‘Allow Interconnector BM Units to choose their P/C Status’ David Kemp 12 April 2012

  18. P277: Issue • Energy entering GB over Interconnector assigned to different Account to energy leaving GB • Applicable to both transit flows and flows starting/ending in GB • Without ECVN, in net imbalance even though net volume is zero Moyle 100MW out of GB Allocated to C Account Charged SBP IFA 100MW into GB Allocated to P Account Paid SSP

  19. P277: Solution • Single BM Unit per Interconnector per User • Lead Party can elect P/C Status of these BM Units • Allows Party to net import over one Interconnector and export over another • Volumes would not net to zero, due to transmission losses • Solution would be mandatory

  20. P277: Panel’s initial views on:Applicable Objectives • Relevant Objectives are (c) and (d) – no impact on (a), (b) and (e) • Majority – does not better facilitate (c) and (d): • Unduly discriminatory (c) • Current arrangements not barrier to entry (c) • Wouldn’t improve efficiency (d) • Minority – does better facilitate (c) and (d): • Interconnectors already treated differently (c) • Precedent for different treatment (c)

  21. P277: Panel’s initial views on:legal drafting • Legal text consulted on during Assessment • One minor comment made – amendment made accordingly • Drafting for BSCPs 15, 31 & 65 and CRA SD prepared during Assessment • Not consulted on during Assessment • Panel unanimously agreed drafting for Report consultation

  22. P277: Panel’s initial views on:Implementation Date • Unanimous Panel support for proposed Implementation Dates: • February 2013 Release • Fall-back June 2013 Release • Driven by East-West Interconnector

  23. P277: Report Phase Responses • No new respondents • No new arguments raised • Majority support for Panel’s initial recommendation • Unanimous support for Implementation Date • No comments on legal drafting

  24. P277: Recommendations (1 of 2) The BSC Panel is invited to: • NOTEthe P277 Draft Modification Report and the Report Phase Consultation responses; • CONFIRM the recommendation to the Authority contained in the P277 draft Modification Report that P277 should not be made;

  25. P277: Recommendations (2 of 2) • APPROVEan Implementation Date for P277 of: • 28 February 2013 if an Authority decision is received on or before 28 May 2012; or • 27 June 2013 if an Authority decision is received after 28 May 2012 but on or before 27 September 2012; • APPROVE the BSC legal text for P277; • APPROVE the changes to BSCP15, BSCP31, BSCP65 and the CRA Service Description for P277; and • APPROVE the P277 Modification Report.

  26. 196/07 P278: ‘Treatment of Transmission Losses for Interconnector Users’ David Kemp 12 April 2012

  27. P278: Issue • BSC allocates transmission losses to Interconnector BM Units • Anomalous in light of ITC scheme • Compensates TSOs for National losses caused by cross-border flows • National Grid passes through compensation to generators and Suppliers through TNUoS • Compensation can be positive or negative • Interconnectors should not be subject to additional network charges • GB arrangements need to comply with European legislation

  28. P278: Solution • Set TLM to 1 for Interconnector BM Units • BSC to no longer adjust Interconnector BM Unit Metered Volumes for any GB transmission losses • BSC would still allocate total GB transmission losses proportionally across all other types of BM Unit • Interconnector BM Units account for 2% of losses • Low materiality – volatility of losses can exceed this amount

  29. P278: Panel’s initial views on:Applicable Objectives • Relevant Objectives are (a), (c) and (e) – no impact on (b) and (d) • Majority – better facilitates (a), (c) and (e): • P278 most proportionate solution to demonstrate compliance • Minority – does not better facilitate (a), (c), and (e): • Undue discrimination (c) • May not be needed

  30. P278: Panel’s initial views on: legal drafting • Legal text consulted on during Assessment • No comments received • Panel unanimously agreed drafting for Report consultation

  31. P278: Panel’s initial views on:Implementation Date • Unanimous Panel support for proposed Implementation Dates: • November 2012 Release • Fall-back February 2013 Release • Driven by lead time for changes to central systems

  32. P278: Report Phase Responses • No new respondents • No new arguments raised • Majority support for Panel’s initial recommendation • One respondent was unsure • Unanimous support for Implementation Date • No comments on legal drafting

  33. P278: Recommendations (1 of 2) The BSC Panel is invited to: • NOTEthe P278 Draft Modification Report and the Report Phase Consultation responses; • CONFIRM the recommendation to the Authority contained in the P278 draft Modification Report that P278 should be made;

  34. P278: Recommendations (2 of 2) • APPROVEan Implementation Date for P278 of: • November 2012 if an Authority decision is received on or before 1 May 2012; or • 28 February 2013 if an Authority decision is received after 1 May 2012 but on or before 28 August 2012; • APPROVE the BSC legal text for P278; and • APPROVE the P278 Modification Report.

  35. 196/08 P282: ‘Allow MVRNs from Production to Consumption or Vice Versa’ David Kemp 12 April 2012

  36. P282 Allow MVRNs from Production to Consumption or Vice Versa Nigel Cornwall For Statkraft

  37. Metered Volume Reallocation Notifications • Dual trading accounts are key feature of Neta market template • designed to ensure larger, vertically integrated players could not enjoy netting benefit • MVRNs have from outset provided valuable flexibility for licensed parties to • consolidate generation or consumption volumes horizontally • in effect avoid active day-to-day participation in central trading arrangements • An unnecessary restriction exists, which P282 seeks to remove • this prevents energy from Production BM Units being transferred to Consumption Energy Accounts and vice versa

  38. MVRN restriction % volume or MWh Trading charges Consumption Consumption Production Production Subsidiary party Energy Account Lead Party BM Unit

  39. Defects • The current restriction: • is ineffective in its original assumed aim • competitive restrictions should be matter for regulation • e.g. mandatory auctions • inappropriately restricts participants’ ability in managing imbalance risk • denies organic commercial choices • imposes cost • unnecessarily complicates the trading arrangements • creates an inequity with embedded generation • can consolidate against demand • also sits uncomfortably with trading unit concept • treats trading parties differently from system operator • may not be in line with European practice

  40. Key benefits of P282 • Additional flexibility to manage imbalance risk, particularly for smaller participants to consolidate positions • increases efficiency • reveals true imbalance • competitive benefits • benefits relative to off-take market • Levels playing field with embedded generation • P100 de facto acknowledged desire to stimulate competition and permit consolidation • Reduces complexity of trading arrangements and costs of compliance • especially with regard to contract notification process • credit?

  41. Against BSC relevant objectives • c) (facilitating competition) - significantly, through additional flexibility to manage imbalance exposure to own circumstances and strategies. Risk reduction increases competition and encourages new entrants • d) (efficiency in arrangements) – removing an unnecessary restriction and helping trading parties manage their own costs • e) (European compliance) - may harmonise arrangements with those in Europe (P277 workgroup)

  42. Issues • Working group invited to consider: • if restriction should remain for participants over a certain size e.g. 20TWh annual production or consumption • single energy account alternative? • allow flag switching? • Targetted and proportionate relative to alternatives

  43. P282: Modification Proposal • Allow MVRNs from Production BM Units to Consumption Energy Account or vice versa • Would also allow a Party to MVRN energy from their Production BM Units to their own Consumption Energy Account or vice versa

  44. P282: Things to consider • What changes are needed to support the proposed solution? • What wider impacts would the proposed solution have? • How would GB’s two-Account arrangements be affected? • What benefits would Parties gain from P282? • What meaning would ‘Production’ and ‘Consumption’ hold? • What are the benefits to the Applicable BSC Objectives?

  45. P282: Proposed progression (1 of 2) • Recommend: 6-month Assessment Procedure (11 October 2012) • Workgroup membership should include: • Members of Settlement Standing Modification Group (SSMG) • Any other relevant experts and interested Parties • 6 months needed to allow: • Full assessment of wider impacts, including detailed analysis • Full consideration of wider implications • 20WD Industry IA and 15WD consultation • Avoiding Workgroup meetings during London 2012 Olympics

  46. P282: Proposed progression (2 of 2) • Proposer believes no link with any current SCRs • Possible interactions with Cash-Out SCR • Proposer is not requesting Self-Governance • Material impact on existing arrangements

  47. P282: Recommendations (1 of 2) The BSC Panel is invited to: • DETERMINEthat Modification Proposal P282 progresses to the Assessment Procedure; • AGREE the Assessment Procedure timetable such that an Assessment Report should be completed and submitted to the Panel at its meeting on 11 October 2012;

  48. P282: Recommendations (2 of 2) • DETERMINEthat the P282 Workgroup should be formed from members of the Settlement Standing Modification Group (SSMG), supplemented with any other relevant experts and interested Parties; • AGREE the Workgroup’s Terms of Reference; • AGREE that P282 has no interaction with any on-going SCRs; and • AGREE that P282 does not meet the Self-Governance Criteria.

  49. 196/09 Recommendation to raise a Modification Proposal: ‘Reinforcing the Commission of Metering Equipment Process Dean Riddell 12 April 2012

  50. Background • Metering Equipment subject to commissioning process (CoP4) • Metering System Registrant responsible • Typically discharged via appointed Meter Operator Agent (MOA) • Intended to prove accuracy of metering and detect problems • Failure may mask significant issues (unlikely to be detected later) • Technical Assurance of Metering Expert Group (TAMEG) and ELEXONconcerns • Certain Metering Equipment usually not within Registrant/MOA control when commissioning required • Issues prevent proper commissioning and lead to incomplete records

More Related