EL-TC 27.4.2005. 1. Overview 2. Photos of old installation 3. Outline of new project 4. Budget 5. Conclusions. Proposal for Renovation Project b. 151. K. KAHLE, TS-EL. 1. Project Overview. b. 151. PS Test (2006). ME6. 3 MeV (2006). LEIR (2005). LINAC 4 (2008). b. 152. b. 150.
E N D
EL-TC 27.4.2005 1. Overview 2. Photos of old installation 3. Outline of new project 4. Budget 5. Conclusions Proposal for Renovation Project b. 151 K. KAHLE, TS-EL
1. Project Overview b. 151 PS Test (2006) ME6 3 MeV (2006) LEIR (2005) LINAC 4 (2008) b. 152 b. 150
1. Overview • Hall 151: • Test of PS magnets • Test of RF equipment
2. Old installation EBD13*SHC - obsolete
2. Old installation EBD11*SHC - obsolete
2. Old installation EBD30 and EBD31*SHC - obsolete
2. Old installation Disconnected OIL CABLE in the cable duct
2. Old installation Old switchboard, disconnected
2. Old installation Spaghetti Bolognese
2. Old installation The purple snake
2. Old installation Socket box - obsolete
3. Outline of new project • dismantle obsolete switchboards • (ERD30*SHC, ERD31*SHC, EBD11*SHC, EBD13*SHC, EBD14*SHC) • NEW: one single switchboard 1000A (type EBD) • existing incoming cables remain (200m x 11 PVC 240 Cu from b.264) • this would free feeders from s/st ME6 • OPTION: • one large switchboard ERD + one switchboard EBD for Gen. Serv. • clean all cable ducts, dismantle unused cables • replace all outgoing cables from the new switchboard • remove all oil cables in the zone
5. Conclusion • Project is necessary: Safety Reasons • Project Duration 6 months • no manpower available • Project is defined now • START depending on available manpower + budget
Questions ? Thank you.