740 likes | 1.47k Views
6. Material Requirements Planning (MRP). Homework problems: 2,6,7,8,9,13. 1. MRP Foundation. Material requirements planning (MRP):
E N D
6. Material Requirements Planning (MRP) Homework problems: 2,6,7,8,9,13.
1. MRP Foundation • Material requirements planning (MRP): • A computer-based information system that translates master schedule requirements for end items into time-phased requirements for subassemblies, components, and raw materials. • The MRP is designed to answer three questions: • What is needed? • How much is needed? • When is it needed?
1. MRP Foundation • Dependent demand • Demand for items that are subassemblies or component parts to be used in the production of finished goods. • Dependent demand tends to be sporadic or “lumpy” • Large quantities are used at specific points in time with little or no usage at other times
What went wrong when EOQ is used to manage a dependent demand item ? • Incorrect assumption of uniform, continuous demand • Incorrect assumption on item independence • Lack of Forward visibility
MPR Inputs • Master Production Schedule (MPS) • Bill of Materials (BOM) • Inventory Records
MRP Inputs: Inventory Records • Inventory records/status data • Includes information on the status of each item by time period, called time buckets • Information about • Gross requirements • Scheduled receipts • Expected amount on hand • Other details for each item such as • Supplier • Lead time • Lot size • Changes due to stock receipts and withdrawals • Canceled orders and similar events
MRP Record Gross requirements • Total expected demand Scheduled receipts • Open orders scheduled to arrive Projected Available • Expected inventory on hand at the beginning of each time period
MRP Record Net requirements • Actual amount needed in each time period Planned-order receipts • Quantity expected to received at the beginning of the period offset by lead time Planned-order releases • Planned amount to order in each time period
Manufacturing Planning and Control System Resource planning Sales and operations planning Demand management Enterprise Resource Planning (ERP) System Master production scheduling Front End Detailed material planning Inventory status data Routing file Bills of material Time-phased requirement (MRP) records Detailed capacity planning Engine Material and capacity plans Shop-floor systems Supplier systems Back End
MPR: Development • The MRP is based on the product structure tree diagram • Requirements are determined level by level, beginning with the end item and working down the tree • The timing and quantity of each “parent” becomes the basis for determining the timing and quantity of the children items directly below it. • The “children” items then become the “parent” items for the next level, and so on
MRP: Updating PAB PABt=PABt-1 + SRt + PRt - GRt • PAB: projected available balance • SR: scheduled receipts • PR: planned order receipts • GR: gross requirements
Basic MRP Record A previously released order due in period 1 Requirements from all sources A unreleased order due in period 5
Bill of Materials The BOM shows the components and sub-assemblies required to produce one unit of product
Indented Bill of Materials Finished item is not indented Level 2 sub-assemblies Level 1 sub-assemblies Level 1 components Components and sub-assemblies are indented relative to their order of usage
Indented BOM example Finished product is located at the top, components below Sub-assemblies are represented by separate levels
MRP Explosion • Explosion–the process of translating product requirements into component part requirements • Considers existing inventories and scheduled receipts • Calculating the quantities of all components needed to satisfy requirements for any given part. • Continued until all parts have been considered, leading to exact requirements for all purchased and/or raw material parts
Gross and Net Requirements • Gross requirements represent the total planned usage for the part • Net requirements account for existing inventory and/or scheduled receipts 100 req’d – 25 inventory = 75 net req’d Net req’d for assembly becomes gross req’d for component 75 req’d – 22 inventory – 25 sched. rec. = 28 net req’d
Low-Level Coding • Low-level coding • Restructuring the bill of material so that multiple occurrences of a component all coincide with the lowest level at which the component occurs
Low Level Coding Level 0 Level 1 Level 2 14127 Rivet is a common part. It belongs to Level 2, not 1. Level 3
MPR Lot Sizing Rules (L4L) • Lot-for-Lot (L4L) ordering • The order or run size is set equal to the demand for that period • Minimizes investment in inventory • It results in variable order quantities • A new setup is required for each run
MPR Lot Sizing Rules (EOQ) • Economic Order Quantity (EOQ) • Also called fixed order quantity (FOQ) • Can lead to minimum costs if usage of item is fairly uniform • This may be the case for some lower-level items that are common to different ‘parents’ • Less appropriate for ‘lumpy demand’ items because inventory remnants often result
MPR Lot Sizing Rules (POQ) • Fixed Period Ordering (POQ) • Provides coverage for some predetermined number of periods • When an order is planned (i.e., planned order receipts), it should be sufficient to cover the next P periods (e.g., p=3)
Lead Time Offsetting • Gross to net explosion shows how much of each part is required, but not when • Timing requires consideration of two factors • Lead times–how long does it take to obtain the component or sub-assembly • Precedent relationships–the order in which parts must be assembled • MRP considers both factors when developing the plan
Scheduling Logic • Two common approaches to scheduling exist • Front schedule–schedule each step as early as possible. This approach is simple, but parts are scheduled (and finished) earlier than need be, thus increasing WIP inventory. • Back schedule–schedule each step as late as possible. This approach will reduce WIP, minimize storage (and time) of completed parts, reserve flexibility (postpone the commitment or raw materials to specific products), but it requires accurate BOM data and lead time estimation.
Scheduling Logic and MRP • MRP combines back scheduling and performs the gross requirements to net requirements explosion. • Reduced inventories • Minimized storage time
Back Scheduling Top handle assembly has the longest duration of any sub-assembly Scoop assembly must be complete before final assembly can begin Only when all sub-assemblies and components are available can final assembly begin
Planned order release for top handle assembly becomes gross requirement for top handle component and nail (note 2 nails required per assembly) MRP Records Lot-for-lot order policy exactly matches supply to net requirements Fixed lot size order policy requires orders in multiples of lot size
MRP Technical Issues • Processing frequency–recalculating all records and requirements is called regeneration • This is a computationally intensive process so it is often run in the background and during periods of low system demand • Net change approach only recalculates those records that have experienced changes • Less frequent processing results in an out-of-date picture • More frequent processing increases computer costs and may lead to system nervousness
Safety Stock & Safety Lead Time • Theoretically, MRP systems should not require safety stock • Variability may necessitate the strategic use of safety stock • A bottleneck process or one with varying scrap rates may cause shortages in downstream operations • Shortages may occur if orders are late or fabrication or assembly times are longer than expected • When lead times are variable, the concept of safety lead time is often used • Safety Lead Time (see Fig. 6.9) • Scheduling orders for arrival or completion sufficiently ahead of their need that the probability of shortage is eliminated or significantly reduced
Safety Stock & Safety Lead Time • Safety stock is buffer stock over and above the quantity needed to satisfy gross requirements • Used when quantity uncertainty is the issue • Safety lead time changes both the release and due date of shop and/or purchase orders to provide a margin for error • Used when timing of orders is the issue • Safety lead time is not just an inflated lead time
Pegging • Pegging provides a link between demand (order releases, customer orders, etc.) and the gross requirements for parts • Pegging records include the specific part numbers associated with a gross requirement • Pegging information can track the impact of a problem (e.g. material shortage) back to the order(s) it will affect
Firm Planned Orders • Regeneration of the MRP records can lead to large numbers of planned order changes • To avoid this, a planned order can be converted to a firm planned order (FPO) • An FPO is not the same as a scheduled delivery, but can’t be changed by the MRP system • Temporarily overrides the MRP system to provide stability or to solve problems
Planning Horizon • Total amount of time included in MRP calculations • Longer planning horizon increases computational requirements • Shorter planning horizon may result in less-effective plans if significant future demand is not visible • At a minimum, should cover the cumulative lead time for all finished goods items
Scheduled Receipts vs. Planned Order Releases • Scheduled receipts represent an actual commitment (purchase order, production order, etc.) • Planned orders are only the current plan and can be changed more easily • Scheduled receipts for production orders already have component materials assigned • Scheduled receipts do not impact gross requirements • Planned order releases do not have component materials assigned • Planned order releases do impact gross requirements
MRP Processing Example Note: Component D is required by two parents.
Bottom-Up Replanning • Using pegging data to guide efforts to solve material shortages • Pegging data allows the planner to take action only when actual customer orders are impacted
MRP System Output Part number and description MRP system data MRP planning data Exception messages
System Dynamics • An MRP is not a static document • As time goes by • Some orders get completed • Other orders are near completion • New orders will have been entered • Existing orders will have been altered • Quantity changes • Delays • Missed deliveries • See Figure 6.11,6.12,6.13
Principles • Effective use of an MRP system allows development of a forward-looking approach to managing material flows. • The MRP system provides a coordinated set of linked product relationships, which permits decentralized decision making for individual part numbers. • All decisions made to solve problems must be implemented within the system, and transactions must be processed to reflect the resultant changes. • Effective use of exception messages allows attention to be focused on the “vital few” rather than the “trivial many.”