RCC Meeting 13 December 2007. Interconnections: primary market IP Taisnières / Blaregnies / Quévy IP Obergailbach / Medelsheim Key achievements Since the RCC of Sept 2007. Agenda. IP Taisnières / Blaregnies Coordinated open seasons Fluxys / GRTgaz Interruptible transit and transparency

essien
Download Presentation

RCC Meeting 13 December 2007

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RCC Meeting13 December 2007 Interconnections: primary market IP Taisnières / Blaregnies / Quévy IP Obergailbach / Medelsheim Key achievements Since the RCC of Sept 2007

  2. Agenda • IP Taisnières / Blaregnies • Coordinated open seasons Fluxys / GRTgaz • Interruptible transit and transparency • IP Obergailbach / Medelsheim • Transparency • Diagnostic • 2008 • Questionnaires and IP meetings • The other IPs

  3. Open seasons of Fluxys and GRTgazOn track • High interest of the market for additional capacity showed during the first non binding phase • Information meeting for shippers organised by GRTgaz in October • Allocation mechanisms for shippers submitting binding bids published • New agenda: • January 4, 2008: Deadline for submitting binding bids • January 31, 2008: Capacity allocation by GRTgaz • February 1-28, 2008: Capacity allocation by Fluxys and contracts signature with GRTgaz • Memorandum of Understanding between Fluxys and GRTgaz • Open seasons closely monitored by regulators

  4. Obergailbach/Medelsheim– Transparency • From February 2008, GDFDT will publish its daily flows on Internet • EGT’s information on capacity for the coming 3 gas year available since October • EGT: Flows publication since Dec 1, as prescribed by the Reg. 1775/2005 (i.e. monthly maximum and minimum capacity utilisation rate), as more than 2 shippers active in the last 36 months

  5. Obergailbach/Medelsheim Joint diagnostic • TSOs produced a joint diagnostic, as of July 2007, of the products offered • No firm capacity available for EGT and GDFDT until at least September 2010. • Available firm capacity for GRTgaz from March 2008. • Interruptible capacity with different quantities and features: • Temperature dependent: not available for EGT, GDFDT, available from December 2009 for GRTgaz. • Short term interruptible UIOLI (product of GRTgaz): available • Overbooking for unlimited interruptible capacity (products of EGT and GDFDT): available

  6. 2008: IP meetings and questionnaires • IP meetings to be held at the end of January 2008 for Obergailbach / Medelsheim and Blaregnies / Taisnières, in order to further enhance the functioning of these IPs. • Prior to this meeting, questionnaires to shippers to voice their concerns and demands concerning: • Improvement of the use of existing capacity and harmonisation of capacity products for H gas and L gas • Backhaul services • Transit of L gas through Belgium • Potential need for additional capacity • Transparency

  7. 2008: Proposals • At the Bonn workshop in February 2008, 8 IPs have been classified as important : • Taisnières, Obergailbach and Bunde Oude Statenzijl • 5 remaining IP: Bocholtz (G/NL), Ellund (G/DK), Eynatten (G/B), Zelzate (B/NL) and Bacton (UK-NL/B) • Discussion on whether to tackle these IPs in 2008 • Address the coming cross-border open seasons in the NW GRI