NERC ATC STANDARD April 22, 2009 HISTORY -

NERC ATC STANDARD April 22, 2009 HISTORY -. Aug 2008 ATC Standards submitted to FERC for approval March 19, 2009 FERC issued a NOPR regarding the proposed new ATC Standards. How was the Rated System Path ATC Calculation Methodology Standard (MOD-029) Developed?.

eulalie
Download Presentation

NERC ATC STANDARD April 22, 2009 HISTORY -

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NERC ATC STANDARDApril 22, 2009HISTORY - • Aug 2008 ATC Standards submitted to FERC for approval • March 19, 2009 FERC issued a NOPR regarding the proposed new ATC Standards.

  2. How was the Rated System Path ATC Calculation Methodology Standard (MOD-029) Developed? • ANS – It was modeled after the WECC Path Rating Process.

  3. What do the NERC ATC Standards require for the Rated System Path Methodology? • Power flow model requirements– R1 • Power flow simulation for all “ATC Paths – R2.1 • “Existing Ratings” respected – R2.7 • Check for simultaneous interaction – R2.4 & R2.5 • Study report for every TTC study – R2.8 • Equations for calculation of ETC & ATC – R5 – R8 • Limitation on CBM & TRM – MOD-004, -008 • Documentation on ATC, CBM & TRM calculations “Implementation Document”

  4. What do the NERC STC Standards apply to? • All “ATC Paths” which are “any combination of Point of Receipt and Point of Delivery for which ATC is calculated; or any Posted Path.” • Only apply out to 13 months in the future – MOD-001 R2.

  5. What did the FERC NOPR address? • Approval of the NERC ATC Standards with certain exceptions and clarifications- • NERC to audit TP’s ATCID, CBMID & TRMID within 180 days of effective date of standards – Par 80-101 • Implementation Documents available to all transmission customers – Par 103-105 • Elimination of “Grandfathering” requirement R2.7 – Par 112-115 • More specificity regarding calculation of NITS Existing Transmission Commitments – Par 116-120 • Extend the standards into the planning horizon via FAC-012, -013 – Par 135-138 • Other “tweeks” regarding CBM, double counting, VSL’s & VRF’s, & definitions

  6. Questons/Problems the ATC Standards generate • Contractual issues if ATC after restudy is less than existing committments • Curtailment issues if simultaneous interaction discovered between paths with “Existing” ratings • Confidence issues if limiting element for one path rating is dependent on rating of another path that hasn’t been re-studied.