State Veterans Homes Recognized (February 2010 – February 2011)

State Veterans Homes Recognized (February 2010 – February 2011). 5 New Homes and/or Additions to Existing Homes Representing 4 States: CA: Ventura (60-Bed DOM) CO: Rifle (80-Bed NHC- Reduced ) Homelake (50-Bed DOM- Replacement ) NY: Oxford (242-Bed NHC - Replacement )

forbes
Download Presentation

State Veterans Homes Recognized (February 2010 – February 2011)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. State Veterans Homes Recognized(February 2010 – February 2011) 5 New Homes and/or Additions to Existing Homes Representing 4 States: CA: Ventura (60-Bed DOM) CO: Rifle (80-Bed NHC-Reduced) Homelake (50-Bed DOM-Replacement) NY: Oxford(242-Bed NHC - Replacement) UT: Ogden (120-Bed NHC)

  2. State Veterans Homes Recognized(February 2010 – February 2011) Representing 552 new/replacement beds: New: 120 Nursing Home Beds 60 Domiciliary Beds Replacement Beds: 322 Nursing Home Beds 50 Domiciliary Beds

  3. Upcoming State Veterans Homes(To Be Recognized) 5 New Homes and/or Replacements 60-Bed Domiciliary, Lancaster, CA 84-Bed Domiciliary, West Los Angeles, CA 120-Bed Nursing Home, Lake City, FL 40-Bed Nursing Home, (Replacement) Fort Bayard, NM 122-Bed Nursing Home, (Replacement) Sulphur, OK

  4. SVH Recognition Process ESTIMATED Timeline-After the initial request letter is received from the State: 6 – 9 Months: The Entire Process 1 – 2 Weeks: Once all materials are received 1 – 2 Months: Internal Concurrence Process

  5. SVH Recognition ProcessInitial Contact • Send letter to Chief Consultant, GEC requesting recognition and certification • Letter must be signed by the State official authorized to establish the home. Please include: • FAI Number • Total numbers of beds with levels of care • Allow VA to survey the facility (State Home Regulation: 38 Part 51. Subpart B §51.20)

  6. SVH Recognition Process ESTIMATED Timeline-After the initial request letter is received from the State: 6 – 9 Months: The Entire Process 1 – 2 Weeks: Once all materials are received 1 – 2 Months: Internal Concurrence Process

  7. SVHRecognition Process Major Obstacles Completion of the Survey Securing the proper number of residents prior to survey Indicating ALL standards are met Collecting all the necessary forms

  8. Recognition Survey All documents in the Construction Grant phase must be completed To be recognized the SVH must meet ALL standards set by VA Per Diem is granted on the date all standards are met

  9. SVH Recognition Process Thank You!