1 / 65

Long-Term Plan Update

Long-Term Plan Update. Process Development and Engineering (PDE) February 28, 2006 Long-Term Plan Annual Update Matahel Ansar, P.E. Acquisition of Survey Data. Project Manager: Howard Ehmke Project Description:

fran
Download Presentation

Long-Term Plan Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Long-Term Plan Update Process Development and Engineering (PDE) February 28, 2006 Long-Term Plan Annual Update Matahel Ansar, P.E.

  2. Acquisition of Survey Data Project Manager: Howard Ehmke Project Description: • Topographic surveys were performed inside the STAs to more clearly delineate ground surface elevations between interior levees and control structures • Vertical control surveys were conducted at flow measurement stations to confirm, and correct where necessary, gage datum elevations

  3. Acquisition of Survey Data Project status Work completed to date (FY04 and FY05): • Vertical Control Surveys • All planned vertical control survey work complete • Topographic Surveys • All planned STA surveys complete

  4. Additional Flow & Water Quality Monitoring Stations Project Manager: Matahel Ansar Project Description: • Establishment of 47 new flow and water quality monitoring stations for the STAs • These additional monitoring stations are mostly in STA-3/4 in FY04 (11 structures), in STA-1E in FY05 (19 structures), and in STA-2 & STA-1W in FY06 (4 structures)

  5. Additional Flow & Water Quality Monitoring Stations

  6. Additional Flow & Water Quality Monitoring Stations Project status • Work completed to date • All FY04 stage-related work completed: 9 culverts in STA-3/4 and 2 culverts in STA-1W (G-258 gate sensors & G-259) • FY05 work completed: STA-3/4 structures G-380 B&E, G-381 B&E certified and registered and flow computations have been implemented in the FLOW program • All 9 culverts in STA-3/4 certified and registered and flow computations have been implemented in the FLOW program

  7. Additional Flow & Water Quality Monitoring Stations Project status • Work planned for remainder of FY06 • Validation tests for water quality samplers at G-370 and G-372 seepage pumps – scheduled for completion on 28th February 2006 • Validation tests for water quality samplers at 9 culverts: G-374B&E, G-375B&E, G-377B&D, G-378B&D, and G-383 - scheduled for completion on 28th February 2006 • Install and survey stilling wells at G-383 - scheduled for completion by May 2006

  8. Additional Flow & Water Quality Monitoring Stations • Work planned for remainder of FY06 (Continued) • 19 structures in STA-1E completed, certification to be completed by March 2006 • 2 new stations in Cell 2A of STA-1W – to be completed May 2006 • By end of FY06, 42 of 47 stations will be complete, with 5 stations to be completed in FY07

  9. Correction of Flow Measurements Anomalies Project Manager: Emile Damisse Project Description: • To address anomalies in discharge measurements, and provide good quality flow data at all major flow stations in the STAs • Complete correction of Flow Measurement Anomalies in STA-1E and STA-3/4 by the end of FY06

  10. Correction of Flow Measurement Anomalies Project status • Work completed to date • 465 streamflow measurements

  11. Correction of Flow Measurement Anomalies Project status • Work completed to date • 106 rating analyses at 99 stations

  12. Correction of Flow Measurement Anomalies Rating Analysis calibration and validation • 90% Completed at STA-3/4 culverts • 50% Completed at STA-3/4 pumps - two major pumps are validated while the seepage pumps will be validated during FY06 • 25% Preliminary rating validation at STA-3/4 • 90% Completed at STA-2 • 50% Completed at STA-6 culverts • 100% Completed at STA-6 pumps • 100% Completed at the two pumps in STA-1W • 100% Completed at the two spillways in STA-1W • 90% Completed at culverts in Cell 5 STA-1W - implementation is pending on the SOP

  13. Correction of Flow Measurement Anomalies

  14. Correction of Flow Measurement Anomalies Flow Rating Equations for G-370 and G-372

  15. Correction of Flow Measurement Anomalies Project status • Work planned for remainder of FY06 • Perform streamflow measurements: 132 measurements at 70 stations

  16. Correction of Flow Measurement Anomalies Rating Analysis Prediction for FY 2006 70 60 50 40 30 20 10 0 STA1W STA2 STA5 STA6 STA1E STA3/4 10 7 5 3 62 60 Analysis 4 8 5 3 17 12 # of Station Project status • Work planned for remainder of FY06 • Perform/complete Rating Analysis: 147 rating analyses at 49 stations

  17. Long-Term Plan Update Process Development and Engineering (PDE) February 28, 2006 Long-Term Plan Annual Update Tracey Piccone, P.E.

  18. Update and Maintenance of Hydraulic Models Project Manager: Tracey Piccone Project Description: • Evaluate and predict changes in flow distribution as the STAs mature and change with time • Develop calibrated two-dimensional hydraulic simulation model of each STA • Regularly update and calibrate the models as new information is received (topo, structural, vegetation)

  19. Update and Maintenance of Hydraulic Models Work completed to date • Work Order completed with Sutron Corporation • Used FESWMS/SMS • New models of STA-2, STA-6, STA-1E, STA-1W, STA-5 and STA-3/4 • Three flow conditions: Low Flow, Design Flow, and Peak Flow • Developed, calibrated, and verified models for STA-1W, STA-2, STA-3/4, STA-6 Section 1 • Future efforts will improve upon STA models for which calibration data was not available (STA-5, STA-1E)

  20. Update and Maintenance of Hydraulic Models • All reports posted at: • http://www.sfwmd.gov/org/erd/longtermplan/documents.shtml • Work planned for remainder of FY06: • Refine models with updated calibration, topographic, and vegetation data when available • Modeling in support of decision-making for operational and structural modifications

  21. Continued Development DMSTA Project Manager: Kathy Pietro Project Description: • Refine and update the DMSTA model, including reservoir component • Develop calibrated DMSTA model for each STA as additional full-scale data becomes available

  22. Continued Development DMSTA Project status • Work completed to date: • FY05 and FY06 work funded by the U.S. Army Corps of Engineers and Department of the Interior (Dr. Bill Walker) • Tasks completed to date: • Built reservoir module • Updated STA calibration • Enhanced Phosphorus Cycling component • Updated model platform • DMSTA v.2 was released April 2005 • Used for EAARFS evaluations in mid-2005

  23. Water Quality Impacts of Reservoirs Project Manager: Yanling Zhao Project Description: • Assist the EAA Storage Reservoirs Phase 1 PDT in the acquisition and analysis of calibration data sets for water quality impacts associated with reservoirs. These calibration data sets will be obtained from similar water bodies in central and southern Florida i.e., Lake Apopka, Lake Jessup, the Brevard County Stick Marsh and the Sun Ag reservoir, as well as Lake Istokpoga and other large-scale water supply reservoirs in South Florida. • Develop data files and summary report(s) of data sets collected and analyzed for use in calibrating reservoir components of water quality model(s)

  24. Water Quality Impacts of Reservoirs Project Status: • All lake and reservoir data was provided to Dr. Bill Walker for use in calibrating reservoir module of DMSTA2 • All data is accessible through District’s web site: • http://spatial1.sfwmd.gov/wqir/ • All Project Deliverables are posted at: • http://www.sfwmd.gov/org/erd/longtermplan/documents.shtml • All work complete • 1.5 years early • $1.2 million under recommended budget

  25. Evaluation of Full-Scale STA Enhancements Project Manager: Tracey Piccone Project Description: • Complete demonstration projects including construction of a limerock berm in Cell 5B of STA-1W and implementation of vegetation management measures designed to improve STA performance • Project is being funded by a cost-share agreement between the District and the DEP • District received grant funding in the revised amount of $1.1 million from DEP/EPA (original proposal $1.3 million) • Project includes management of DEP Grant Agreement G0040 • Results of the demonstration projects can be applied to other STAs to improve their performance

  26. Evaluation of Full-Scale STA Enhancements Project Status – Limerock Berm • Limerock berm was completed in STA-1W Cell 5 in August 2003 • With-berm Cell 5 outflow phosphorus concentrations will be compared to pre-berm values • Dye Tracer Project was completed in early FY05 • 2004 Hurricane Damage Repairs completed in early FY05 • Top elevation of berm was lowered in 2005 for consistency with revised Cell 5 target stage • Summary report underway

  27. Evaluation of Full-Scale STA Enhancements Project status - STA-3/4 Vegetation Management Demonstration Project • 50 sites inoculated with SAV in August 2004 • Inoculated species root in October-November 2004 • Natural colonization at locations without vegetation • Initial SAV grow-in assessed March 2005 • Second assessment March 2006

  28. Evaluation of Full-Scale STA Enhancements • Work planned for remainder of FY06 • Complete summary report for limerock berm • Continue monitoring STA-3/4 Cell 2B vegetation management demonstration project • Ongoing submittal of quarterly progress reports and invoices to FDEP • Amend agreement with FDEP to extend by 6 months • To include results of March 2006 SAV assessment • Complete Final Grant Project Report

  29. Update Baseline Data Sets Project Manager: Tracey Piccone Project Description: • Update the analyses presented in the Baseline Data report to continually improve the degree of confidence in the projected total phosphorus loads in inflows to the stormwater treatment areas (or, in some instances, discharged directly to the EPA)

  30. Update Baseline Data Sets Status • First update completed in FY05 as part of EAA Regional Feasibility Study • Work was completed by District staff and consultants • Flows and loads entering STAs higher than estimated in LTP • Revised flows and loads used during Regional Feasibility Study to evaluate alternatives for optimizing STA performance • No work scheduled for FY06 • Next update scheduled for FY07

  31. Basins with Limited Current Data Project Manager: Kathy Pietro Project Description: • To enhance the water quality and quantity data for basins with limited current data, e.g., C-51 West and C-11 West Basins

  32. Basins with Limited Current Data Project status • Work completed to date: • C-51 West Basin • Final Report posted at: • http://www.sfwmd.gov/org/erd/longtermplan/documents.shtml • A regression equation was developed for estimating daily phosphorus concentrations, and this was applied to the 31-year simulated runoff used in the Long-Term Plan, a document developed for achieving compliance with the phosphorus criterion

  33. Basins with Limited Current Data Project status • The resulting phosphorus levels were 38% lower (115 ppb compared to 185 ppb) than the estimates used in developing the STA performance projections associated with the Long-Term Plan • Updated projections were used in EAA Regional Feasibility Study

  34. Basins with Limited Current Data Project status • No work scheduled for FY06 • Next work scheduled for FY07

  35. Influence of CERP Projects on Inflow Volumes and Loads Project Manager: Tracey Piccone Project Description: • Update the projected impact of CERP projects on inflow volumes and loads to STAs and receiving water bodies of the Everglades Protection Area • Two updates to the estimated STA inflows (one upon completion of EAA Storage Reservoirs Project Phase 1 PDT and one upon completion of Phase 2 PDT)

  36. Influence of CERP Projects on Inflow Volumes and Loads Status • First update completed in FY05 as part of EAA Regional Feasibility Study • Updated information on the EAA Storage Reservoir project used during the EAA Regional Feasibility Study • Second update scheduled for end of FY2010

  37. Lake Okeechobee Long-Term Trends Project Manager: Kathy Pietro Project Description: • To better understand the temporal and spatial relationship between Lake Okeechobee nutrient status and operation (e.g., choice of outflow point) on phosphorus loads discharged to the STAs • In conjunction with Lake Okeechobee PDT, update the TMDL modeling and trend analyses • Conduct a temporal and spatial trend analyses for TP at outflow points that deliver water to the STAs and reservoirs

  38. Lake Okeechobee Long-Term Trends Project status • Work completed to date: • Reviewed project with Lake Okeechobee staff • Obtained available data • Work planned for remainder of FY06: • Continue to coordinate with Lake Okeechobee staff • Develop approach for updating STA input data sets

  39. Long-Term Plan Update Determine Relationship Between Discharges and Water Quality Within the EPA Tracey Piccone, P.E.

  40. Determine Relationship Between Discharges and Water Quality Within the EPA Project Manager: Tracey Piccone (interim) Project Description: • Define the relationships between the quality of water discharged into, and the water quality within, the Everglades Protection Area. The Parameter of Concern: • Phosphorus

  41. Determine Relationship Between Discharges and Water Quality Within the EPA Project Status Work completed to date: • Initial analyses conducted by District staff in FY04 and FY05 • No clear relationship was determined • Currently working with FDEP to revise scope of project to obtain necessary information

  42. Determine Relationship Between Discharges and Water Quality Within the EPA Work planned for remainder of FY06: • Proposed revision to extend project completion date by 2 years (from FY05 to FY07) • Provide funding for soil phosphorus reflux study • New soil data to be used with forthcoming models (EPGM/DMSTA/Refuge model) to gain information on relationship between discharges and water quality within the EPA

  43. Long-Term Plan Update Process Development and Engineering (PDE) February 28, 2006 Long-Term Plan Annual Update Jana Newman

  44. ECP Operational Monitoring Project Manager: Linda Crean Project Description: Operational monitoring of the STAs • Weekly/biweekly water quality collection and sample analysis for TP, SRP, TDPO4, OPO4, TSS, Ca, Cl, ALK, TKN, NH4, and NOx • Maintenance (plus purchase and installation as required) of sampling and flow monitoring equipment • Calibration of autosamplers and weir structures • Quality control for the collection, analysis, and archiving of the data collected • Calibration, installation, monitoring, data collection, maintenance, QA, and archiving of flow data for all the flow structures indirectly associated with permit compliance but necessary for flood control and STA Optimization

  45. ECP Operational Monitoring Project Status • Collection of flow measurements and weekly/ biweekly water quality samples (grabs and autosamplers) from interior non-permit sites in STA-1W, STA-2, STA-3/4, STA-5, and STA-6 on-going • Collection of bi-weekly grabs at internal STA-1E stations by March 2006 • Activation of autosamplers in STA-1E should be completed in FY06

  46. Analysis and Interpretation Project Manager: Jana Newman Project Description: • Ecological assessment of data obtained from the permit compliance and operational monitoring • Annual vegetation maps and synoptic water collection along with tri-annual collection and analysis of sediment from all internal cells of the STAs • Staff will provide annual phosphorus inflow/outflow budgets for the internal cells, short-term and long-term analyses in support of operational assessment • Establish sampling design for all STA internal cells

  47. Analysis and Interpretation Project status • Work completed to date • Hired contract staff for data analysis and project management through Sept. 2009 • 2005 internal water collection completed • Biweekly nutrient sampling at inflow and outflow of each cell ongoing • Vegetation maps for STAs 1W, 1E, 2, 5, and 6 completed • Optimized number of internal sample sites • Calculated TP mass budgets for each cell of each STA; results reported in the 2006 SFER • Work planned for remainder of FY06 • Calculation of inflow/outflow TP mass budgets for each cell of each STA • Complete annual vegetation maps for all STAs • Monitor STA-1W, Cell 5 drawdown and enhancements effort

  48. STA-5 Vegetation Map

  49. STA Sediment Analysis STA1E STA1E STA1E STA1E STA1E STA1W STA1W STA1W STA1W STA1W STA2 STA2 STA2 STA2 STA2 STA3/4 STA3/4 STA3/4 STA3/4 STA3/4 STA5 STA5 STA5 STA5 STA5 STA6 STA6 STA6 STA6 STA6

  50. PSTA Investigations Project Manager: Jana Newman Project Description: • To track the performance of District PSTA field-scale and test cell demonstration projects and factor the results into Post-2006 projects, as appropriate • Additionally, periphyton systems under investigation by the USACE at STA-1E and C-111 are under investigations, and to the extent possible, the District will invite the researchers to submit their data to the District for use in DMSTA model forecasting

More Related