An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GLYNN COUNTY • Project Commencement • Public Meeting • East Beach Utilities Infrastructure Improvements • December 5, 2007 • 7:00 p.m. • CASINO Room 108

  2. Glynn County Board of Commissioners INTRODUCTIONand OPENING REMARKS

  3. Sanitary Sewer Replace sagging and reverse grade sewer lines Proactive approach to reduce inflow and infiltration (I&I) problems Primary source of I&I is main lines and service laterals EAST BEACH OBJECTIVES

  4. EAST BEACH OBJECTIVES Sanitary Sewer • Reduce odor problems • Reduce maintenance service calls for East Beach area • Provide for better wastewater transmission via a pump station behind the Coast Guard station

  5. EAST BEACHOBJECTIVES Water System • Improve pressure within the system and fire flow capabilities Storm Drainage System • Improve drainage to relieve localized flooding

  6. Contractor is Douglas Electric and Plumbing Company of Douglas, GA Notice to Proceed December 17, 2007 Total project cost is $9.1 M EAST BEACH PROJECT STATUS

  7. SCHEDULE • Preliminary Start of Construction Early January 2008 • Construction Period 18 Months • Estimated Completion June 2009

  8. SERVICE LINE RESTORATION Homeowner Responsibility • Sanitary sewer service line installation on private property will be the responsibility of the homeowner • Water service line installation on private property will be the responsibility of the homeowner

  9. SERVICE LINE RESTORATION Glynn County Responsibility • All water, sewer and drainage construction within the public rights-of-way and easements will be performed by Glynn County • New radio read water meters will be installed in the East Beach neighborhood

  10. PUBLIC PROPERTY • Streets will be repaved • Contractor will seed all disturbed areas upon completion of work • Landscape plants will not be restored • Permanent structures on rights-of-way will not be restored • Walls, Brick Mailboxes, etc.

  11. PRIVATE PROPERTY • Driveway restoration of paved driveways will be limited to plain concrete or asphalt • Irrigation systems in the rights–of-way will not be restored

  12. COMMUNICATION • Letters to property owners • Door hangers • Glynn County website www.glynncounty.org • Verbal notification

  13. COMMUNICATION • Public Meetings • CGL will be the primary point of contact during the construction phase for homeowners

  14. PROGRAM MANAGER Travis Thomas Carter Goble Lee, LLC 1801 B Gloucester Street Brunswick, Georgia 31520 Office (912) 264-0357 Mobile (770) 560-1146 tthomas@leedesign.com GLYNN COUNTY ENGINEERING Jim Bruner, P.E. Engineering Department 700 Gloucester Street Brunswick, Georgia 31520 (912) 554-7495 jbruner@glynncounty-ga.gov GLYNN COUNTY ADMINISTRATION Becky Rowell 701 G StreetBrunswick, Georgia 31520 (912) 554-7171 browell@glynncounty-ga.gov www.glynncounty.org CIVIL ENGINEER Brennan Jones, P.E. Integrated Science & Engineering 105 McIntosh Crossing Fayetteville, Georgia 30214 (770) 461-4292 bjones@intse.com CONTACTS

  15. Questions and Comments