Evolution of the Williston Basin Drilling Pad ;

Evolution of the Williston Basin Drilling Pad ;. Drilling Pad. What affects a drilling pad Types of pads in North Dakota Advances in pad construction. What affects a drilling pad. Placement Geology Unit spacing Topography Protected Easements Road infrastructure

geneva
Download Presentation

Evolution of the Williston Basin Drilling Pad ;

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Evolution of the Williston Basin Drilling Pad;

  2. Drilling Pad • What affects a drilling pad • Types of pads in North Dakota • Advances in pad construction

  3. What affects a drilling pad • Placement • Geology • Unit spacing • Topography • Protected Easements • Road infrastructure • Gathering infrastructure • Flood potential • Erosion control • City / county / state regulation • Size • Rig foot print • Numberof wells • Battery size • Flare orientation • Panic line distance • Topography • Necessary Frac crew space • Solids control plan • Construction • Soil Moisture • Number of wells on pad (Traffic Volume) • Weather • Seasonal consideration of operations

  4. Prehistoric Drilling Pad(pre 2000’s - 2011) • A thing of the PAST

  5. Single Well Pad • Purpose: HBP and Test a spacing unit • Size: 300’x500’

  6. Dual Well Pad • Purpose: Develop a single 1280 and minimize impact • Allows for full development with only 4 locations • Size: 300’x550’

  7. Three Well Pad • Purpose: Develop a full 2560 acre spacing unit and minimize impact of foot print • Size: 395’x550’

  8. Eco Pad • Four Wells • Purpose: Develop a full 2560 acre spacing unit & minimize foot print • Size: 395’x550’ • SIMULTANEOUS OPERATIONS Four Well Eco Pad: 550’x700’

  9. Eco Well Pad

  10. Cyclone # 28

  11. Multi Well Pad • Purpose: • Meet requirements for multiple wells • Minimize impact • Overcome rough terrain, & access issues (water) • Size: 6 - 14 Wells 550 x 750

  12. Multi Well Pad

  13. Cyclone #2 Total Footage: 79,521’ @ Day 80

  14. Lifecycle of Drilling Pads • Scoria – 2 yrs. – Avg. maintenance $5-7K / yr. • Gravel – 5 yrs. – Avg. maintenance $2-4K / yr. • Textile Reinforced – 7 – Avg. maintenance $1.5-3K / yr. • Cement Stabilized – 10 – Avg. maintenance $500-2000 / yr.

  15. Materials to Extend Lifecycle of Pads • 2 ply wood mats: wood mats interlocking form surface on location • Composite mats: Composite mat systems form surface on location • Reinforced Geotextiles: High strength fabrics for separation & reinforcement of soil and aggregate • Geo Cell System: Plastic 3-D soil confinement system • Cement Stabilization: Blending cement with native soil to create a more durable surface.

  16. 2-Ply Wood Mats - OK • Advantages: • Less expensive • Available • Disadvantages: • Absorb Liquid • Damage Easily • Slip & trip hazard when wet • Cost • $2.50 / sq. yd.

  17. Composite Mats - Good • Advantages: • Light weight, easy to move • More durable • Low or no work over pad cost when placed over surfacing • Minimize days to sales • Disadvantages: • Leasing - Mats not for sale • Time to place on location • High demand • Cost • $5.00 / sq. yd.

  18. Geotextiles - Good • Advantages • One size fits all solution • Deployed quickly • Disadvantages • Not easily removed • Difficult to “repair” • Life and stability of material is dependant upon load size, traffic, water • Cost • $4.00 – 7.00 / sq. yd.

  19. Geo Cell System - Better • Advantages • Reduce vertical and lateral movement • Less surface material required • Product life estimated 25 years • Can be placed in low temps where cement cannot • Disadvantages • Labor intensive to place • Cost • $7.50 – 10.00 / sq. yd.

  20. Cement Stabilization - Best • Advantages • Reduces Trucking Impacts – Less surfacing material • Harder sub-grade • Lower maintenance • Disadvantages • Must be placed in temps above 40°F • Time for shipping and coordinating product • Preplanning of battery, electrical, flow lines, etc. • Cost • $7.50 – 10.00 / sq. yd.