An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CenterPoint Dynamic Reactive ProjectBoard of DirectorsAugust 15, 2006Bill BojorquezDirector, System Planning

  2. Description of Project • 2 Sites Selected: • - Bellaire • - Crosby • Estimated Cost $20 – 25 M for devices and all construction. • In-Service by Peak 2008. Installation of devices (type to be determined through RFP) to provide dynamic reactive support at two substations in the Houston area

  3. Project is Needed for Reliability Project is needed to: • Maintain voltage within acceptable limits following severe (NERC Category D) contingencies • Operating Guide 3.1.4.6, Protective Relaying Requirement • Maintain level of load shed following Category D contingencies to acceptable level • Limit the amount of load shedding to less than 1250 MW to avoid possible over frequency tripping, loss of significant local demand, and mitigate risk of cascading regional blackout

  4. Multiple Facility Forced Outages • ERCOT surveyed Transmission Operators to determine frequency of extreme events resulting in two or more components removed or cascading out or service – NERC Category D • Results Showed: • Average 19.71 events per year • Average 3.89 circuits removed per event • Average Time Between Events – 16.67 Days • Similar MAAC Data compiled by PPL Electric Utilities showed an average of 18.4 events per year with 2.4 to 2.6 circuits removed per event.

  5. Stakeholder Review • The Regional Planning Group stakeholder review period for this project was held in April 2006 • The project was presented to TAC at the August 3rd meeting • There have been no dissenting comments on this project through the RPG or at TAC

  6. ERCOT Support For the Project ERCOT staff recommends that the Board endorse the need for the CenterPoint Dynamic Reactive Support Project as described in the ERCOT report to the Board.