DEPARTMENT OF HEALTH AND SOCIAL DEVELOPMENT VOTE 07: HEALTH Third QUARTER Provincial Budget Review PRESENTED BY HONOURABLE Mme M.R.K SEGABUTLA MEMBER OF EXECUTIVE COUNCIL. HOSPITAL REVITALIZATION GRANT (HRG) 3 rd QUARTER EXPENDITURE TRENDS 2007/08-2009/10.
E N D
DEPARTMENT OF HEALTH AND SOCIAL DEVELOPMENT VOTE 07: HEALTH Third QUARTER Provincial Budget Review PRESENTED BY HONOURABLE Mme M.R.K SEGABUTLA MEMBER OF EXECUTIVE COUNCIL
HOSPITAL REVITALIZATION GRANT (HRG) 3rd QUARTER EXPENDITURE TRENDS 2007/08-2009/10
HOSPITAL REVITALIZATION GRANT (HRG) EXPENDITURE AS AT 31 DECEMBER 2009
CHALLENGES • Slow construction progress on site • Civil and building contracts delayed at Thabazimbi due to finalization of Environmental Impact Assessment (EIA) • Dependencies within sites have a ripple effect on all other projects due to follow • Musina site changes: from current hospital site, to 2nd site and now ultimately to 3rd site • Musina 3rd Site confirmed in August 2009 but official allocation not yet attained • Determination of specifications and scope of work for corrective work at Jane Furse Hospital
VALUE OF DELAYED PROJECTS(progress dependent on the terminated projects)
MONITORING AND EVALUATION: HRP IMPROVEMENT PLAN • Performance Monitoring and Evaluation: • Resident clerks of works appointed to assist in ensuring performance of contractors per site on a daily basis. • Measurement of construction works to be undertaken and paid for twice per month • Projects monitored closely by DPW and professional teams; and Health PMU and professional teams
IN CONCLUSION • The HRG below targeted Expenditure noted in all components • An HRP Improvement Plan supported a Provincial level (Premier’s Office, Provincial Treasury, the Department and Implementing Agents) implemented as of September 2009 • Dependencies and slow performance of contractors delayed expenditure plan • Projected under spending R40,247due to the above stated reasons