170 likes | 317 Views
FLOW THROUGH WATER TREATMENT SYSTEM USING ALUM & PAM. REEDY CREEK IMPROVEMENT DISTRICT. BRIDGE DEMOLITION PROJECT @ EPCOT WINTER 2000. High Pressure Water Blasting To Remove Concrete Down To Rebar. After Blasting With 15,000 psi Water Jet. Runoff Turbidity Greater Than 300 NTUs.
E N D
FLOW THROUGH WATER TREATMENT SYSTEM USING ALUM & PAM REEDY CREEK IMPROVEMENT DISTRICT
BRIDGE DEMOLITION PROJECT @ EPCOT WINTER 2000
High Pressure Water Blasting To Remove Concrete Down To Rebar
Wood Baffle Boards Skim Large Concrete Debris & Provide Alum Mixing
Runoff Flows Into 1st Cell Of Three Stage Treatment System (Inflow >300 NTU)
1st Stage Treatment: Inflow >300 NTU Outflow 30 NTU
2nd Stage Treatment: Inflow 30 NTU Outflow 17 NTU
Polyacrylamide (PAM) Floc Log Used For Final Polishing (40-50% Turbidity Reduction) & Free Aluminum Binding
Final Discharge Water Sheet Flows Over Grass Berm (Trapping Sediment)Then Into Canal Behind Floating Turbidity Boom
Canal Receiving Water 15 NTU Final Discharge Water 10-12 NTU
Treatment System Performance: System Usage: 15 Days Daily Volume: 80,000 Gallons Total Pumping Volume: 96 Million Gallons Alum Usage: 40 Gal / Day (600 Gal Total) Treatment System Size: 50 x 15 Ft. Turbidity Reduction (NTU): >300 (Inflow) 15 (Outflow) % Turbidity Reduction: 95 % Contractor’s System Cost: < $1,000 Time Lost Due To Non-Compliance: NONE!
Contractor: Hubbard Construction Contact: Jeff Forsythe (407)560-0442