MyFloridaMarketPlace CRB Meeting MFMP 2.0 Upgrade Status March 29, 2007. Agenda Review. Summary status of upgrade Review Project lifecycle review with highlights Review upgrade timeline MFMP 2.0 Go/No go Decision Point Summary MFMP 2.0-Aspire Project Schedule Synchronization
E N D
MyFloridaMarketPlace CRB Meeting MFMP 2.0 Upgrade Status March 29, 2007
Agenda Review • Summary status of upgrade • Review Project lifecycle review with highlights • Review upgrade timeline • MFMP 2.0 Go/No go Decision Point Summary • MFMP 2.0-Aspire Project Schedule Synchronization • Training Review • Testing results • Performance Testing • Migration Process • Overview of MFMP 2.0 migration weekend • Closing
MFMP 2.0 Upgrade – Plan Status Technical Infrastructure Plan Design Build Test Train Deploy Build 4/2/07
MFMP 2.0 Upgrade “Go/No Go” Decision Points Go/No go decision points per the Upgrade Plan established Sept. ’06 and finalized in Oct. ’06: • Can we synchronize schedules for Aspire go-live and MFMP 2.0 upgrade? – (target decision date 1/19/07) • Do the MFMP 2.0 Training Plan and User Acceptance testing results support moving forward with the upgrade (target decision date 3/12/07)? • Do the Performance test results and upgrade migration results (“Dress Rehearsals”) substantiate beginning the final cut over to MFMP 2.0 (target decision date 3/29/07)?
MFMP 2.0 Upgrade “Go/No Go” Decision Point #1 Can we synchronize schedules for Aspire go-live and MFMP 2.0 upgrade? • Decision target date 1/19/07 • Late December announcement Aspire schedule no longer viable • MFMP 2.0 go/no go decision = GO!
MFMP 2.0 Upgrade “Go/No Go” Decision Point #2 Do the MFMP 2.0 Training Plan and User Acceptance testing results support moving forward with the upgrade? • Decision target date 3/12/07 • Training plan supports broad base of agency personnel covering the differences between current version and MFMP 2.0 • results on following pages • User (Functional) Acceptance testing meets exit criteria • results on following pages
MFMP 2.0 Upgrade “Go/No Go” Decision Point #2 - Training • MFMP 2.0 Training • Total of 1925 people trained for the upgrade (as of 3/27/07) • 877 core purchasing and finance specialists trained in 26 agencies • 40 sessions in 10 days of requester training @ 5 locations • 963 requesters trained – number expected to exceed 1,000 • 59 System Administrators trained & 26 acceptance testers • 26 acceptance testers trained • Overall training satisfaction rating is Good+ • The total number of people trained directly by MFMP Project is nearly double the number trained for the initial implementation MFMP 2.0 go/no go decision - Training= GO!
MFMP 2.0 Upgrade “Go/No Go” Decision Point #2 – Functional Acceptance Exit Criteria MFMP 2.0 go/no go decision - UAT = GO!
MFMP 2.0 Upgrade “Go/No Go” Decision Point #3 Do the Performance test results and upgrade migration results (“Dress Rehearsals”) substantiate beginning the final cut over to MFMP 2.0? • Decision target date 3/29/07 • MFMP 2.0 performance testing meets exit criteria • results on following pages • Upgrade migration is accurate and can be completed in the time available • results on following pages
MFMP 2.0 Upgrade “Go/No Go” Decision Point #3 –Performance Testing Summary • Performance Testing • Exit criteria established from historical performance based on the highest productive day over the last Fiscal Year MFMP 2.0 go/no go decision - Performance = GO!
MFMP 2.0 Upgrade “Go/No Go” Decision Point #3 – Migration Test Run Summary • Migration Test Runs (“Dress Rehearsals”) • Five test runs were completed • 3 mock conversions: all programs and verifications to convert the data run to capture initial timings and validate data • 2 full dress rehearsals: full-scale practice runs for the implementation • Results: Starting the migration processes at 6:00 PM Thursday, 3/29 we expect to complete the entire cut-over by 8:00 PM Sunday. • Data verification • Control count totals: verifies the same number of records into the conversion process come out of the process • Run reports before migration on current version and same reports after migration on MFMP 2.0 then compare MFMP 2.0 go/no go decision - Migration = GO!
MFMP 2.0 Upgrade “Go/No Go” Decision Summary MFMP 2.0 go/no go decision = GO!
MFMP 2.0 Implementation Planning • MFMP 2.0 implementation/contingency planning • Readiness checklist • Communication sent on 2/20 to Agency Purchasing and F&A Liaisons • Posted to the toolkit: MFMP 2.0/Deployment section • Communication approach • Updates during the conversion weekend will be provided via 1-866-352-3776 • Emails will be sent at the completion of tasks below in bold green font • MFMP Customer Service Desk will be available 4/2-4/6 from 7:00 AM to 7:00 PM • Overview of migration weekend • 3/29 6:00 PM: Current MFMP shutdown • 3/29 6:00 PM – 3/30 4:00 AM: Final MFMP 1.0 processing & close-out • 3/30 2:00 AM – 3/31 10:30 PM: MFMP 2.0 conversion • 3/31 10:30 PM – 4/1 11:30 AM: MFMP 2.0 environment configuration/Group & Role conversion • 4/1 11:30 AM – 4/1 4:00 PM: MFMP 2.0 application verification • 4/1 5:00 PM: Final production release decision • 4/1 5:30 PM – 4/1 10:00 PM: Production configuration • 4/1 10:00 PM – 4/2 7:00 AM: Production batch cycles • MFMP 2.0 available 7:00 AM Monday, 4/2/07
Contingency Planning – Our Plan B! • Contingency Plans – only if needed • Monday, 4/2 will be used for the implementation of MFMP 2.0 • Project Team management will make decision no later than 4/1 5:00 PM • Email communications will be sent to Purchasing Directors and Finance & Accounting Directors regarding execution of back up plan • BuyerHelp voice response system will be updated • Only if necessary, we will move the go-live date for MFMP 2.0 • 4/9/2007 • Operations would continue on current version • Same transition weekend approach applies – down Thurs after business day and until Monday 4/9/07
What’s Next? • Any closing discussion 0 business days until MFMP 2.0! Thank you!