360 likes | 456 Views
Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005. Beam parameters obtained from the central frequency measurements, averaged over the data obtained from the horizontal and vertical planes. Results of TI8 test.
E N D
Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005
Beam parameters obtained from the central frequency measurements, averaged over the data obtained from the horizontal and vertical planes.
End of civil engineering works in Point 5 (1st February 2005)
Number of quenches to reach 8,33 Tat the first cooldown (560 dipoles)
Magnet Installation • Installation is progressing in sectors 8-1 and 4-5. More than 100 superconducting magnets have been installed. The installation rate must now ramp up to 20 magnets per week (16 dipoles and 4 SSSs) in the next few weeks. • At the end of October, sector 7-8 will be liberated for magnetic installation. From then on there will be no shortage of slots.
Interconnect in sector 8-1: in progress in sub-sectors C and F
Reinstallation of QRL in 7-8 • Sub-sectors A and B (600 m) have been cooled down on Wednesday 14th September. • After the cold tests, the inner triplet will be installed, cooled down and powered whilst the rest of the line is being installed.
First cooldown of 600 m cryogenic LHC line sector 13-14 September 2005 He out Th.screen line LHe line Pump. line He in 20 K line
Conclusions • Main objectives: • terminate installation in February 2007 • first collisions in summer 2007 • The industrial production of standard components is compatible with this objective. • The ramping up of QRL activities and magnet installation is critical to maintain this schedule. • Additional actions have been implemented to ensure proper QRL production and installation rates. • The installation and interconnection of cryomagnets have started in the tunnel. • The commissioning of technical systems will take place in two adjacent sectors in parallel. • Main next actions: • partial test of sector 7-8 in autumn 2005 • commissioning test of the two first sectors (7-8 and 8-1) in summer 2006 • find external collaborators to help with commissioning. => many thanks to INFN for its support !