An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Installation plans from mid 2005 ATLAS overview week Miikka Kotamäki Freiburg, 7th October 2004

  2. General • In the July EB it was decided to start an informal task force to look at in details what can be done to accelerate the schedule in the first 6 months following the insertion of the barrel calorimeter. • The task force had its first meeting 27th of July and since then has met roughly once a week. • The following is a summary of a possible installation sequence worked out in the task force meetings. The sequence covers the period from completion of the BT in July ’05 to the end of the Calorimeter A assembly on the Truck in the beg of ’06. • The sequence has also been implemented in a working schedule. • All the working documents of the task force (including the working version of the schedule) are available on EDMS at:https://edms.cern.ch/document/490947 M. Kotamäki -Installation plans from mid 2005

  3. Starting point • Our starting point is the mechanical completion of the Barrel Toroid in July ’05. By this time: • Barrel Calorimeter is ready, tested with all possible services we can install. • Toroid installation platforms are still in place. • Jacks supporting the BT are still in place. • Some Muon chambers (especially in bottom sectors 12, 13 and 14) are installed. • Some cable trays, Muon rails and brackets of the access gangways have been installed on the coils/warm structure. • Muon access gangways in sector 13 installed. • Cryogenic lines installed in the bottom sector. M. Kotamäki -Installation plans from mid 2005

  4. Barrel Toroid Installation Structures BT status in July ’05. M. Kotamäki -Installation plans from mid 2005

  5. Status of barrel muons when BT mechanically completed 5 4 6 Muon Barrel status in July ’05. 3 7 Sectors 12, 14:- BMF (all)- BOG(6+)- BOF (4) Sector 13:- BOL(6?)- BML(6?) Sectors 2, 8, 10, 16:- BMS (all) 2 8 1 9 16 10 15 11 US USA 13 14 12 M. Kotamäki -Installation plans from mid 2005

  6. From mid July onwards • When the BT is mechanically assembled we move on to a hectic installation period which consists of parallel work almost all over the detector and the cavern. • To simplify the planning of this period we have divided the next ~4 months (from mid July) in 5 short phases that are easier to manage. The length of the phases are from 2 to 4 weeks and they are marked with letters A-E. • For this presentation I have also added 5th phase (F) which was discussed in the last two task force meetings and which covers the period from end Oct ’05 to Jan ’06. M. Kotamäki -Installation plans from mid 2005

  7. Phase A: From mid July to mid August M. Kotamäki -Installation plans from mid 2005

  8. Q1 Q2 U5 r D13 Q3 Q4 Phase A: From mid July to mid August • During this PHASE : • Jacks released • -Central platforms dismounted • -Part of the extended platforms • -BT final survey 6 zones (in phi): - 4 quadrants - 2 vertical sec. M. Kotamäki -Installation plans from mid 2005

  9. Release of jacks and partial removal of platforms Release jacks and remove top pilars Remove central platform and part of extended platforms to give space for the Barrel Cal and to create a gap for services installation at z=0. Release jacks M. Kotamäki -Installation plans from mid 2005

  10. Phase A: What else can be done during this phase? • Mount cable trays on the warm structure, if not yet done. • HS arches during the evening. • Install some cryogenic transfer lines in Q1 and Q2. • Install temporary new scaffolding to access bolting critical positions in Q1, U5, Q2 • Prepare minivans on side A. • Bring in the Solenoid Chimney before we push the Calorimeter in and fix it temporary M. Kotamäki -Installation plans from mid 2005

  11. HS Arches The top part of the arches will be pre-assembled into 3 large sections, and equipped with platforms and cable trays if possible, already on surface. Already installed. M. Kotamäki -Installation plans from mid 2005

  12. Barrel cryogenic lines in top sectors LAr fill line from expansion vessel and N2 lines from the valve box (located next to the expansion vessel) to z=0 will be placed asap. Manual welds at z=0 when calorimeter moved in. LAr fill line LN2 lines (2 per side) each containing internally three lines M. Kotamäki -Installation plans from mid 2005

  13. C A Phase B = Insertion of Barrel Calorimeter, end Aug ‘05 3 zones (in Z): I • During this PHASE : • - Move Barrel Calo inside • Prepare and move in Minivans side C • Side C lower and start Calo end-cap C A C Access scaffolding Minivans Barrel Calo inside, working platforms in place (4x2 minivans) M. Kotamäki -Installation plans from mid 2005

  14. What else can be done during phase B • Finish fixation of Solenoid Chimney & Control Dewar • Remove truck A and install muon elevating platform A • Install phi scaffolding on the surface of the barrel calorimeter • Finish installation of the cable trays • Start connecting up the cooling and vacuum pipes. • Start connecting up the cryogenic lines • Install the muon elevating platform on side C between the Truck and BT. This is a new idea and makes it possible to assemble end-cap calorimeter and install muon chambers in parallel on the same side. The platform has to be installed, operated and accessed above the rail line. • Start installing BT busbars under the HS arches. M. Kotamäki -Installation plans from mid 2005

  15. Muon installation platform On side C the platform is installed between the BT and Truck C. The platform cannot go below the rail level because of the bridge and rail extensions between the BT and Truck. M. Kotamäki -Installation plans from mid 2005

  16. Phase C: From end Aug till mid Sep. M. Kotamäki -Installation plans from mid 2005

  17. Phase C: From end Aug till mid Sep ’05. • We can now start 4 main activities in parallel: • Calo and ID services installation along the Barrel and exit at z=0 • Start first putting in place the radial cable supports at z=0 • Muon Barrel installation • In the present scenario we can install chambers from both ends. Side A platform has access to the full face. Side C platform is put in between the BT and Truck C and has access only to sections above the rail height. Access gangways are installed where possible. • Cryo lines connections + cryo services installation • End-cap Calorimeter C assembly on the Truck M. Kotamäki -Installation plans from mid 2005

  18. Services along the Barrel and exit at z=0 • Cable trays z=0 : First operation. Install all the support structures and z=0 cable trays at z=0 sector by sector in the order 5, 13, 3, 7, 9, 1 • Install pipes from z=0 to cooling units (cal) and distribution racks (ID) on HS and make connections at z=0. • LAr Services: in the order 5,13,3,7,9,1,15,11 • Tile Cal Services: in the order 13,3,7,9,5,1,15,11 • ID Services: in the order 5,13,3,7,9,1,15,11 • Muon Services: install services in top sectors M. Kotamäki -Installation plans from mid 2005

  19. Services along the Barrel and exit at z=0 • -All sectors install cable tray supports • Install pipes and connect them at z=0 • Install calo cables followed by ID cables sector by sector M. Kotamäki -Installation plans from mid 2005

  20. ID services on cryostat flange and along the barrel Total 160 shifts estimated for the installation. Assuming 4 teams and 2 shifts per day on each side -> 1 week per sector, total 8 weeks. M. Kotamäki -Installation plans from mid 2005

  21. Muon Barrel installation, step 1Chambers before removal of the BT top platforms Must wait for 1 monthbefore re-tightening the BT bolts and removing the platforms. Cannot start installing BMS chambers in sectors 4 and 6 before the platforms are removed -> try to do something else in between. BOS chambers: all on normal rails (If simpler install all from side A) BIS & BIL: If possible, insert first 3 chambers per side and park at large Z till services are in place. Can now be inserted from both sides no need to jump over at Z=0. The chambers can be later moved into their final positions without using elevating platform. M. Kotamäki -Installation plans from mid 2005

  22. Muon Barrel installation, step 1 (cont.)Chambers before removal of the BT top platforms Inner layers:- Insert BIL & BIS 3/sect and keep them in parking position (sectors 4 & 6 full) Sectors 2,4,6,8:- BOS M. Kotamäki -Installation plans from mid 2005

  23. Muon gangways in BT • The brackets for the access gangways in the BT coil will be installed where possible as the coil is assembled. • After removing the BT coil jacks, and the barrel calorimeter put into position, the gangways and barrel muons will be installed as the BT assembly platforms are removed. • Prototype platform received from Pakistan. M. Kotamäki -Installation plans from mid 2005

  24. Gangways, platforms and ladders inside BT M. Kotamäki -Installation plans from mid 2005

  25. Connection of Barrel Cryogenic lines • All the cryogenic lines inside BT are already installed while building it up or in phase A. In the same way all the lines along the Barrel Calorimeter up to z=0 are installed already on the Truck. • As soon as the calorimeter is moved inside to its final position we can start connecting up the lines at z=0: • LAr and LN2 lines on top of the cryostat • FT vacuum lines on top • LAr dump line on bottom • Insulation vacuum lines on bottom M. Kotamäki -Installation plans from mid 2005

  26. Goals for phase C At the end of phase C : • All barrel calorimeter cables are installed (but in many sectors still not connected up) • Installation of the ID cables from PP1 to PP3 has started. • All possible BIL,BIS chambers are either in the parking position or in the final position. All BOS chambers in top sectors installed. • The cryo-ring is being connected in sector 5 at Z=0. • Final servicing of BT bolts done. M. Kotamäki -Installation plans from mid 2005

  27. Phase D: From mid Sep till end Sep M. Kotamäki -Installation plans from mid 2005

  28. Muon Barrel installation, step 2Chambers after removal of BT top platforms First step: remove BT top platforms. Then, install BMS chambers in sectors 4 and 6 first after which aim at completing sector 5 asap. BMS chambers in sectors 4 & 6:Will be brought in from Sector 5. Sector 5:As soon as calo & ID services installed at z=0 finish BIL. When BMS in sectors 4 & 6 done install all BML, EIL4 and BOL. Might still need to leave a gap for services at Z=0. Sectors 3 & 7: Install all BOL (possibly on extended rails to leave a gap for services). The first 3 BML chambers could also be installed at this stage but it seems better to wait and install full sectors at one go once the ID services through Muons are done and all BIL chambers installed. M. Kotamäki -Installation plans from mid 2005

  29. Muon Barrel installation, step 2Chambers after removal of the BT top platforms Sectors 4, 6:- BMS installed from 5 Sector 5:-As soon as Calo & ID services installed finish BIL. When BMS in sectors 4 & 6 done, install all BML, EIL4 and BOL- install gangways Sectors 3, 7:- BOL- install gangways 5 4 6 3 7 M. Kotamäki -Installation plans from mid 2005

  30. Endcap flexible cryogenic lines The contractor will continue installing Endcap cryogenic lines as soon as the Barrel cryo lines are installed and connected. M. Kotamäki -Installation plans from mid 2005

  31. Goals for phase D At the end of phase D : • In top sectors 4, 5, and 6 all chambers are installed with their services. • 50% of the ID cables from PP1 to PP3 installed. Probably sectors 5, 13, 3, 7 done • The first 3 BIL chambers in final positions in sectors 5, 13, 3, 7 + the BIS chambers in the neighbouring sectors (full sectors?) • Phi scaffolding removed where possible • ID cabling from PP2 to PP3 done M. Kotamäki -Installation plans from mid 2005

  32. Phase E: ~ October ‘05 M. Kotamäki -Installation plans from mid 2005

  33. Removal of lateral platforms & Muon installation • Lateral platforms provide good access in many areas and should therefore kept in place as long as possible. However, they need to be gradually removed to: • give space for the gangways and chamber installation in lower sectors • give space for the installation of the last BOF/BOG chambers between the feet after which we can put back the HS extensions which the flexible chains in sectors 11 and 15 will be supported from. The chains in turn must be installed before the Muon chamber installation in these sectors can be completed (access still to be sorted out). • After removal of the lateral platforms all the rest of the BOS and BOL chambers can be installed on side A, BOS chambers possibly also on side C. • Chambers in the inner layers are still dependent on the ID services installation and must wait for the installation of the ID services through the gaps in Muons to PP2s. M. Kotamäki -Installation plans from mid 2005

  34. Muon Barrel installation, step 3Chambers after removal of lateral platforms Sectors 10,16:- all BOS from side A Sectors 1 and 9:- BOL Sectors 12 and 14- Rest of the BOF, BOG Sectors 11 and 15- BOL side A only - access to install BIR and BIM chambers still to be sorted out. 1 9 16 10 11 15 14 12 M. Kotamäki -Installation plans from mid 2005

  35. Cable chains in sector 9 M. Kotamäki -Installation plans from mid 2005

  36. Cable chains sectors 11 & 15 The last BT platforms must be removed and the last BOF/BOG chambers installed before the supports on the HS and the cable chains can be installed. M. Kotamäki -Installation plans from mid 2005

  37. Goals for the phase E At the end of phase E : • all the ID cables from PP1 to PP3 installed. • all calorimeter cables connected and tested -> Ready for Barrel cooldown • all BT supports & platforms dismounted • all muon services installed • ~2/3 of the barrel chambers mechanically installed on rails. • endcap flexible chains installation started. • we are ready to move in the end-cap calorimeter C for connection of the services M. Kotamäki -Installation plans from mid 2005

  38. Phase F: from end Oct ’05 to Jan ’06. M. Kotamäki -Installation plans from mid 2005

  39. Phase F: From end Oct ’05 to Jan ‘06 Side A: • Assembly of the calorimeter endcap A • Using muon platform A install chambers where possible Center: • ID cabling through Muons to PP2. • Complete flexible chains installation, first side C then side A • Continue connection of services on muon barrel • Get ready for the testing of the BT. Side C: • Start connecting up Calorimeter C • Push all remaining side C chambers in place (interlinked with PP2 ID cabling) • Insert Monoblock and washers • Start Big Wheels (TGC1) assembly! M. Kotamäki -Installation plans from mid 2005

  40. ID services through Muons to PP2 Six PP2s per side. Current estimate for the workload is 20 shifts per PP2!? M. Kotamäki -Installation plans from mid 2005

  41. TGC1 assembly on side A Muon barrel installation continues in parallel. Elevating platform in front of the Toroid not shown. M. Kotamäki -Installation plans from mid 2005

  42. TGC1 assembly By the completion of the TGC1 assembly the Muon Barrel installation should also be finished, and the elevating platform removed. M. Kotamäki -Installation plans from mid 2005

  43. Feb ’06: Close for Solenoid field mapping • Move endcap calorimeters to run position and bring down the shield discs. • After field mapping re-open and start connecting calorimeter A and continue with 2nd Big Wheel on side C. M. Kotamäki -Installation plans from mid 2005

  44. From Jan ’06 onwards Detailed version available on EDMS at: https://edms.cern.ch/document/380587 Installation schedule version 6.24 summary M. Kotamäki -Installation plans from mid 2005

  45. Summary • “Installation Summer 2004 task force” has worked out a schedule proposal for the 6 months following the completion of the BT. • The schedule is now much more detailed than before, especially on the installation of services. • The main difference in the sequence w.r.t previous version is that on both sides, A and C, the installation of the Muon barrel chambers is done partially in parallel with the End-cap Calorimeter assembly, and on side C the assembly of the first Big Wheel is started when the barrel chambers installation is still going on. • The rest of the schedule has not been discussed in the task force, but I have now scheduled the assembly of all four Big Wheels on side C before lowering End-cap Toroid C. On side A the sequence is in reverse order. • In the schedule all the Big Wheels on side A are assembled before closing the beam pipe (March ’07). However, in case of problems and delays we must be able to assemble the Big Wheels also with the beam pipe closed. M. Kotamäki -Installation plans from mid 2005