An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Utility Coordination Oversight on Design-Build Projects: A New Approach Trunk Highway 169/Interstate 494 Design-Build

  2. Trunk Highway 169/Interstate 494 Design-Build Project This Project Involves: • Reconstruction and reconfiguration of the interchange and adjacent local roads • Reconstruction of segments of Trunk Highway 169 and Interstate 494

  3. Trunk Highway 169/Interstate 494 Design-Build Project Utility Involvement • 17 different Utility • Companies • 3 Separate Cities involved • Estimated $16.5 Million in reimbursable utility relocations • Relocation of telephone facilities from adjacent CO that serves all 3 cities

  4. Utility Coordination on Design-Build Projects Design-Build Contracts • MnDOT’s main goals: • Utility Relocation will NOT cause any delays on Design-Build projects • Accurate location information on installed facilities

  5. Utility Coordination on Design-Build Projects Roles and Responsibilities • Contractor is responsible for project design • Contractor has greater freedom and control to mitigate utility issues • MnDOT Utilities Unit oversees the Design-Build Contractor • MnDOT issues permits, approves individual work orders, accepts plans, and ensures the Design-Build Contractor adheres to the terms of the MUA and the appropriate process

  6. Utility Coordination Oversight on Design-Build Projects Utility Coordination Oversight Role: • Review Design-Build Contractor’s utility work plan • Attend Utility meetings • Individual work order meetings • Weekly Task Force meetings • Facilitate work order negotiations and permits • Reimbursement/Betterment

  7. Utility Coordination Oversight on Design-Build Projects Utility Coordination Oversight Role: • Coordinate the State’s utility permit process for all relocated utility facilities • Review Utility Tracking Report • Monitor utility field activities • Review utility invoices • Contract Compliance

  8. Utility Coordination Oversight on Design-Build Projects Where the information is: • Master Utility Agreement (MUA) • General terms and conditions • Lists authorized representatives for all parties involved • Establishes work order process • Design and Construction Work Orders • Scope of the work • Party to who performs the work • Who is responsible for the cost • Work schedule • Property Rights issues

  9. Utility Coordination Oversight on Design-Build Projects Where the information is con’t: • Utility Data Sheet • Specifically describes the work covered in the work orders

  10. Utility Coordination Oversight on Design-Build Projects Keeping Track of the Information: • Utility Tracking Report • Work Order No. • UDS No. • Design Dates • Construction Dates • Percent Complete • MnDOT Permit No. • Utility Contractor

  11. Utility Coordination Oversight on Design-Build Projects Benefits of Procuring Consultant Services: • Dedicated specifically to project • Remove burden from MnDOT staff • Importance of being on premises • Meet with Design-Build Contractor (OTS) • Work closely with MnDOT Verification Staff • Field inspections • Ability to provide immediate attention

  12. Utility Coordination Oversight on Design-Build Projects Methods of Procuring Utility Coordination Oversight Services: • Project Specific RFP • Establishing an On-Call Contract • Include as a service in Verification RFP

  13. Thank you!Questions?