National LambdaRail Update Dave Jent NLR Layer 2/3 Service Center Indiana University

National LambdaRail Update Dave Jent NLR Layer 2/3 Service Center Indiana University. July 18, 2005. National LambdaRail Update. Installation update Phase 2 Layer 1 Layer 2 deployment Layer 3 deployment Other Credits. Cisco 15808 terminal Cisco 15808 OADM Cisco 15454 terminal

joshua
Download Presentation

National LambdaRail Update Dave Jent NLR Layer 2/3 Service Center Indiana University

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. National LambdaRail UpdateDave JentNLR Layer 2/3 Service CenterIndiana University July 18, 2005

  2. National LambdaRail Update Installation update Phase 2 Layer 1 Layer 2 deployment Layer 3 deployment Other Credits

  3. Cisco 15808 terminal Cisco 15808 OADM Cisco 15454 terminal Cisco 15454 OADM 8 8 4 4 National LambdaRail Update SEA 8 8 POR 8 BOI SYR 8 8 4 4 STA 4 4 NYC 4 4 4 OGD PIT 8 8 8 DEN KAN 8 8 CLE CLE 8 CHI 8 SVL 8 4 8 8 8 SLC 4 4 8 8 WDC 4 8 8 4 RAT LAX RAL 4 8 LAX 8 4 TUL 4 PHO ALB 4 8 4 ATL 4 8 4 DAL 4 ELP 4 4 PEN 4 4 JAC 8 4 4 4 4 4 4 4 4 Level3 fiber WilTel fiber BAT 4 SAA 4 HOU

  4. Cisco 15808 terminal Cisco 15808 OADM Cisco 15454 terminal Cisco 15454 OADM 8 8 4 4 National LambdaRail Update Phase II Layer I Deployment SYR 4 4 4 NYC 4 4 OGD CLE DEN 4 KAN SLC 4 4 WDC 4 4 RAT LAX 4 4 TUL 4 PHO ALB 4 4 4 4 DAL 4 ELP 4 4 PEN 4 4 JAC 4 4 4 4 4 4 4 4 Level3 fiber WilTel fiber BAT 4 SAA 4 HOU

  5. 15808 15808 West East 6509 CRS-1 NLR demarc 15500 15500 15500 Metro and Regional Optical Networks DWDM 10GE or OC192 1GE National LambdaRail Update Phase I PoP Layout

  6. 15454 15454 West East 6509 CRS-1 NLR demarc 15500 15500 15500 Metro and Regional Optical Networks DWDM 10GE or OC192 1GE National LambdaRail Update Phase II PoP Layout

  7. 10GE wave 10GE managed wave Cisco 6509 switch National LambdaRail Update Layer 2 Network Design SEA CHI NYC PIT DEN CLE KAN SVL WDC RAL LAX ALB TUL PHO ATL ELP JAC BAT HOU

  8. Layer 2 Completed and connected via 10GE: Sunnyvale Denver Kansas City Chicago Cleveland Pittsburg Washington DC Raleigh Jacksonville installation this week, Seattle next week Atlanta scheduled for the week of August 1 Tulsa scheduled for the week of August 8, Los Angles scheduled for the week of August 15. Houston and EL Paso scheduled for the week of August 22. Baton Rouge scheduled for the week of August 29. New York City scheduled for the week of Sept 5. Albuquerque scheduled for he week of OC 4. FE's ==== FE"s are in from SNVA to PIT. JAC goes in next week. Atlanta is currently scheduled for the week of August 1. That could push back by up to 2 weeks. WDC is scheduled for the week of Aug 8.

  9. Cisco CRS-1 router 10GE wave 10GE managed wave National LambdaRail Update Layer 3 Network SEA CHI NYC DEN PIT WDC RAL LAX PHO TUL ALB ATL BAT JAC HOU

  10. Layer 3 Denver is complete Chicago is complete 10GE circuit between DEN & CHI up. Seattle scheduled for the week of JUL 25th *Atlanta scheduled for the week of August 1. *Pending schedule adjustment

  11. Layer 3 WDC is scheduled for the week of Aug 8. LAX is scheduled for the week of AUG 15. HOU is scheduled for the week of AUG 22. NYC is scheduled for the week of Sept 5. DC, LA, HOU, NYC are dependent on the Wiltel schedule.

  12. Other • Tom has Layer 1 pricing • NLR Board is working setting prices for L2 and L3 • Anticipate some information soon  • Group B report impact, not, yet • Layer 2/3 and Service Desk have renewed contracts for support of the network and users.

  13. Credits (IU) Caren Litvanyi, Lead Technical Engineer, L2/3 Jon-Paul Herron, Project Manager Grover Browning, Deployment Manager Steve Peck and staff, Service Desk Manager Caroline Carver Jay Duncan Andrew Lee Chris (smokin’ hot) Robb Brent Sweeny Luke Fowler Chris Small Steve Kerby

  14. Credits (CENIC) Sherilyn Evans Director of Technical Services Cindy Abercrombie NOC Manager Chris Costa Darrell Newcomb Heather Sherman

  15. Credits (MCNC) • Mark Johnson • Bonnie Phillips • John Moore • Tommy Jacobson

  16. N L R light the future For more information… NLR puts the control, the power and the promise of experimental Contact Tom West twest@nlr.net NLR: putting the control, the power and the promise of experimental network infrastructure in the hands of our nation’s scientists and researchers.